Removing site obstacles, promoting the progress of 2 1,500 billion VND bridge projects in Thai Nguyen

Việt Bắc |

Thai Nguyen - Units are focusing on removing site obstacles and accelerating the progress of Quang Vinh 1 and 2 bridge projects.

2 Quang Vinh 1 and Quang Vinh 2 bridge projects in the center of Thai Nguyen province have a total investment of more than 1,500 billion VND, started in early 2025.

According to the design, Quang Vinh 1 bridge has a total length of more than 3.4km, starting point Km0+0.00 at the intersection of Duong Tu Minh road. End point at Km138+118, intersecting with National Highway 17.

The bridge is designed with box girders and prestressed reinforced concrete, combined with steel arches.

Công trường dự án cầu Quang Vinh 1. Ảnh: Việt Bắc
Quang Vinh 1 bridge project construction site. Photo: Viet Bac

Meanwhile, Quang Vinh 2 bridge connecting Quan Trieu ward with Linh Son ward has a total length of about 1.43 km. The sections of the route have different widths, from 27m to 40.5m.

PV's records at the end of May 2026, at the Quang Vinh 1 bridge construction site, dozens of workers and machinery and equipment are being mobilized to deploy construction. Many items of Quang Vinh 1 bridge have gradually taken shape.

The contractor is focusing on constructing foundations, welding steel structures, completing bridge frames and handling technical items according to plan.

And at the Quang Vinh 2 bridge construction site, units are deploying drilling, filling, making foundations, and pressing piles. Many construction teams are organized continuously to ensure the set plan.

According to Mr. Duong Quoc Khanh - Deputy General Director of Investment and Construction Joint Stock Company No. 18, the contractor is mobilizing maximum manpower and equipment, organizing many construction teams to compensate for progress.

However, the biggest difficulty currently is that the ground is not continuous, while early rain and floods directly affect the construction items under the river.

Các đơn vị đang tháo gỡ vướng mắc về mặt bằng để đẩy nhanh tiến độ dự án. Ảnh: Việt Bắc
Units are removing site obstacles to speed up project progress. Photo: Viet Bac

The construction package for the connecting road section 1 also faced many difficulties due to small handover sites and lack of access roads for transporting materials. The realized value only reached about 2.8% of the plan.

According to the investor's assessment, the overall progress of the project is about 10% behind schedule.

According to the Project Management Board for Investment and Construction of Transport and Agricultural Works of Thai Nguyen province, the project has a total recovered area of more than 17.6ha, affecting 491 households and 11 organizations in Quan Trieu and Linh Son wards; of which nearly 200 households must be resettled.

Up to now, site clearance work in Linh Son ward has completed the inventory of almost all affected households. Approving compensation plans for 226 households with a total cost of more than 84.6 billion VND.

However, there are still 31 households that have not been allocated resettlement land.

Meanwhile, in Quan Trieu ward, the progress of site clearance is still slow. The locality has only completed statistics for more than half of the households subject to land acquisition and arranged resettlement for 10/131 households.

Dự án cầu Quang Vinh 2. Ảnh: Việt Bắc
Quang Vinh 2 bridge project. Photo: Viet Bac

Currently, at Quang Vinh 1 bridge, the contractor has cast 32/34 girder slabs. The value of the implemented volume reached more than 192 billion VND, equivalent to over 60% of the contract value.

At Quang Vinh 2 bridge, pile foundation, pile body, approach road and steel structure items are being deployed simultaneously, with a implementation value of nearly 170 billion VND.

The Provincial Traffic and Agricultural Construction Investment Project Management Board is coordinating with localities to focus on removing each difficulty, especially in resettlement and site clearance work.

Việt Bắc
RELATED NEWS

Removing bottlenecks in material supply for key projects in Ninh Binh

|

Ninh Binh - Ninh Binh province requests departments, branches, and localities to focus on removing difficulties in material supply for key projects.

Da Nang removes obstacles to complete 32,000 social housing units

|

Da Nang is promoting the review and recovery of the housing fund used for improper purposes and increasing investment capital to complete the target of 32,000 social housing apartments (NƠXH) by 2030, ensuring social security for low-income people.

10th grade Math exam in Hanoi: Some candidates burst into tears and left the exam room

|

At the end of the Math exam for 10th grade in Hanoi this year, some candidates breathed a sigh of relief, but some also burst into tears and left the exam room.

US attacks ship suspected of drug trafficking again, 3 people killed

|

The US anti-smuggling campaign at sea continues to be controversial as the death toll rises.

Luis Enrique set a record after PSG won the UEFA Champions League

|

Luis Enrique has become the fifth coach in history to win 3 Champions League titles, after PSG defeated Arsenal.

Many rice milling plants accused of causing pollution, functional agencies in Can Tho inspect

|

Can Tho - Functional agencies have inspected many rice milling plants along the Thot Not canal (Co Do commune) to clarify compliance with environmental protection regulations.

Removing bottlenecks in material supply for key projects in Ninh Binh

NGUYỄN TRƯỜNG |

Ninh Binh - Ninh Binh province requests departments, branches, and localities to focus on removing difficulties in material supply for key projects.

Da Nang removes obstacles to complete 32,000 social housing units

Nguyễn Linh |

Da Nang is promoting the review and recovery of the housing fund used for improper purposes and increasing investment capital to complete the target of 32,000 social housing apartments (NƠXH) by 2030, ensuring social security for low-income people.

Nghệ An gỡ vướng, giải quyết chế độ phụ cấp theo Nghị định 126 cho cán bộ các hội

QUANG ĐẠI |

Nghệ An - Tỉnh xây dựng phương án tháo gỡ để xem xét giải quyết phụ cấp công vụ cho cán bộ các hội theo Nghị định 126/2024.