Image of an underpass worth nearly VND800 billion nearing completion in Hanoi

HỮU CHÁNH |

Hanoi - After more than 2 years of construction, the Kim Dong - Giai Phong underpass project has reached over 70% of the volume, expected to be completed in 2025.

The project to build an underpass on the Ring Road 2.5 through the Kim Dong - Giai Phong intersection (Hoang Mai district, Hanoi) started construction in October 2022.

The total tunnel length and the path is 890m in the direction of Ring Road 2.5, of which 140m long, open tunnel is 320m long. The section through the tunnel 2 lanes is 3.5m wide/lane, the tunnel is 3 lanes in each direction of 3.5m wide/lane.

The underpass project has a total investment of 778 billion VND, invested by the Hanoi Traffic Construction Investment Project Management Board.

This is the 5th underpass in the capital built from 2009 to present, after the Kim Lien, Trung Hoa, Thanh Xuan, and Le Van Luong tunnels.

According to Lao Dong on May 25, after more than 2.5 years of construction, the underpass of Ring Road 2.5 through the Giai Phong - Kim Dong intersection has now revealed its shape.

The main item is the closed tunnel (underpass through the intersection) more than 50% of the tunnel sections have been completed.

A representative of the Hanoi Traffic Construction Investment Project Management Board said that the project including the road leading up and down the tunnel, the closed tunnel sections and the open tunnel on the Dinh Cong side with symbols from U1A to U19A have been basically completed.

The investor said that the tunnel sections will be completed in the second quarter of 2025, after which the project will move through the tunnel completion stage, connecting road system, painting lines, lighting, traffic organization, etc.

Reporting to the Hanoi People's Committee, the investor's representative said that the project has completed more than 70% of the work and is ensuring the set plan. It is expected that in the fourth quarter of 2025, the project will be completed.

When completed, the underpass is expected to solve the congestion between Ring Road 2.5 and Giai Phong Road, gradually completing Ring Road 2.5 according to the city's plan.

Ham chui Vanh dai 2,5 qua nut giao Kim Dong - Giai Phong da lo dien hinh hai sau hon 2 nam thi cong. Anh: Huu Chanh
The underpass of Ring Road 2.5 through the Kim Dong - Giai Phong intersection (Hoang Mai district, Hanoi) has revealed its shape after more than 2.5 years of construction. Photo: Huu Chanh
Den nay hang muc ham ho phia Dam Hong da co ban hoan thanh. Anh: Huu Chanh
Up to now, the open tunnel project on the Dinh Cong side has been basically completed. Photo: Huu Chanh
Tuy nhien, ham phia Kim Dong hien van con 1 tram bien ap chua duoc di doi. Anh: Huu Chanh
However, the tunnel on the Dinh Cong side still has 1 transformer station that has not been relocated. Photo: Huu Chanh
Tuong tu, ham ho phia Kim Dong cung da co ban hoan thanh. Anh: Huu Chanh
Similarly, the open tunnel on the Kim Dong side has also been revealed. Photo: Huu Chanh
Mot phan long duoc pho Kim Dong dang duoc hoan tra sau thoi gian nha thau rao chan de phuc vu thi cong. Anh: Huu Chanh
Part of Kim Dong Street is being restored after the contractor barricaded it to serve the construction. Photo: Huu Chanh
Hien nha thau dang tap trung nhan luc thi cong hang muc ham chui di duoi duong sat. Anh: Huu Chanh
Currently, the contractor is focusing on human resources to construct the underpass section under the railway. Photo: Huu Chanh
Day duoc xem la hang muc kho va mat nhieu thoi gian thi cong nhat cua du an. Anh: Huu Chanh
This is considered the most difficult and time-consuming item of the project. Photo: Huu Chanh
Hien du an dang dao, thi cong cac dot ham kin tu HK1 den HK3 va duong dan phia Kim Dong. Anh: Huu Chanh
Machinery digging and constructing the closed tunnel sections from HK1 to HK3 and the Kim Dong approach road. Photo: Huu Chanh
Cong trinh ham chui dang dam bao tien do theo ke hoach, du kien hoan thanh trong nam 2025. Anh: Huu Chanh
The Ring Road 2.5 underpass project through the Kim Dong - Giai Phong intersection is ensuring the planned progress, expected to be completed in 2025. Photo: Huu Chanh
HỮU CHÁNH
TIN LIÊN QUAN

HCMC finalizes the opening of the 341 billion VND underpass at An Phu intersection after many delays

|

HCMC - The 341 billion VND underpass at An Phu intersection (Thu Duc City) will be moved to June 30, 2025, after not being completed in time for the April 30 holiday.

Image of the underpass at the largest intersection in Ho Chi Minh City about to open to traffic

|

HCMC - After many delays, the HC1 underpass - an important item at the An Phu intersection - is preparing to be put into operation from May 9.

The 341 billion VND underpass at the largest intersection in Ho Chi Minh City has been delayed twice, don't lose your promise for the third time

|

The HC1-01 underpass under the An Phu intersection project was not open to traffic during the April 30 holiday as planned.

Home team Da Nang shines brightly on the opening night of DIFF 2025

|

Da Nang - The fireworks display "Cultural quintessence" by the home team Da Nang caused an explosion of emotions at DIFF 2025.

Relieve summer heat at the beach of a pristine church in Nam Dinh

|

Nam Dinh - The beach of the church in Hai Ly commune, Hai Hau district is famous for its wild beauty, suitable for visitors to experience and avoid the heat of summer.

Clip of husband assaulting wife in front of elderly father and young child appears

|

Tuyen Quang - Originating from a family conflict, a woman in Vinh Loi commune (Son Duong district) was assaulted by her husband to the point of hospitalization.

A new breeze for Vietnamese women's volleyball at AVC Nations Cup 2025

|

The combination of experience and youth promises to create a new look for the Vietnam women's volleyball team at the AVC Nations Cup 2025.

Doctor Tran Thanh Trai passes away

|

HCMC - Doctor Tran Thanh Trai passed away in the early morning of May 31, at the age of 88.

HCMC finalizes the opening of the 341 billion VND underpass at An Phu intersection after many delays

MINH QUÂN |

HCMC - The 341 billion VND underpass at An Phu intersection (Thu Duc City) will be moved to June 30, 2025, after not being completed in time for the April 30 holiday.

Image of the underpass at the largest intersection in Ho Chi Minh City about to open to traffic

Tâm Tú |

HCMC - After many delays, the HC1 underpass - an important item at the An Phu intersection - is preparing to be put into operation from May 9.

The 341 billion VND underpass at the largest intersection in Ho Chi Minh City has been delayed twice, don't lose your promise for the third time

Lê Thanh Phong |

The HC1-01 underpass under the An Phu intersection project was not open to traffic during the April 30 holiday as planned.