Disbursing 1,100 billion VND for key and dynamic projects in Da Nang

Thu Giang |

Da Nang - According to the Department of Finance of Da Nang City, by July 15, 2025, VND 1,100 billion has been disbursed for key and dynamic projects (equal to 37.5% of the assigned plan).

According to the report of the Department of Finance of Da Nang City, after the merger, the total public investment capital plan for 2025 of the city assigned by the Prime Minister is more than 15,902 billion VND. Of which, Da Nang City (old) was over VND 8,720 billion; Quang Nam province (old) was over VND 7,182 billion.

Da Nang City has assigned a plan higher than the plan assigned by the Central Government of more than VND 17,126 billion, Da Nang City (old) of VND 8,744 billion and Quang Nam Province (old) of more than VND 8,382 billion.

From the beginning of 2025, Da Nang City has allocated a detailed capital plan to units and localities of VND 17,062 billion.

As of July 15, 2025, Da Nang City has disbursed the 2025 public investment capital plan to more than VND 6,227 billion; reaching 35.9% of the plan assigned by the Prime Minister; reaching 33.3% of the plan assigned by the local People's Council.

Regarding the implementation of key projects, creating momentum, the Department of Finance of Da Nang City said that according to Resolution No. 91/NQ-HDND of the Da Nang City People's Council, the capital plan for 2025 to allocate key and dynamic projects is VND 2,935 billion.

Du an cau Quang Da (TP Da Nang). Anh: TTXVN
Quang Da bridge project (Da Nang city). Photo: VNA

By July 15, 2025, key projects had disbursed VND 1,100 billion, equal to 37.5% of the assigned plan. Some projects with high disbursement rates such as Quang Da Bridge and the bridge approach road (71%); Compensation and clearance of Hoa Khanh Nam Industrial Cluster (79%); Coastal Road project connecting Lien Chieu Port (62.3%); Investment in the construction of Lien Chieu Port - Shared infrastructure (43.6%) ...

Da Nang City has inaugurated 8 major projects such as Quang Da Bridge and the bridge approach road, Software Park No. 2 (phase 1), Quang Nam Province Data integration Center; Social apartment for people with revolutionary contributions on Vu Mong Nguyen Street...

In addition, 5 typical projects with large investment capital have been started such as upgrading and renovating 29/3 Park, Renovation of drainage and undergrounding systems for information cables and lighting on 4 inner-city roads; Anti-erosion and sustainable protection of Hoi An coast...

According to the Department of Finance of Da Nang City, in the remaining months of 2025, the unit has advised and proposed to the City People's Committee a list of 22 projects expected to start construction; Da Nang City is expected to complete and put into use 20 projects.

Ms. Tran Thi Thanh Tam - Director of the Department of Finance of Da Nang City - said that to remove difficulties and obstacles, the city has established 9 working groups led by the leaders of the People's Committee of Da Nang City.

Da Nang City also reviewed and promptly transferred capital plans for slow-disbursement projects to supplement other projects with good disbursement capacity and need to speed up progress according to regulations.

Thu Giang
RELATED NEWS

Late at night, hundreds of people are still tirelessly taking the driving test in Ho Chi Minh City

|

HCMC - At 10pm, hundreds of candidates are still waiting for the exam at the Eastern Center, the authorities are on duty all night to ensure the exam is safe and serious.

Big fire in Au Lau Industrial Park in Lao Cai, hundreds of police are approaching the scene

|

Lao Cai - The authorities are trying to approach the scene at Au Lau Industrial Park to put out the fire.

Coach Kim Sang-sik wants U23 Vietnam to improve their experience after winning the championship

|

Coach Kim Sang-sik hopes that the U23 Vietnam players will improve their experience and abilities after winning the U23 Southeast Asian Championship.

It is expected to submit to the Politburo a project to reorganize and streamline mass associations before August 31

|

On the afternoon of July 29, the Central Committee of the Vietnam Fatherland Front held a conference to give comments on the project to reorganize and streamline mass associations assigned by the Party and the State.

U23 Vietnam wins Southeast Asian U23 Championship for the 3rd consecutive time

|

On the evening of July 29, the U23 Vietnam team defeated U23 Indonesia 1-0 to win the 2025 U23 Southeast Asian Championship.

Upgrading the stock market, expanding capital mobilization channels for the economy

|

In order to improve quality and open up the ability to attract large-scale, stable and long-term international investment capital flows for the Vietnamese stock market, Lao Dong Newspaper in coordination with the Ministry of Finance organized a seminar on "Upgrading the stock market, expanding capital mobilization channels for the economy".

Nhà hàng ven biển Đà Nẵng khắc phục sau sự cố xả nước thải xuống bãi tắm tự do

Thu Giang |

Đà Nẵng - Nhà hàng ven biển trên đường Võ Nguyên Giáp đã khắc phục sau phản ánh xả nước thải sang lối đi xuống bãi tắm tự do.

Phường Hải Châu, Đà Nẵng sẽ chi trả trực tiếp trợ cấp bảo trợ xã hội để rút ngắn thời gian

Thu Giang |

Đà Nẵng - Phường Hải Châu đã lập phương án bố trí cán bộ công chức, lập danh sách để chi trả trực tiếp tiền trợ cấp bảo trợ xã hội tháng 7-8.2025.

Phường ở Đà Nẵng bị phản ánh chậm trả tiền trợ cấp bảo trợ xã hội hàng tháng

Thu Giang |

Đà Nẵng - Người dân bức xúc khi chưa nhận được tiền bảo trợ xã hội (BTXH) tháng 7.2025 ở phường Hải Châu.