Shabby scene at slow-progress project
The project information board is obscured by weeds, the corrugated iron fence surrounding the land area shows many graffiti and advertising leaflets pasted all over. Inside the land area, weeds grow lushly, causing unsightliness. This is the reality recorded by reporters at the land area implementing the primary school project of Van Phu - Trung Kinh Investment Co., Ltd. at address No. 177, group 51 Trung Kinh street, Yen Hoa ward.
The project has been delayed for many years because the investor and residents of Home City Apartment have not found common ground.
According to Home City residents, when buying this project, the investor committed to selling the apartment at 177 Trung Kinh address. However, for many years, residents have had to go by borrowed walkways behind the building. 177 Trung Kinh walkway - the only path that meets fire prevention and fighting conditions is restricted by the investor, only bicycles and motorbikes are allowed.
The investor's announcement that it will start the school construction project in the land area in front of the apartment building, narrowing the road leading to the building, makes residents worried about not ensuring fire safety.
Located in the "golden land" of Viet Hung ward - right opposite Tasco Mall shopping center, the Viet Phuong shopping center, office and supermarket construction project has also been behind schedule for many years.
It is known that this project was granted a Construction Permit by the Hanoi Department of Construction in July 2020. In December 2020, Long Bien District People's Committee issued Decision No. 25/QD-XPVPHC sanctioning Viet Phuong Joint Stock Company as the project investor for violating regulations in the field of construction.
Not far away, the Trade - Display Area of products and general services at No. 2 Ngo Gia Tu street (Viet Hung ward) is also in a state of corrugated iron fence, closed and silent.
These are 3 of the 300 projects on the list of projects using non-budget capital that are slow to implement in Hanoi City.
Promoting the progress of a series of slow-progress projects
Hanoi City People's Committee has just issued a notice on urgently completing investment procedures, planning, land, construction and accelerating the progress of projects using non-budget capital with slow land use in Hanoi City.
According to the content of the notice, the City People's Committee requests investors implementing 300 land-using projects in the city to proactively review all legal documents of the project; urgently contact and coordinate with departments, branches, commune and ward People's Committees to complete procedures on investment, planning, land, construction, site clearance according to regulations; supplement complete dossiers and documents as required by competent authorities to ensure completion of procedures within no more than 2 months from the date of receiving complete dossiers.
Along with that, focus financial resources, human resources, and equipment to implement the project according to the approved schedule. For projects that have met the conditions for commencement, urgently organize commencement in August 2026; for projects that are undergoing site clearance work, proactively coordinate with the People's Committees of communes, wards and city departments and branches to complete within a period of no more than 3 months for eligible cases.
In case investors do not contact to carry out procedures; do not coordinate in the process of resolving dossiers; do not implement the committed progress; do not have sufficient capacity; do not implement or continue to delay project implementation, delay land use without objective reasons; or have been extended or adjusted the progress many times but still do not rectify, the City People's Committee will direct relevant agencies to review and complete project recovery dossiers and land recovery according to the provisions of law.