Extending the implementation period of the bypass project worth over VND1,800 billion in Dak Lak

BẢO TRUNG |

Dak Lak - The Ho Chi Minh Road project (the section avoiding the East of Buon Ma Thuot) has been extended by the Ministry of Construction until December 31, 2025.

On August 12, Mr. Nguyen Tai Minh - Deputy Director of the Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board informed that packages 3 and 4 of the Ho Chi Minh Road project (the section avoiding the East of Buon Ma Thuot) have been extended by the Ministry of Construction to December 31, 2025.

According to Mr. Minh, up to now, the site clearance work for the main route has reached 99.71%. However, there are still 113 m (equivalent to 0.35 ha) of the section passing through Cuor Dang commune that have not completed site clearance; the second ditch at Km13+203.5 is still stuck at about 120 m.

Regarding the construction progress, the completed volume has reached 84.8%.

The authorities have approved compensation and support plans for 33 households (total of 38 households). Of which, 28 households have received money and handed over construction sites.

"The investor strives to complete the handover of the construction site in August 2025. The project will be handed over and put into use before December 31, 2025," Mr. Minh added.

As reported by Lao Dong Newspaper, the Ho Chi Minh Road Project, the section avoiding the East of Buon Ma Thuot (Dak Lak province) has a total investment of more than VND1,800 billion from the central budget with a length of more than 39km.

The project is invested by the Dak Lak Province Traffic Construction Investment and Rural Development Project Management Board.

However, for more than a year, the project still has 1km (from Km0+000 to Km1+000) that has not been constructed due to land clearance.

This has led to existing roads being damaged with mud, potholes, buffalo holes... greatly affecting the travel and living needs of the people.

BẢO TRUNG
RELATED NEWS

Dak Lak mobilizes people to hand over project land worth over VND1,800 billion

|

Dak Lak - The authorities have mobilized and persuaded many households to hand over the land for early construction, completing the road project worth more than VND1,800 billion.

Many households have not agreed to the draft compensation for a project worth over VND1,800 billion in Dak Lak

|

Dak Lak - Many households have not agreed with the draft compensation at the Ho Chi Minh Road Project, the eastern bypass section through Buon Ma Thuot city worth more than VND1,800 billion.

Reasons for not yet completing site clearance for a project worth over VND1,800 billion in Dak Lak

|

Dak Lak - The authorities have not been able to complete the clearance of 113m of the urban bypass project worth more than VND1,800 billion because many households have not agreed to the compensation plan.

Bich Tuyen's new move when wanting to reduce risks in the lawsuit with Dam Vinh Hung

|

The civil lawsuit between singer Dam Vinh Hung and billionaire Gerard Williams in the US has just had a new development.

The secret inside the huge convoy of sand trucks running from Quang Tri to Hue

|

Quang Tri - Inside the huge tractor-trailers covered with tarpaulins was a huge amount of sand. Despite signs of violating the load, this type of vehicle still circulates successfully on many routes.

Hanoi leaders have directed that the My Dinh ICD dry port project is still slow to be implemented

|

Although the leaders of Hanoi City requested to start construction before June 30, 2025, the My Dinh ICD dry port project is still inactive.

South Korea awaits verdict on arrest of former First Lady

|

The five-hour hearing did not yet reach a final decision on the arrest of former First Lady of South Korea Kim Keon Hee.

A series of headquarters next to Hoan Kiem Lake collected furniture and handed over the site to build a square of more than 2 hectares

|

Hanoi - Some agency headquarters are clearing furniture and equipment, handing over the site to the city to expand the space east of Hoan Kiem Lake.

Kẻ gian cắt trộm cáp ngầm dự án đường giao thông hơn 1.800 tỉ đồng ở Đắk Lắk

BẢO TRUNG |

Đắk Lắk - Kẻ gian liên tục cắt trộm cáp ngầm, thiết bị tại dự án đường Hồ Chí Minh đoạn tránh phía Đông Buôn Ma Thuột, gây thiệt hại cho nhà thầu.

Dak Lak mobilizes people to hand over project land worth over VND1,800 billion

BẢO TRUNG |

Dak Lak - The authorities have mobilized and persuaded many households to hand over the land for early construction, completing the road project worth more than VND1,800 billion.

Many households have not agreed to the draft compensation for a project worth over VND1,800 billion in Dak Lak

THANH QUỲNH |

Dak Lak - Many households have not agreed with the draft compensation at the Ho Chi Minh Road Project, the eastern bypass section through Buon Ma Thuot city worth more than VND1,800 billion.

Reasons for not yet completing site clearance for a project worth over VND1,800 billion in Dak Lak

THANH QUỲNH |

Dak Lak - The authorities have not been able to complete the clearance of 113m of the urban bypass project worth more than VND1,800 billion because many households have not agreed to the compensation plan.