The Hanoi Ring Road 4 project is about 59.2km long, passing through 17 wards and communes with a total recovered land area of 800.15ha and 9,039 graves that need to be moved.
Up to now, after 3 years and 2 months of implementation, wards and communes have completed the construction of 13/13 resettlement areas, completed land acquisition, site clearance, tomb relocation, and surface underground construction relocation to ensure progress.


Recorded by Lao Dong Newspaper reporters at the construction site of package No. 9 - building the parallel road of Ring Road 4 section passing through Hanoi in the early days of 2026, the construction atmosphere is extremely urgent.
Package No. 9 - construction of the Ring Road 4 parallel road has a total length of more than 20km, undertaken by Vietnam Import-Export and Construction Joint Stock Corporation (Vinaconex) contractor.
This is the largest bidding package for the Ring Road 4 parallel road in the Capital region section passing through Hanoi.



Talking to Lao Dong Newspaper reporters, Mr. Nguyen Hoang Hai - Commander of package No. 9 said that at the end of December 2025, localities have handed over the entire remaining land area to the contractor.
Time is running out, the contractor encourages engineers and workers to stick to the project site during the New Year holiday. Everyone unanimously puts aside the holiday and shares the determination to accelerate the project progress" - Mr. Hai said.
Up to now, the bidding package constructed by Vinaconex has reached about more than 80% of the workload. The contractor is committed to completing the bidding package in June 2026 according to the direction of Hanoi city.


At package No. 8, a representative of Truong Son Corporation said that up to this point, the contractor has completed about over 90% of the construction volume.
The section about 13km long is expected to be basically completed before the Lunar New Year, exceeding the set schedule.
Similarly, package No. 10 and package No. 11 are also being implemented simultaneously by contractors with many construction teams, ensuring the project progress.
Regarding the construction progress of the Ring Road 4 parallel road through Hanoi city, the Hanoi Traffic Construction Investment Project Management Board said that about 35/53km of asphalt concrete has been constructed.
To date, output has reached about 3,575/4,205 billion VND (about 85%), basically completing the entire parallel road in the second quarter of 2026.

For component project 3 - investing in the construction of the expressway according to the public-private partnership (PPP) method, investors are focusing on organizing the construction of main items, including Hong Ha, Me So, Hoai Thuong bridges and elevated bridge sections on the route.
During the implementation process, some technical contents have been reviewed and adjusted to ensure compliance with planning, optimizing traffic connectivity and exploitation efficiency.
According to the Project Management Board, investors are focusing resources, striving to accelerate construction progress, complete the main route before the APEC Conference in 2027, and closely follow the direction of the Government and the Project Steering Committee.