Slow disbursement, a director was temporarily suspended from his position

Nguyễn Hùng |

Quang Ninh - Due to slow disbursement, the Director of the Ha Long City Construction Investment Project Management Board, Quang Ninh Province, was temporarily suspended from his position from October 1, 2024.

The above decision was made at a meeting of the Standing Committee of the Ha Long City Party Committee, Quang Ninh province, on the progress of disbursement of capital for the 2024 public investment plan on the afternoon of September 30.

Implementing the 2024 public investment plan, Ha Long City strives to achieve a disbursement rate of 50% by June 30, 2024; a disbursement rate of 80% by September 30, 2024; and a disbursement rate of 100% by December 31, 2024.

Accordingly, the city has set out a series of drastic solutions, such as: Requiring investors to make detailed disbursement plans for each project; assigning leaders to be responsible for monitoring the implementation progress and disbursement of each specific project according to the set plan; urging and proactively removing difficulties for each project. At the same time, the city requires investors to review and commit to disbursement progress according to timelines; establishing a working group to speed up the implementation and disbursement progress of programs and projects using public investment capital in 2024; directly inspecting the site to check, grasp the situation, promptly handle difficulties and problems in site clearance, construction organization and disbursement of public investment capital, etc.

However, as of September 30, the city's public investment disbursement has not yet met the set plan. The operation and implementation of tasks by the heads of some departments, offices and units are not resolute, effective, slow in progress, showing signs of fear of responsibility, fear of collision, and facing difficulties... This has affected the overall development of the city.

At the meeting, after listening to opinions from departments, offices and units, the Ha Long Standing Committee determined that the slow disbursement of public investment capital was partly the responsibility of Mr. Le Viet Hai - Director of the City's Construction Investment Project Management Board.

Therefore, the Standing Committee of the Ha Long City Party Committee agreed to the policy for the City People's Committee to immediately implement the procedure for temporary suspension from work in "necessary cases" according to Regulation No. 148-QD/TW dated May 23, 2024 issued by the Politburo on the authority of the head in temporarily suspending the work of subordinate officials in necessary cases or when there are signs of serious violations of Party regulations and State laws.

The temporary suspension of the Director of the City Construction Investment Project Management Board will be implemented from October 1, 2024, to strictly implement Party regulations, working regulations and continue to affirm that there are no forbidden areas, no exceptions to the work responsibilities of Ha Long City's staff.

Nguyễn Hùng
TIN LIÊN QUAN

Tiến độ giải ngân gói tín dụng nhà ở xã hội 120.000 tỉ đồng

Phương Anh |

Theo Bộ Xây dựng, đến nay gói tín dụng nhà ở xã hội 120.000 tỉ đồng đã giải ngân được 1.344 tỉ đồng.

Bộ Xây dựng nêu lý do gói 120.000 tỉ đồng giải ngân chậm

ANH HUY |

Bộ Xây dựng cho biết, việc giải ngân gói tín dụng 120.000 tỉ đồng còn chậm bởi lãi suất cao, ít ngân hàng tham gia.

5 cơ quan giải ngân vốn đầu tư công rất thấp

PHẠM ĐÔNG |

Bộ Tài chính cho biết, có 8 cơ quan giải ngân vốn đầu tư công trên mức bình quân của cả nước, 16 cơ quan giải ngân thấp, 5 cơ quan giải ngân rất thấp.

Cựu Chủ tịch FLC và 2 em gái xin giảm án

Việt Dũng |

Trong số 25 người kháng cáo, ông Trịnh Văn Quyết - cựu Chủ tịch Tập đoàn FLC và em gái đều xin giảm nhẹ hình phạt và giảm trách nhiệm dân sự.

Bệnh nhân ung thư hy vọng được thêm thuốc vào danh mục BHYT

Cao Thơm - Phương Anh |

Trước kiến nghị từ cử tri về việc xem xét, cập nhật danh mục thuốc ung thư mới cho bảo hiểm y tế (BHYT), niềm hy vọng đang nhen nhóm trong lòng nhiều bệnh nhân.

Nhật Bản có Thủ tướng mới

Song Minh |

Ngày 1.10, Quốc hội Nhật Bản đã bầu ông Shigeru Ishiba, lãnh đạo Đảng Dân chủ Tự do (LDP) cầm quyền, làm thủ tướng mới của đất nước.

Giá vé máy bay Tết 2025 tăng, đắt nhất gần bằng 1 chỉ vàng

Chí Long |

Trước Tết Âm lịch vài tháng, giá vé máy bay nội địa dịp Tết có xu hướng tăng trung bình khoảng 5-8% so với cùng kỳ năm ngoái.

Bắc Ninh bắt kẻ chống đối xử lý vi phạm môi trường Phong Khê

Trần Tuấn |

Công an TP Bắc Ninh đã bắt khẩn cấp kẻ có hành vi chống đối xử lý vi phạm môi trường ở phường Phong Khê.

Ministry of Construction gives reasons for slow disbursement of 120,000 billion VND package

ANH HUY |

The Ministry of Construction said that the disbursement of the 120,000 billion VND credit package is still slow due to high interest rates and few participating banks.

5 agencies with very low public investment disbursement

PHẠM ĐÔNG |

The Ministry of Finance said that there are 8 agencies that disburse public investment capital above the national average, 16 agencies that disburse low capital, and 5 agencies that disburse very low capital.