Slow disbursement, many projects in Dak Lak are waiting for a time to accelerate

BẢO TRUNG |

Dak Lak - At the beginning of 2026, disbursement of public investment capital in the locality is still slow, many projects, although capital has been allocated, are still waiting for a favorable time to accelerate.

Disbursement rate is very low

In 2026, the Project Management Board for Investment in Construction of Transport and Agriculture Works, Rural Development of Dak Lak province (Board A) was assigned to represent the investor, implementing 22 projects in the province.

In which, there are 12 transportation projects and 10 agricultural and rural development projects with a total capital allocated to March 2026 of more than 3,700 billion VND.

However, to date, the investor has only disbursed more than 100.36 billion VND, reaching about 3.16% of the plan. The capital source in 2025 extended to 2026 with more than 782 billion VND has not yet been disbursed.

Lãnh đạo UBND tỉnh Đắk Lắk thường xuyên đi thực địa, đôn đốc tiến độ các dự án trọng điểm. Ảnh: Tuấn Hải
Leaders of Dak Lak Provincial People's Committee regularly urge the progress of key projects. Photo: Tuan Hai

Some projects invested by Board A are being implemented in 2026, including: Traffic road from Ea Ho to Tam Giang; project to stabilize free migrants in Ea Rot village (Cu Pui commune); inter-district road Krong Nang - Ea H'Leo; pumping station system and Dur Kmal irrigation works (Dur Kmal commune); construction of Cay Sung bridge (Km78+400), Trang bridge...

According to a representative of Board A, the disbursement progress is slow because the capital source for 2026 has just been allocated and is continuing to be supplemented. The capital source extending from 2025 will also only be allocated at the end of February 2026, so the unit is completing procedures for disbursement.

In addition, in January 2026, the unit focused on disbursing capital for 2025; along with the extended holiday in the first quarter, the progress of capital disbursement in 2026 has not reached expectations. Board A said it will overcome this situation in the second quarter.

Một số công trình giao thông lớn tại địa bàn sẽ hoàn thành ngay trong năm 2026. Ảnh: Bảo Trung
Some large transport projects in the area will be completed in 2026. Photo: Bao Trung

Do as far as possible, finalize as far as possible.

Mr. Dang Tho Dan - Head of the Traffic Project Management Department (Department A) said that in the first half of 2026, the unit will focus on completing the Khanh Hoa - Buon Ma Thuot expressway project (section passing through the locality), and at the same time open the route and put into use the eastern bypass of Buon Ma Thuot.

After that, the unit will continue to arrange personnel to implement the remaining projects in 2026. This is an important task with a large workload, requiring the unit to proactively coordinate with local authorities to ensure progress, contributing to the implementation of the province's socio-economic growth goals.

According to Mr. Tran Tien Dong - Director of Board A, immediately after the Lunar New Year holiday, the unit reviewed each project and developed detailed plans according to each time milestone to speed up construction progress.

For large projects with high allocated capital, the Board strengthens coordination with departments, branches and localities to remove obstacles in compensation, resettlement support and site handover to contractors. At the same time, request contractors to focus manpower, equipment, and organize multi-pronged construction to ensure progress.

After completing transitional projects from 2025, the Board will continue to strengthen on-site inspections, urge contractors and closely coordinate with localities to promptly handle arising difficulties.

According to leaders of Board A, accelerating the progress of transport and irrigation projects not only contributes to ensuring the disbursement of public investment capital but also to completing the infrastructure system, promoting sustainable socio-economic development of the province, towards the goal of double-digit growth in the year.

BẢO TRUNG
RELATED NEWS

Disbursed 91%, Lang Son sports project still lacks space

|

Lang Son - The Sports Complex Project has disbursed more than 91% of the 2025 capital plan, but the construction progress is still slow due to site clearance work.

The head must be responsible if public investment capital disbursement is delayed

|

Lang Son - The Provincial People's Committee requests investors and communes and wards to focus on disbursing public investment capital, if progress is delayed, the head is responsible.

Ho Chi Minh City seeks solutions for the situation of excess public investment capital but difficult disbursement

|

Ho Chi Minh City has only disbursed about 70% of public investment capital so far, the situation of "excess capital but not being able to disburse" is something to think about.

Hung Yen disburses more than 31,245 billion VND of public investment capital

|

Hung Yen - In 2025, state budget revenue in Hung Yen exceeded estimates, budget expenditures were tightly managed, and credit continued to grow safely.

US responds to news of Russia providing locations of US warships and aircraft to Iran

|

The Pentagon affirmed that US forces are monitoring the activities of Russia and Iran amid escalating conflict in the region.

Road worth over 1,300 billion VND in Hanoi completed all items in March

|

Hanoi - Ring Road 2.5 project, Dam Hong - National Highway 1A section, 1.6km long, with a total capital of over 1,300 billion VND, will complete all items in March 2026.

Ho Chi Minh City traffic police ambush and film violating motorbikes

|

Ho Chi Minh City - Traffic police deploy ambushes, filming many motorbikes intentionally crossing the railway when red lights and barriers have lowered, posing a risk of traffic accidents.

The mother burst into tears when she first heard her child call "mother" after 3 years of waiting

|

During the days of persistently accompanying her congenitally hearing impaired child, the mother burst into tears when she first heard her child call "mother" after 3 years.

Disbursed 91%, Lang Son sports project still lacks space

Khánh Linh |

Lang Son - The Sports Complex Project has disbursed more than 91% of the 2025 capital plan, but the construction progress is still slow due to site clearance work.

The head must be responsible if public investment capital disbursement is delayed

Khánh Linh |

Lang Son - The Provincial People's Committee requests investors and communes and wards to focus on disbursing public investment capital, if progress is delayed, the head is responsible.

Ho Chi Minh City seeks solutions for the situation of excess public investment capital but difficult disbursement

MINH QUÂN |

Ho Chi Minh City has only disbursed about 70% of public investment capital so far, the situation of "excess capital but not being able to disburse" is something to think about.

Hung Yen disburses more than 31,245 billion VND of public investment capital

Mai Hương |

Hung Yen - In 2025, state budget revenue in Hung Yen exceeded estimates, budget expenditures were tightly managed, and credit continued to grow safely.