Slow disbursement, a director was temporarily suspended from his position

Nguyễn Hùng |

Quang Ninh - Due to slow disbursement, the Director of the Ha Long City Construction Investment Project Management Board, Quang Ninh Province, was temporarily suspended from his position from October 1, 2024.

The above decision was made at a meeting of the Standing Committee of the Ha Long City Party Committee, Quang Ninh province, on the progress of disbursement of capital for the 2024 public investment plan on the afternoon of September 30.

Implementing the 2024 public investment plan, Ha Long City strives to achieve a disbursement rate of 50% by June 30, 2024; a disbursement rate of 80% by September 30, 2024; and a disbursement rate of 100% by December 31, 2024.

Accordingly, the city has set out a series of drastic solutions, such as: Requiring investors to make detailed disbursement plans for each project; assigning leaders to be responsible for monitoring the implementation progress and disbursement of each specific project according to the set plan; urging and proactively removing difficulties for each project. At the same time, the city requires investors to review and commit to disbursement progress according to timelines; establishing a working group to speed up the implementation and disbursement progress of programs and projects using public investment capital in 2024; directly inspecting the site to check, grasp the situation, promptly handle difficulties and problems in site clearance, construction organization and disbursement of public investment capital, etc.

However, as of September 30, the city's public investment disbursement has not yet met the set plan. The operation and implementation of tasks by the heads of some departments, offices and units are not resolute, effective, slow in progress, showing signs of fear of responsibility, fear of collision, and facing difficulties... This has affected the overall development of the city.

At the meeting, after listening to opinions from departments, offices and units, the Ha Long Standing Committee determined that the slow disbursement of public investment capital was partly the responsibility of Mr. Le Viet Hai - Director of the City's Construction Investment Project Management Board.

Therefore, the Standing Committee of the Ha Long City Party Committee agreed to the policy for the City People's Committee to immediately implement the procedure for temporary suspension from work in "necessary cases" according to Regulation No. 148-QD/TW dated May 23, 2024 issued by the Politburo on the authority of the head in temporarily suspending the work of subordinate officials in necessary cases or when there are signs of serious violations of Party regulations and State laws.

The temporary suspension of the Director of the City Construction Investment Project Management Board will be implemented from October 1, 2024, to strictly implement Party regulations, working regulations and continue to affirm that there are no forbidden areas, no exceptions to the work responsibilities of Ha Long City's staff.

Nguyễn Hùng
RELATED NEWS

Benchmark scores for Pedagogy majors in Ho Chi Minh City, many majors approach 30 points

|

The benchmark score for Pedagogy majors in Ho Chi Minh City in 2026 continues to be high, with many majors having admission scores close to 30 points.

Hanoi studies traffic infrastructure along 126km of the Red River

|

Hanoi assesses traffic infrastructure on the section of the Red River about 126km long to recline the route, improve elevation and ensure flood drainage safety.

Product matrix for treating erectile dysfunction with "complete cure" commitment

|

Faced with the "matrix" of erectile dysfunction treatment products on the market, doctors warn men not to arbitrarily use the product without examination.

Tiến độ giải ngân gói tín dụng nhà ở xã hội 120.000 tỉ đồng

Phương Anh |

Theo Bộ Xây dựng, đến nay gói tín dụng nhà ở xã hội 120.000 tỉ đồng đã giải ngân được 1.344 tỉ đồng.

Bộ Xây dựng nêu lý do gói 120.000 tỉ đồng giải ngân chậm

ANH HUY |

Bộ Xây dựng cho biết, việc giải ngân gói tín dụng 120.000 tỉ đồng còn chậm bởi lãi suất cao, ít ngân hàng tham gia.

5 cơ quan giải ngân vốn đầu tư công rất thấp

PHẠM ĐÔNG |

Bộ Tài chính cho biết, có 8 cơ quan giải ngân vốn đầu tư công trên mức bình quân của cả nước, 16 cơ quan giải ngân thấp, 5 cơ quan giải ngân rất thấp.