Set the time to hand over the site for the bypass project worth over VND1,841 billion in Dak Lak

PHAN TUẤN |

Dak Lak - The Ministry of Construction proposed that Dak Lak hand over the eastern bypass of Buon Ma Thuot city before May 30 to complete the project on June 30, 2025.

During the project implementation, the Ministry of Construction has sent many documents to the Dak Lak Provincial People's Committee requesting support to speed up the site clearance progress, completing the handover of the entire site to the project before May 15, 2025.

In the past, the locality has resolved some shortcomings and problems such as: The relocation of the T20 power pole at Km32+600 has been completed, and the entire site section through Buon Ma Thuot city has been handed over.

However, there are still 113m sections through Cu M'gar district and locally existing at some drainage ditches through Krong Pac and Cu Kuin districts that have not been completely resolved.

In order to ensure the completion of the project before June 30, 2025, the Ministry of Construction asked the Secretary of the Provincial Party Committee and the Chairman of the People's Committee of Dak Lak Province to continue to pay attention to directing the relevant units of the province to accelerate the site clearance, complete the handover of the entire ground to the project before 30.5.2025.

In particular, focus on implementing a number of contents such as directing the People's Committee of Cu M'gar district to promptly organize the approval of compensation and support plans when the State reclaims land to have a basis for paying people.

Hand over the construction site for 113m of the main route and the area of 2 floodgates (the floodgate on National Highway 14 and the floodgate at Km1+700).

Direct the People's Committee of Krong Pac district to strengthen propaganda, mobilization, and take measures to organize and protect the construction of the remaining 2 households to have a construction site to complete the No. 2 canals at Km13+203.

Direct the People's Committee of Cu Kuin district to promptly organize payment to the people and hand over the construction site for the area of canals No. 5 at Km15+511.

In case the site clearance work of the project continues to be delayed and does not meet the requirements for project completion, the Ministry of Construction recommends that the leaders of Dak Lak province consider handling the responsibilities of related groups and individuals.

By May 30, 2025, if there are still any problems with the site, the Ministry of Construction will consider zoning the project to hand over to the locality for management and completion of investment after the locality has arranged funding sources.

The Ho Chi Minh Road project, the eastern bypass of Buon Ma Thuot city (Dak Lak province) has a total initial investment of more than 1,500 billion VND from the central budget, with a length of more than 39km.

After that, the project increased its capital to more than VND 1,841 billion due to land clearance problems.

PHAN TUẤN
TIN LIÊN QUAN

Enforcing households that have not yet handed over the land for the Bien Hoa - Vung Tau expressway project

|

Dong Nai - The authorities are enforcing households in Long Duc commune, Long Thanh district that have not yet handed over the construction site of the Bien Hoa - Vung Tau expressway.

Mobilizing people to hand over the site of the expressway project through Dong Nai before enforcement

|

Dong Nai - On May 20, the authorities will enforce 12 households in Long Duc commune, Long Thanh district, and clear the land for the Bien Hoa - Vung Tau expressway.

Deadline for handing over the site of 2 billion-dong roads in Tuyen Quang

|

Tuyen Quang is currently implementing 2 routes connecting to Bac Kan and Thai Nguyen, the site clearance progress for the projects is being accelerated.

Many people agree to hand over the site for the National Highway 28B upgrade project

|

Binh Thuan - Many people agree to hand over the construction site for the project to renovate and upgrade National Highway 28B with compensation land price according to state price.

Truck collapsed bridge in Can Tho

|

Can Tho - Currently, the authorities have stretched ropes, installed signs, and instructed people and vehicles to go in other directions.

Calculating school meal tax, experts say that there may be incorrect policies

|

Some schools are required to pay student meal tax. Experts say that this is an internal service activity, and may be being applied incorrectly.

Ngan 98 responds to suspicions of selling poor quality weight loss drugs, authorities intervene

|

DJ Ngan 98 responded to the fact that the weight loss products she sells and advertises are suspected to be of poor quality.

The incident at Song Doc oil and gas field has been controlled

|

The incident at Song Doc mine, off the coast of Southwest Vietnam, has been controlled and has not affected the environment.

Enforcing households that have not yet handed over the land for the Bien Hoa - Vung Tau expressway project

HÀ ANH CHIẾN |

Dong Nai - The authorities are enforcing households in Long Duc commune, Long Thanh district that have not yet handed over the construction site of the Bien Hoa - Vung Tau expressway.

Mobilizing people to hand over the site of the expressway project through Dong Nai before enforcement

HÀ ANH CHIẾN |

Dong Nai - On May 20, the authorities will enforce 12 households in Long Duc commune, Long Thanh district, and clear the land for the Bien Hoa - Vung Tau expressway.

Deadline for handing over the site of 2 billion-dong roads in Tuyen Quang

Việt Bắc |

Tuyen Quang is currently implementing 2 routes connecting to Bac Kan and Thai Nguyen, the site clearance progress for the projects is being accelerated.

Many people agree to hand over the site for the National Highway 28B upgrade project

Duy Tuấn |

Binh Thuan - Many people agree to hand over the construction site for the project to renovate and upgrade National Highway 28B with compensation land price according to state price.