On August 31, according to information from investors of the Bien Hoa - Vung Tau expressway projects, Ho Chi Minh City Ring Road 3 and Long Thanh airport, thousands of personnel and machinery are actively constructing through the September 2 progress race.
According to the Dong Nai Province Investment and Construction Project Management Board, the investor of Component Project 1, Bien Hoa - Vung Tau Expressway and the investor of Component Project 3, Ho Chi Minh City Ring Road 3; and according to Project Management Board 85, the investor of Component Project 2, Bien Hoa - Vung Tau Expressway, the consortium of contractors is mobilizing more than 2,000 human resources and machinery to focus on roadbed construction, crushed stone supply, concrete pouring, and bridge completion.
Due to the slower progress of many packages in these projects compared to the plan, the investor requires contractors to increase human resources and machinery in the coming time, speeding up the construction of "3 shifts, 4 teams".
Meanwhile, according to Vietnam Airports Corporation (ACV), Long Thanh airport is simultaneously implementing packages, units mobilizing nearly 14,000 human resources and about 3,000 machines to organize hundreds of construction teams.
In Dong Nai, there are currently 3 key national projects including: Long Thanh airport, Bien Hoa - Vung Tau expressway, Ho Chi Minh City Ring Road 3 is in the final stage of construction, to speed up the project progress, on the occasion of National Day 2.9, organize the construction of "3 shifts, 4 teams", investors of the projects are arranged to have full forces on duty, supervise, ensure the construction takes place safely and with quality.