Images of completed and under construction sections of Hanoi Ring Road 2.5

SÓNG HỮU |

Hanoi - Many sections of Ring Road 2.5 have been put into use, while the remaining sections are being urgently constructed, and technical traffic is expected to be opened in the near future.

Hanoi Ring Road 2.5 has a total length of about 19.64km, planning width of 40-50m. Starting point at Ciputra new urban area, ending at the intersection with Ring Road 3 (section near Thanh Tri bridge).

According to reporters of Lao Dong Newspaper, to date, many sections have been completed and put into use: Section from Doan Ngoai Giao urban area to the intersection to Cau Giay street; Duong Dinh Nghe to Vu Pham Ham section (Trung Kinh street); Tran Duy Hung to Nguy Nhu Kon Tum section (Hoang Dao Thuy street); Dam Hong - National Highway 1A section (completed, is undergoing handover procedures to the city); section from National Highway 1A to Linh Nam street.

s
Ring Road 2.5 section passing through the Diplomatic Corps urban area, September 2026. Photo: Song Huu
d
Ring Road 2.5, Duong Dinh Nghe - Vu Pham Ham section (Trung Kinh street) has been put into use for many years. Photo: Song Huu
d
Ring Road 2.5 section Tran Duy Hung - Nguy Nhu Kon Tum (Hoang Dao Thuy street). Photo: Song Huu

Currently, many sections of the route are being urgently constructed, striving to clear the technical route before October 10 according to Hanoi's direction.

The Ring Road 2.5 project, Cau Giay section - Dich Vong new urban area (Cau Giay ward, Hanoi) has a length of 420m, started many years ago, but until May 2026, the local government completed site clearance to deploy the construction of the road.

s
Ring Road 2.5 project, Cau Giay section - Dich Vong new urban area, September 13. Photo: Song Huu
d
The road when completed has a cross-section of 50m. Photo: Song Huu

The investment project to build Ring Road 2.5 sections: Dich Vong - Duong Dinh Nghe new urban area; Vu Pham Ham - Tran Duy Hung; Nguy Nhu Kon Tum - Nguyen Trai has a total length of about 2.26 km.

This is a project implemented under the urgent construction order of the City People's Committee and started on March 20, 2026.

ưd
In the photo is the Ring Road 2.5 project, Vu Pham Ham - Tran Duy Hung section under construction, on September 13. Photo: Song Huu
ư
Machinery working at the project construction site. Photo: Song Huu
ư
Project information board at the beginning of the route. Photo: Song Huu
Dự án đường Vành đai 2,5 đoạn Ngụy Như Kon Tum - Nguyễn Trãi, ngày 13.9. Ảnh: Sóng Hữu
Ring Road 2.5 project, Nguy Nhu Kon Tum - Nguyen Trai section, September 13. Photo: Song Huu

To date, the Dich Vong - Duong Dinh Nghe new urban area section has reached more than 80% of the volume, has completed the rainwater and wastewater drainage system and is constructing the foundation, road surface, and technical infrastructure, striving to basically complete it before October 5, 2026.

The remaining two sections are focusing on constructing the roadbed and drainage system.

s
Ring Road 2.5 section of Dich Vong - Duong Dinh Nghe new urban area is under construction. Photo: Song Huu
s
Project progress is being accelerated. Photo: Song Huu

Meanwhile, the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, has a route length of about 1.5km, with a cross-section scale of 40m.

The total investment of the project is more than 2,432 billion VND, of which site clearance costs are more than 2,001 billion VND.

To implement the project, Khuong Dinh ward must recover over 60,900m2 of land, involving 736 cases, including 720 households, individuals and 16 organizations.

By May 2026, site clearance work will be completed and transferred to the construction phase.

s
Ring Road 2.5 Nguyen Trai - Dam Hong section. Photo: Song Huu
ư
The section has revealed its shape. Photo: Song Huu
s
Building materials are gathered at the construction site. Photo: Song Huu
d
Machinery working at the project construction site. Photo: Song Huu

At the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, project construction is being urgently deployed by the contractor.

Many machines, equipment and a team of engineers and workers were mobilized by the contractor. Looking from above, the section of Ring Road 2.5 through Khuong Dinh ward has revealed its appearance.

Talking to Lao Dong Newspaper, Secretary of the Party Committee, Chairman of the People's Council of Khuong Dinh ward Vo Dang Dung said that in the context of tight time, the weather is not really favorable, but the Khuong Dinh ward government is still very effortful and determined, striving to technically open the project according to the city's direction.

In the immediate future, the investor directs the contractor to urgently complete the section from the Nguyen Trai road intersection to the To Lich river bridge before 10. 10.

For the remaining section, the progress must also ensure technical traffic on the occasion of October 10. The completion work will continue to be implemented afterwards, ensuring the progress and quality of the project.

a
Ring Road 2.5 project section passing through Xuan Dinh ward, January 11. 9. Photo: Song Huu
s
s
Many items are being implemented. Photo: Song Huu

For the construction item of road No. 5 to the center of Tay Ho Tay new urban area (Belt Road 2.5 through Xuan Dinh ward), the length of the route is 582.04m, cross-section 50m, connecting from the Diplomatic Corps area to Nguyen Hoang Ton street.

By the end of June 2026, the entire site has been handed over, creating conditions for the project to accelerate implementation. The project is expected to be technically opened to traffic before September 30.

SÓNG HỮU
RELATED NEWS

Ring Road 2.5 must be technically opened to traffic on October 10th, Ward Secretary shares existing worries

|

Hanoi - Regarding the progress of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, Secretary of the Party Committee of Khuong Dinh ward shared that his biggest concern is the weather factor.

Ring Road 2.5 section, 582m long, is expected to be technically opened to traffic in September 2026

|

Hanoi - Ring Road 2.5 section passing through Xuan Dinh ward, 582m long, is expected to be technically opened to traffic before September 30th after many years of stagnation due to site clearance issues.

Hanoi Ring Road 2.5 is about to be closed

|

Hanoi - Ring Road 2.5 when closed will reduce congestion for Ring Road 2 and Ring Road 3 routes, contributing to the socio-economic development of the Capital.

Central Committee of the Vietnam Youth Federation has a new Chairman

|

Hanoi - Mr. Nguyen Kim Quy was consulted to hold the position of Chairman of the 9th Central Committee of the Vietnam Youth Federation, term 2024-2029.

The last smiles of fishermen staying at sea

|

Gia Lai - After 4 days drifting at sea, 32 fishermen were rescued, but the smiles of fellow shipmen before letting go still remain in the memories of returnees.

The underpass in front of the new Mien Dong Bus Station in Ho Chi Minh City is deeply flooded again after heavy rain

|

Ho Chi Minh City - After a heavy rain on the afternoon of September 15, the new Mien Dong Bus Station underpass was flooded, causing many vehicles to stall, and people had to turn around and drive in the opposite direction.

Van Hau banned for 4 matches after a rough foul on Doan Ngoc Tan

|

The Disciplinary Committee of the Vietnam Football Federation has issued additional penalties for Doan Van Hau and Da Silva after rough fouls in round 2 of the V.League.

Number of patients hospitalized suspected of poisoning after eating bread in Quang Tri continues to increase

|

Quang Tri - The number of people hospitalized suspected of poisoning after eating bread has increased to 46 cases.

Ring Road 2.5 must be technically opened to traffic on October 10th, Ward Secretary shares existing worries

SÓNG HỮU |

Hanoi - Regarding the progress of the Ring Road 2.5 project, Nguyen Trai - Dam Hong section, Secretary of the Party Committee of Khuong Dinh ward shared that his biggest concern is the weather factor.

Ring Road 2.5 section, 582m long, is expected to be technically opened to traffic in September 2026

SÓNG HỮU |

Hanoi - Ring Road 2.5 section passing through Xuan Dinh ward, 582m long, is expected to be technically opened to traffic before September 30th after many years of stagnation due to site clearance issues.

Hanoi Ring Road 2.5 is about to be closed

SÓNG HỮU |

Hanoi - Ring Road 2.5 when closed will reduce congestion for Ring Road 2 and Ring Road 3 routes, contributing to the socio-economic development of the Capital.