Slow disbursement, a director was temporarily suspended from his position

Nguyễn Hùng |

Quang Ninh - Due to slow disbursement, the Director of the Ha Long City Construction Investment Project Management Board, Quang Ninh Province, was temporarily suspended from his position from October 1, 2024.

The above decision was made at a meeting of the Standing Committee of the Ha Long City Party Committee, Quang Ninh province, on the progress of disbursement of capital for the 2024 public investment plan on the afternoon of September 30.

Implementing the 2024 public investment plan, Ha Long City strives to achieve a disbursement rate of 50% by June 30, 2024; a disbursement rate of 80% by September 30, 2024; and a disbursement rate of 100% by December 31, 2024.

Accordingly, the city has set out a series of drastic solutions, such as: Requiring investors to make detailed disbursement plans for each project; assigning leaders to be responsible for monitoring the implementation progress and disbursement of each specific project according to the set plan; urging and proactively removing difficulties for each project. At the same time, the city requires investors to review and commit to disbursement progress according to timelines; establishing a working group to speed up the implementation and disbursement progress of programs and projects using public investment capital in 2024; directly inspecting the site to check, grasp the situation, promptly handle difficulties and problems in site clearance, construction organization and disbursement of public investment capital, etc.

However, as of September 30, the city's public investment disbursement has not yet met the set plan. The operation and implementation of tasks by the heads of some departments, offices and units are not resolute, effective, slow in progress, showing signs of fear of responsibility, fear of collision, and facing difficulties... This has affected the overall development of the city.

At the meeting, after listening to opinions from departments, offices and units, the Ha Long Standing Committee determined that the slow disbursement of public investment capital was partly the responsibility of Mr. Le Viet Hai - Director of the City's Construction Investment Project Management Board.

Therefore, the Standing Committee of the Ha Long City Party Committee agreed to the policy for the City People's Committee to immediately implement the procedure for temporary suspension from work in "necessary cases" according to Regulation No. 148-QD/TW dated May 23, 2024 issued by the Politburo on the authority of the head in temporarily suspending the work of subordinate officials in necessary cases or when there are signs of serious violations of Party regulations and State laws.

The temporary suspension of the Director of the City Construction Investment Project Management Board will be implemented from October 1, 2024, to strictly implement Party regulations, working regulations and continue to affirm that there are no forbidden areas, no exceptions to the work responsibilities of Ha Long City's staff.

Nguyễn Hùng
RELATED NEWS

Iran announces situation of President Pezeshkian after US airstrike

|

Iran confirms President Masoud Pezeshkian is still safe after a series of airstrikes by the US and Israel.

Two 8th grade female students in Nghe An "arrested" to get married

|

Nghe An - Although the school propagated and prevented it, two 8th grade female students in Na Loi commune were still organized to "take wives" according to local customs.

Hong Phuong speaks out about the scandal of being accused of "borrowing the name" of artist Vu Linh

|

Faced with controversies surrounding being accused of "borrowing the name" of the late artist Vu Linh for artistic activities, singer Hong Phuong has officially spoken out.

Race boat capsizes in Dong Nai

|

Dong Nai - The 2026 Open Boat Race on the Dong Nai River experienced a boat capsizing incident, and athletes were rescued in time.

Prime Minister assigns Acting Minister of Education and Training

|

Prime Minister Pham Minh Chinh assigned Mr. Hoang Minh Son to hold the position of Acting Minister of Education and Training.

Lao Cai Provincial Party Secretary holds the position of Standing Deputy Minister of Agriculture and Environment

|

The Prime Minister receives and appoints Mr. Trinh Viet Hung - Secretary of Lao Cai Provincial Party Committee - to hold the position of Standing Deputy Minister of Agriculture and Environment.

Tiến độ giải ngân gói tín dụng nhà ở xã hội 120.000 tỉ đồng

Phương Anh |

Theo Bộ Xây dựng, đến nay gói tín dụng nhà ở xã hội 120.000 tỉ đồng đã giải ngân được 1.344 tỉ đồng.

Bộ Xây dựng nêu lý do gói 120.000 tỉ đồng giải ngân chậm

ANH HUY |

Bộ Xây dựng cho biết, việc giải ngân gói tín dụng 120.000 tỉ đồng còn chậm bởi lãi suất cao, ít ngân hàng tham gia.

5 cơ quan giải ngân vốn đầu tư công rất thấp

PHẠM ĐÔNG |

Bộ Tài chính cho biết, có 8 cơ quan giải ngân vốn đầu tư công trên mức bình quân của cả nước, 16 cơ quan giải ngân thấp, 5 cơ quan giải ngân rất thấp.