Expected to be completed in 2025, Hanoi's Ring Road 4 is still in disarray

Hữu Chánh |

Hanoi is proposing to complete the Ring Road 4 parallel road in 2025, but to date, some residential areas have not been cleared to hand over to the project.

According to the reporter of Lao Dong Newspaper, after more than 2 years since the groundbreaking date, the parallel road of Ring Road 4 through Hanoi has been revealed, many of which have been paved with asphalt.

Stretching 58km through the capital, the contractor is mobilizing many machines and personnel divided into many construction teams, speeding up the project's progress.

In package No. 8, the construction of a parallel road through Soc Son district is Me Linh (old), the basic site has been handed over by the locality to the contractor.

Vanh dai 4 Ha Noi da lo dien hinh hai sau hon 2 nam thi cong. Anh: Huu Chanh
The shape of Hanoi's Ring Road 4 has been revealed after more than 2 years of construction. Photo: Huu Chanh

Speaking to Lao Dong Newspaper reporter, Mr. Nguyen Hoai Nam - Head of technical department, Construction Management Board of Ring Road 4 in the Capital Region, Truong Son Construction Corporation - said that up to this point, the contractor consortium has completed about 70% of the construction volume.

Package No. 8 is about 23km long, most of which has been paved with asphalt. For the remaining sections, the contractor is also rushing to deploy.

In addition to the construction of a parallel road, package 8 also requires the construction of 3 overpasses on the route including the Ca Lo River overpass, the Hanoi - Lao Cai railway overpass and the Hau village bridge.

"We have identified this as an important project with strategic regional connectivity, so there is more motivation for construction. Not only completing on schedule, the goal is also to ensure quality and safety" - Mr. Nam emphasized.

According to the plan, package 8 will be completed in September 2025, 3 months earlier than the request of the Hanoi People's Committee.

Phan mat bang cuoi cung duoc ban giao cho goi thau so 8. Anh: Huu Chanh
The final site was handed over to package 8. Photo: Huu Chanh
Cau vuot duong sat thuoc goi thau so 8 dang duoc nha thau trien khai thi cong. Anh: Huu Chanh
The railway overpass under package 8 is being constructed by the contractor. Photo: Huu Chanh

Except for package 8, many sections of the Ring Road 4 parallel road project under packages 9, 10, and 11 have not been cleared to hand over to the construction contractor.

Mr. Nguyen Hoang Hai, Commander of Package No. 9, the construction of the Ring Road 4 parallel road through Dan Phuong and Hoai Duc districts (old) said that the Vinaconex package is responsible for the construction of 3 residential areas that have not yet been handed over the site in O Dien, Hoai Duc and An Khanh communes (new administrative unit).

Of which, 14 households in O Dien commune are demolishing the project but the progress is very slow. 91 households in An Khanh commune have had their compensation and resettlement support policies approved. Currently, the new commune government is completing the remaining work to soon hand over the site to the contractor.

According to Mr. Hai, the biggest problem is the intersection of National Highway 32, when there are still many houses and business shelters on both sides of the road that have not been cleared.

"There are 2 booths of 2 enterprises, but one enterprise has handed over the land to the locality. The remaining enterprises have not taken any action" - Mr. Hai said.

Khu dan cu, lan xuong o nut giao Quoc lo 32 chua duoc ban giao mat bang cho du an Vanh dai 4. Anh: Huu Chanh
Residential areas and sheds at the National Highway 32 intersection have not yet been handed over the land for the Ring Road 4 project. Photo: Huu Chanh

In package No. 11 (section through the old Thuong Tin district), Mr. Tran Viet Son - Commander of the package (Cicenco 4 contractor) said that the residential areas within the project have been cleared.

Currently, the power line through the West Canal (near National Highway 1A) has not been dismantled, along with a pumping station that has not been relocated.

Mr. Son said that the contractor hopes that the locality and related units will soon hand over the remaining site so that the unit can construct synchronously throughout the project.

"If the site is handed over soon, we will simultaneously construct and complete the parallel road in 2025 as directed by Hanoi City" - Mr. Son said.

Hữu Chánh
RELATED NEWS

Voters recommend Hanoi to speed up site clearance for Ring Road 4

|

Hanoi - Voters of Me Linh district (old) recommended that the city speed up the progress of compensation and site clearance for the construction of Ring Road 4 in the Capital region.

Image of more than 20km of Hanoi's Ring Road 4 parallel road about to reach the finish line

|

Hanoi - Package No. 8 - construction of the Ring Road 4 parallel road section through Soc Son and Me Linh districts (old) is expected to be completed in September 2025.

Hanoi speeds up the progress of Ring Road 4, about to build 2 metro lines and 6 bridges across the Red River

|

In the coming time, Hanoi will accelerate the disbursement of public investment capital and speed up the progress of important transport infrastructure projects.

Z121 fireworks inflated prices on social networks

|

Near the Lunar New Year, the appeal of Z121 fireworks is increasing. On groups and "online markets", the price is 3 times higher.

Request to transfer principal after overcharging, teachers revise exam papers

|

Gia Lai - Department of Education and Training proposes to transfer the Principal of Nguyen Van Cu Primary School after reflecting overcharging, teachers arbitrarily amend students' exam papers.

Buses and Metro Line 1 in Ho Chi Minh City free of tickets during Lunar New Year

|

Ho Chi Minh City - Buses and Metro Line No. 1 (Ben Thanh - Suoi Tien) will be free of tickets during some Tet peak days, to serve the travel and entertainment needs of people.

Chain collision between 4 cars on Van Phong - Nha Trang expressway

|

Khanh Hoa - In the early morning of February 8, a multi-vehicle traffic accident occurred on the Van Phong - Nha Trang highway between 4 cars.

Ecotourism, Can Tho orchards are busy welcoming guests near Tet

|

Can Tho - Approaching Tet, tourists choose to go to eco-tourism spots, orchards to play and experience to be close to nature.

Voters recommend Hanoi to speed up site clearance for Ring Road 4

SÓNG HỮU |

Hanoi - Voters of Me Linh district (old) recommended that the city speed up the progress of compensation and site clearance for the construction of Ring Road 4 in the Capital region.

Image of more than 20km of Hanoi's Ring Road 4 parallel road about to reach the finish line

SÓNG HỮU |

Hanoi - Package No. 8 - construction of the Ring Road 4 parallel road section through Soc Son and Me Linh districts (old) is expected to be completed in September 2025.

Hanoi speeds up the progress of Ring Road 4, about to build 2 metro lines and 6 bridges across the Red River

HỮU CHÁNH |

In the coming time, Hanoi will accelerate the disbursement of public investment capital and speed up the progress of important transport infrastructure projects.