Hanoi is about to hand over enough land, 2 billion-dollar bridges across the Duong River will be completed next year

CHÁNH TIẾN |

Hanoi - In the fourth quarter, the locality will hand over the site to the investor to build 2 road and railway bridges across the Duong River, completing the project in 2026.

According to the reporter of Lao Dong Newspaper, after more than 2 years of construction, some items of the Duong River Waterway Upgrade Project, with an investment capital of nearly VND1,850 billion (including a railway bridge and a road bridge) have been revealed.

Mr. Mai Xuan Tan - Director of the Duong River Waterway Transport Upgrade Project (Relance Project Management Board, Ministry of Construction) said that the road bridge is currently stuck with the entire road surface on both sides of the bridgehead in Viet Hung ward and Phu Dong commune, so construction is only taking place under the river.

"The contractor is implementing the T3 and T4 tower items under the river and waiting for the site to construct on the shore" - Mr. Tan said.

s
The road bridge is 382m long, combined with cable-stayed, 18.5m wide, with a clearance under the bridge of 4.75m. Photo: Chanh Tien
s
s
The road bridge over the Duong River is under construction. Photo: Chanh Tien

For the railway bridge, the construction unit has completed the installation of 2 main girders and temporarily suspended construction from May to the end of October to ensure regulations on the Law on Dikes during the rainy and stormy season. Therefore, the bypass beams will be implemented from November.

According to Mr. Tan, the progress of the railway bridge depends on the road bridge. When the road bridge is opened, the railway bridge will be dismantled and moved to the new bridge.

s
The railway bridge and approach road are 1km long, about 16.5m upstream from the old Duong bridge. Photo: Chanh Tien
s
The railway bridge has completed the installation of 2 main girders. Photo: Chanh Tien

The Duong River waterway upgrade project has a total land use area of about 4.96 hectares involving more than 140 households in Viet Hung ward and Phu Dong commune. Construction started in July 2023, but to date, the investor has only received only 8% of the site from the locality.

Speaking to Lao Dong Newspaper reporter, Mr. Nguyen Van Thuyet - Vice Chairman of Phu Dong Commune People's Committee said that he had assigned the Commune Infrastructure - Investment Project Management Board (PMU) to develop a site clearance plan.

Up to now, the locality has completed the investigation, measurement, and inventory of 92 households; of which, 47 plans have been listed and established.

For the remaining, the Project Management Board is asking for data on population, household registration from the police agency and land origin of the Department of Economics - Infrastructure and Urban Areas to draft a compensation, support and resettlement plan.

For the 72 households assigned to resettlement, the People's Committee of Phu Dong commune worked with the People's Committee of Thuan An commune to agree on resettlement locations. It is expected that in October, the commune will approve about 40 - 50% of households assigned to resettlement.

"Regarding policies and regimes, we always ensure the rights of people according to legal regulations, provide maximum support so that households whose land is recovered can receive a satisfactory compensation and have better living conditions in their new homes" - Mr. Thuyet emphasized.

s
The land on the Phu Dong commune side has not been cleared. Photo: Chanh Tien
s
Similar to Viet Hung ward, the site has not yet been handed over to the project investor. Photo: Chanh Tien

The leader of Phu Dong Commune People's Committee said that Gia Lam District (old) had previously proposed that the city assign resettlement to the old Yen Vien commune. However, the public investment plan to build this resettlement area will be implemented in the period of 2026 - 2028, which leads to delays in the site clearance of the Duong River waterway upgrade project.

Recently, the city has resolved the problem when approving the transfer of Yen Vien resettlement area to the resettlement area in Thuan An commune (old Kim Son commune). Up to now, the site for resettlement allocation has been guaranteed.

"According to the plan, in October, the commune will hand over at least 60% of the site and will hand over the remaining site by the end of 2025 for the investor to implement the project" - Mr. Nguyen Van Thuyet shared.

s
It is expected that the new road and railway bridge across the Duong River will be completed in 2026. Photo: Chanh Tien

According to Mr. Mai Xuan Tan - Director of the Duong River Water Transport Upgrade Project, the locality's delay in handing over the site for about 8 months prevented the project from reaching the finish line in 2025 as originally planned.

With the plan to hand over the site in the fourth quarter of 2025, the project will be delayed until next year. Currently, the Railway Project Management Board is preparing a report to the Ministry of Construction to adjust the project progress to December 2026.

CHÁNH TIẾN
RELATED NEWS

finalizing the completion time of 2 road and railway bridges across rivers in Hanoi

|

Hanoi will complete 2 road and railway bridges across the Duong River, with a total investment of nearly VND 1,850 billion by 2026.

Hanoi is slow to hand over the site, Duong River bridge delays progress

|

Hanoi's delay in handing over the site has hindered the progress of the Duong River bridge project, even though the railway industry has made 10 requests.

Man City, Tottenham and Arsenal win tickets to round 4 of the English League Cup

|

In the early morning of September 25 (Vietnam time), the series of matches of the 3rd round of the English League Cup witnessed easy victories of the "big guys" such as Man City, Tottenham and Arsenal.

lock all mobile subscribers without identified owners in September

|

The Ministry of Public Security emphasizes the requirement to complete the lock for mobile subscribers who have not identified their own owners, immediately eliminating the need for unnecessary certified copies.

Suspect arrested for stabbing Vietnamese female worker to death in Singapore after noisy controversy

|

On September 24, Singaporean police arrested a 66-year-old man for stabbing a Vietnamese woman to death during a noisy controversy in an apartment building.

The predecessor of storm No. 10 is getting stronger every day, approaching Vietnam, easily causing overlapping floods

|

Right after storm No. 9 Ragasa, the East Sea is preparing to welcome storm No. 10 Bualoi, which is now at the level of a severe storm.

Cử tri Hà Nội kiến nghị sớm xây cầu qua sông Đà kết nối tỉnh Phú Thọ

Sóng Hữu |

Hà Nội - Cử tri đề nghị Quốc hội, Chính phủ sớm đầu tư xây dựng cầu Tu Vũ nối Hà Nội - Phú Thọ, thúc đẩy phát triển kinh tế - xã hội khu vực phía Tây Thủ đô.

finalizing the completion time of 2 road and railway bridges across rivers in Hanoi

CHÁNH TIẾN |

Hanoi will complete 2 road and railway bridges across the Duong River, with a total investment of nearly VND 1,850 billion by 2026.

Hanoi is slow to hand over the site, Duong River bridge delays progress