Two key expressways through Khanh Hoa speed up to the finish line

Bình Quý |

The two major expressway projects passing through Khanh Hoa are being accelerated by contractors, many items are close to the completion mark according to the Government's plan.

According to the report of Khanh Hoa Provincial People's Committee, component project 1 of Khanh Hoa - Buon Ma Thuot Expressway is 31.5km long, with a total investment of VND 5,333 billion, invested by the Provincial Agricultural and Traffic Construction Investment Project Management Board.

The total site clearance area of about 228.17 hectares has been 100% handed over to the investor for implementation.

To date, the value of construction output has reached VND2,037 billion (equivalent to 56.28% of construction contracts).

In particular, the first 20km section from National Highway 1 to National Highway 26 is included in the plan of 3,000km of expressway to be completed before the end of 2025, which is being increased in human and material resources to reach the finish line before December 19, 2025.

The remaining sections are constructed in 3 shifts, 4 teams, striving to complete the entire route by 2027.

Component project 2 (37.9km long, Ministry of Construction's managing agency) and Component project 3 (48.1km long, Dak Lak Provincial People's Committee's managing agency) are also being accelerated by contractors, ensuring completion and putting into operation from the beginning of 2027.

Meanwhile, the Van Phong - Nha Trang Expressway project has a total investment of VND 11,808 billion managed by Project Management Board 7 (Ministry of Construction). From April 19, the last 70.35km of the route has been put into operation.

Currently, there are still 13km of the first section of the route (from Co Ma - National Highway 1 intersection to Van Gia - National Highway 1 intersection), contractors are mobilizing maximum human resources, working overtime, striving to complete the main items before August 27 and are expected to hand over and put into operation before September 2.

On the morning of August 18, a working group of the National Assembly led by Mr. Vu Hong Thanh - Vice Chairman of the National Assembly inspected the Khanh Hoa - Buon Ma Thuot Expressway Project and the Van Phong - Nha Trang Expressway Project.

At the inspection, Mr. Vu Hong Thanh requested investors and construction units to continue to remove obstacles related to site clearance, conversion of forest land use purposes... to speed up progress in accordance with the direction of the Central Government.

In particular, the first 20km of the Khanh Hoa - Buon Ma Thuot Expressway Project must be completed by the end of this year under the direction of the Prime Minister.

Bình Quý
RELATED NEWS

Khanh Hoa soon establishes Trade Unions in qualified communes and wards

|

Khanh Hoa - Deputy Secretary of the Provincial Party Committee, Chairman of the Vietnam Fatherland Front Committee of Khanh Hoa province Pham Van Hau chaired a meeting of the Standing Committee of the Vietnam Fatherland Front Committee of the province.

Handing over the Resolution of the Khanh Hoa Provincial People's Council on personnel for leadership of Truong Sa Special Zone

|

On the afternoon of August 12, a conference was held in Khanh Hoa to implement the Resolution of the Provincial People's Council on personnel work in Truong Sa Special Zone.

Completing the institution on labor, wages and social insurance

|

For the 2025-2030 term, the Party Committee of the Ministry of Home Affairs has identified a number of key tasks, including perfecting labor institutions, wages, and social insurance.

Appointing 2 Deputy Departments of the Central Propaganda and Mass Mobilization Commission

|

HCMC - Ms. Pham Thu Huong and Mr. Tran Quoc Phuong Duy were appointed Deputy Directors of the Department of Localities 3 - Central Propaganda and Mass Mobilization Department.

Admiring the special vehicles of the police force participating in the A80 parade

|

Hanoi - The special vehicles block of the police force is practicing hard, ready to carry out the A80 parade mission.

End of the illegal solicitation of foreign currency exchange at Lao Cai International Border Gate

|

Lao Cai - After the authorities took action to handle and propagate, the illegal exchange of foreign currency has gradually limited.

The Ministry of Home Affairs proposes to rate civil servants according to KPI

|

The Ministry of Home Affairs proposes to evaluate the performance of tasks (KPI) for civil servants holding leadership and management positions.

Secretary of the Party Committee of a commune in Dak Lak will livestream to promote and support farmers selling durian

|

Dak Lak - The Secretary of the Commune Party Committee will livestream selling durian to help consume products and promote local agricultural products.

Khanh Hoa soon establishes Trade Unions in qualified communes and wards

Phương Linh |

Khanh Hoa - Deputy Secretary of the Provincial Party Committee, Chairman of the Vietnam Fatherland Front Committee of Khanh Hoa province Pham Van Hau chaired a meeting of the Standing Committee of the Vietnam Fatherland Front Committee of the province.

Handing over the Resolution of the Khanh Hoa Provincial People's Council on personnel for leadership of Truong Sa Special Zone

Hữu Long |

On the afternoon of August 12, a conference was held in Khanh Hoa to implement the Resolution of the Provincial People's Council on personnel work in Truong Sa Special Zone.

Khánh Hòa tạm ngưng xử lý vi phạm giao thông qua hệ thống điện tử để nâng cấp

Hữu Long |

Khánh Hòa - Việc tiếp nhận và xử lý vi phạm trật tự an toàn giao thông trên hệ thống điện tử sẽ tạm ngưng để cơ quan chức năng nâng cấp.