Hanoi completes project to expand roads and underpasses in the first quarter of 2026

SÓNG HỮU |

Hanoi - The project to expand Nguyen Tuan street and build Kim Dong - Giai Phong underpass will be completed in the first quarter of 2026.

The project to renovate and expand Nguyen Tuan street was approved by the old Thanh Xuan District People's Committee in 2018, with a total investment of nearly 400 billion VND.

The project is 720 m long, the starting point intersects with Nguyen Trai street, the ending point reaches alley 162 Nguyen Tuan, the cross-section is expanded to 21 m, including a 15m wide road surface and 2 sidewalks each side 3 m wide.

To implement the project to renovate and expand Nguyen Tuan street, Thanh Xuan district must recover and clear 14,334 m2 of land from 11 organizations and 160 households and individuals.

However, the above-mentioned transportation project could not be implemented according to the initial plan because many households did not agree to hand over the land.

After many times of propaganda and mobilization, by November 2024, the site clearance work for the Nguyen Tuan road expansion project was basically completed.

Local authorities then handed over most of the ground area for contractors to implement the project, setting a goal to complete the project in 2025.

Mot doan duong Nguyen Tuan (Ha Noi) da duoc mo rong, thang 8.2025. Anh: Song Huu
A section of Nguyen Tuan street (Hanoi) has been expanded. Photo: Song Huu

From July 1st, after being operated by the 2-level government, the Nguyen Tuan road expansion project was transferred to Thanh Xuan Ward People's Committee as the investor.

The process of converting local government at 2 levels requires changes in investors and bidding procedures, so some bidding packages have not ensured the initial schedule (bidding packages for relocating electricity systems, information systems...).

Due to having to solve some existing problems as well as difficulties and obstacles, the completion progress of the entire project was postponed to March 2026, instead of 2025 as initially planned.

a
Kim Dong - Giai Phong underpass reveals its shape after more than 3 years of construction. Photo: Song Huu

In the southern area of the city, the progress of the Kim Dong - Giai Phong underpass project is also being accelerated.

The underpass project with a total investment of 778 billion VND is invested by the Hanoi Traffic Construction Investment Project Management Board, started in October 2022.

The project has a total length of tunnel and access road of 890 m in the direction of Ring Road 2.5, of which the closed tunnel is 140 m long, the open tunnel is 320 m long. The section passing through the tunnel is 2 lanes wide 3.5 m/lane in each direction; the section outside the tunnel is 3 lanes wide 3.5 m/lane in each direction.

During the 2026 New Year holiday, the contractor still mobilized many machines and workers to construct the remaining items to bring the project to completion in the first quarter of 2026.

s
The most important items of the project have been basically completed. Photo: Huu Vu

When completed and put into use, the Kim Dong - Giai Phong underpass will contribute to solving traffic congestion at this complex intersection, connecting the Ring Road 2.5, especially the Dam Hong - National Highway 1A section, creating a continuous traffic axis, improving traffic capacity and strengthening connectivity in the Southern Hanoi area, serving socio-economic development.

In addition to the above projects, in 2026, Hanoi will also put into operation a series of ring road projects, including: Ring Road 1, Hoang Cau - Voi Phuc section, Ring Road 2.5, Dam Hong - National Highway 1A section and Ring Road 4 parallel road in the Capital region.

SÓNG HỮU
RELATED NEWS

Hanoi recovers land for 925,000 billion VND project, with a stadium meeting FIFA standards

|

Hanoi - Many communes have begun to implement land acquisition and site clearance to implement the Olympic Sports Urban Area project, with a total capital of about 925,000 billion VND.

Progress of Ring Road 4 parallel road through Hanoi, Hung Yen and Bac Ninh

|

Localities have completed site clearance for the Ring Road 4 project and are focusing on construction, ensuring the set schedule.

Ring Road 4 project receives 100% clean ground, contractor constructs during New Year's Day

|

Hanoi - Many engineers and workers postpone New Year holidays to stick to the construction site, accelerating the progress of the Ring Road 4 parallel road project in the Capital region.

9th Hour No. 209: The Unwilling Child - Part 1

|

Hour 9 - Being absolutely trusted by his wife, the husband calmly cheated. When the third person demanded his status, how would he handle it?

Gia Lai is proposed to pilot the socialist ward model

|

Gia Lai - Head of the Central Propaganda and Training Commission Trinh Van Quyet proposed that the province study selecting Hoai Nhon Bac ward to pilot the socialist ward model.

Following the people who sell PNJ diamonds

|

Ho Chi Minh City - PNJ's regulations make "the rich also cry" because they suddenly become unwilling "creditors" for their own diamonds.

Landslide on National Highway 4D to Sa Pa, Lao Cai traffic police cordon off dangerous areas

|

Lao Cai - Prolonged heavy rain has caused landslides on many locations on National Highway 4D to Sa Pa, soil and rocks overflowing onto the road surface, causing danger.

Hanoi recovers land for 925,000 billion VND project, with a stadium meeting FIFA standards

SÓNG HỮU |

Hanoi - Many communes have begun to implement land acquisition and site clearance to implement the Olympic Sports Urban Area project, with a total capital of about 925,000 billion VND.

Progress of Ring Road 4 parallel road through Hanoi, Hung Yen and Bac Ninh

SÓNG HỮU |

Localities have completed site clearance for the Ring Road 4 project and are focusing on construction, ensuring the set schedule.

Ring Road 4 project receives 100% clean ground, contractor constructs during New Year's Day

SÓNG HỮU |

Hanoi - Many engineers and workers postpone New Year holidays to stick to the construction site, accelerating the progress of the Ring Road 4 parallel road project in the Capital region.