Hanoi is slow to hand over the site, Duong River bridge delays progress

Chánh Tiến |

Hanoi's delay in handing over the site has hindered the progress of the Duong River bridge project, even though the railway industry has made 10 requests.

Many items have taken shape

In July 2023, the Ministry of Transport (now the Ministry of Construction) coordinated with the Hanoi People's Committee to start the Duong River waterway upgrade project. The project includes a railway bridge and a road bridge, replacing the current Duong bridge.

The project has a total investment of VND 1,848.62 billion, of which the cost of site clearance (GPMB) for phase 1 is VND 650.8 billion from the State budget, assigned to the Railway Project Management Board (Ministry of Construction) as the investor.

The road bridge project is 382m long, combined with cable-stayed, 18.5m wide, with a clearance under the bridge of 4.75m. The starting point is at the old Duong bridge intersection on Ngo Gia Tu street (Viet Hung ward), the end point is at the intersection between Ha Huy Tap street and Phan Dang Luu street (Phu Dong commune), about 100m downstream from the old Duong bridge.

The railway bridge and approach road are 1km long according to the existing railway route, about 16.5m upstream from the old Duong bridge, coinciding with the investment location for the construction of Hanoi urban railway line No. 1. The bridge has 6 steel girder spans and a 280m long steel truss, built to ensure a railway with a gauge of 1,000mm and 1,435mm; designed speed of 80km/h.

According to records in mid-September 2025, some project items have taken shape after more than 2 years of construction.

Speaking to Lao Dong Newspaper reporter, Mr. Mai Xuan Tan - Director of the Duong River Waterway Transit Upgrade Project (under the Railway Project Management Board) - said that regarding the construction of the road bridge, the contractor is implementing the T3 and T4 tower items under the river and waiting for the site to be constructed on the shore.

For the railway bridge, the contractor has completed the installation of 2 main girders and temporarily suspended construction from May to the end of October to ensure regulations on the Law on Dikes during the rainy and stormy season. Therefore, the bypass beams will be implemented from November. "The progress of the railway bridge depends on the road bridge. When the road bridge is opened, the railway bridge will be dismantled and moved to the new bridge" - Mr. Tan said.

10 requests for Hanoi to hand over the site soon

According to the leader of the Railway Project Management Board, the Duong River Waterway Transport Upgrade Project has a total land use area for land acquisition and clearance of about 4.96ha/141 households (Viet Hung ward about 3.33ha/55 households; Phu Dong commune about 1.63ha/86 households).

In recent times, the Railway Project Management Board has been very proactive, actively coordinating and working with relevant units to speed up the progress of site clearance. However, up to now, the project has only been handed over the land within the existing railway, public land is the existing Duong Riverbed area and 16/141 households in the dyke safety corridor on the Viet Hung ward side (about 0.4/4.96ha, reaching about 8%); the remaining volume of land clearance is very large (accounting for over 92%), and the relocation of technical infrastructure works has not been carried out.

"The local handover progress has been delayed for about 8 months, while the Railway Project Management Board has sent documents to Hanoi City 10 times with the hope of having the site soon. At the same time, the Ministry of Construction has also sent documents to the Hanoi People's Committee 3-4 times, however, up to now, the investor has not yet received the site for construction" - Mr. Tan said, emphasizing that the delay in handing over the site not only hinders the project's progress but also causes waste in public investment.

According to Mr. Tan, the latest information received by the Railway Project Management Board is expected to be handed over the site in early October 2025, and the project will be extended to 2026. Currently, the Railway Project Management Board is preparing a report to submit to the Ministry of Construction to adjust the project progress to December 2026.

Chánh Tiến
RELATED NEWS

Land to expand to 5 wards in Hanoi is about to be handed over

|

Hanoi - In September-October, the investor will hand over part of the site to the contractor to construct the project to upgrade and expand Linh Nam road through 5 wards.

A series of headquarters next to Hoan Kiem Lake collected furniture and handed over the site to build a square of more than 2 hectares

|

Hanoi - Some agency headquarters are clearing furniture and equipment, handing over the site to the city to expand the space east of Hoan Kiem Lake.

Speed up procedures to receive site handover to start construction of the Trade Union social housing project

|

Vinh Long - The Vietnam General Confederation of Labor's Trade Union Project Management Board is speeding up procedures to receive site handover to start social housing projects in Dong Thap, Vinh Long and Bac Ninh.

Opportunity to form a 3-party commitment from the Workers' Forum for the Environment

|

Workers for the environment are an opportunity to form a commitment to three parties: State - Enterprise - Employee.

Information on personnel work of the 1st Congress of the Vietnam Fatherland Front Party Committee and Central organizations

|

Regarding personnel work, competent authorities will appoint the Party Executive Committee of the Fatherland Front and Central organizations after the 14th National Party Congress.

Proposal to calculate taxes on YouTuber and TikToker's revenues from fans

|

The Hanoi People's Committee proposed to add revenue from voluntary fan donations to YouTubers, TikTokers, ... subject to personal income tax.

Vingroup is in the Top of the Best Companies in the World 2025 voted by Time

|

Vingroup was honored by Time in the Top 1,000 best companies in the world in 2025, the first and only Vietnamese enterprise to make this list.

The blue-plate car entering the prohibited road in Hue belongs to a Medical Center in Quang Tri

|

Quang Tri - Bo Trach Regional Medical Center confirmed that the blue-plate car entering the prohibited road in Hue City on September 17 was the unit's vehicle.

Land to expand to 5 wards in Hanoi is about to be handed over

SÓNG HỮU |

Hanoi - In September-October, the investor will hand over part of the site to the contractor to construct the project to upgrade and expand Linh Nam road through 5 wards.

A series of headquarters next to Hoan Kiem Lake collected furniture and handed over the site to build a square of more than 2 hectares

SÓNG HỮU |

Hanoi - Some agency headquarters are clearing furniture and equipment, handing over the site to the city to expand the space east of Hoan Kiem Lake.

Speed up procedures to receive site handover to start construction of the Trade Union social housing project

Thành Nhân |

Vinh Long - The Vietnam General Confederation of Labor's Trade Union Project Management Board is speeding up procedures to receive site handover to start social housing projects in Dong Thap, Vinh Long and Bac Ninh.