The shape of the VND4,900 billion bridge connecting Ho Chi Minh City - Dong Nai is gradually taking shape

Anh Tú |

HCMC - Phuoc An Bridge worth nearly VND4,900 billion has just been wrapped with the first cable-stayed cable, marking an important step forward, the project is expected to be completed in 2026.

In early September, at the Phuoc An bridge construction site across Thi Vai river (HCMC - Dong Nai), hundreds of engineers, workers and a team of superheavy equipment were working busily. The first cable-stayed cable package has just been stretched at the T38 pillar, marking an important step forward for the project worth nearly VND4,900 billion.

Toan canh cong trinh cau Phuoc An bac qua song Thi Vai. Anh: Anh Tu
Overview of Phuoc An bridge project across Thi Vai river. Photo: Danh Quynh

According to the Cai Mep - Thi Vai Regional Traffic Project Management Board, the cable-stayed extension is considered a decisive technical milestone, opening the contract stage. To date, the main bridge has completed more than 61% of the volume. Two towers hundreds of meters high in the middle of the riverbed are basically taking shape, ready to join in. In package No. 38, the approach bridge section in Phu My ward (HCMC), many items have been completed, more than 160/370 SuperT girders have been installed, the bridge surface is gradually becoming clear. All site clearance work on the Ho Chi Minh City side has also been completed, creating favorable conditions for the contractor to speed up the construction.

hang tram cong nhan, may moc duoc huy dong de thi cong cac tru cau tren song. Trong do, phan cau chinh da dat khoi luong tren 61%. Ảnh: Danh Quynh
Hundreds of workers and machinery have been mobilized to construct the bridge piers on the river. Of which, the main bridge section has reached over 61% of the volume. Photo: Danh Quynh

A representative of the Project Management Board said that the main bridge package is mobilizing more than 350 engineers and workers, along with many tower cranes and cranes with a super load capacity of 250 - 350 tons. Thanks to the application of advanced technology, the project is likely to be completed at least 6 months ahead of schedule, expected to be technically open to traffic by the end of 2026 instead of mid-2027. According to the design, Phuoc An Bridge is 4.38km long (over 3.5km on the bridge, the rest is the approach road), 6 lanes wide, and an operating speed of 70km/h. The bridge has a clearance of 55m, allowing a 30,000-ton ship to travel, with a main span of 250m - the largest in Southeast Asia.

Mat cau Phuoc An phia TPHCM dan thanh hinh sau khi lap hon 160 dam SuperT. Anh: Danh Quynh
The surface of Phuoc An Bridge on the Ho Chi Minh City side is gradually taking shape after installing more than 160 SuperT girders. Photo: Danh Quynh
Trong khi do, phia bo Dong Nai, noi trien khai goi thau 40 va 41 chi moi khoi cong coc khoan nhoi va gia co nen mong. Ảnh: Danh Quynh
Meanwhile, on the Dong Nai shore, where packages 40 and 41 are being implemented, only bored piles and foundation reinforcements have been started. Photo: Danh Quynh
Cong trinh da duoc cang day cap dau tien vao hom 4.9. Anh: Danh Quynh
The project had its first cable stretched on September 4. Photo: Danh Quynh

In contrast to the urgent atmosphere in Ho Chi Minh City, two packages 40 and 41 in Dong Nai have just started construction of bored piles and reinforced foundations. Site clearance is still stuck: only 3.82ha has been handed over, while 2.91ha of forest land must be converted to other purposes. Dong Nai province committed to handing over the entire site in the third quarter of 2025 to ensure progress.

Khi hoan thanh, cong trinh se ket noi truc tiep khu vuc cang Cai Mep - Thi Vai (TP.HCM) voi cao toc Ben Luc - Long Thanh (Dong Nai)
When completed, the project will directly connect the Cai Mep - Thi Vai port area (HCMC) with the Ben Luc - Long Thanh Expressway (Dong Nai). Photo: Danh Quynh
Phoi canh Du an cau Phuoc An sau khi hoan thanh. Anh: Chu dau tu
Perspective of Phuoc An Bridge Project after completion. Photo: Investor

When completed, Phuoc An Bridge will directly connect Cai Mep - Thi Vai port cluster with Ben Luc - Long Thanh expressway, reducing pressure on National Highway 51, while shortening 30km of freight transportation from the West to the seaport.

Anh Tú
RELATED NEWS

People brave the heavy rain on Binh Trieu 1 bridge in Ho Chi Minh City

|

HCMC - After the break, many vehicles traveling through the Binh Trieu 1 bridge area had to inject little by little to move.

Speed up the progress of Phuoc Khanh bridge, an important bottleneck of Ben Luc - Long Thanh expressway

|

HCMC - Phuoc Khanh Bridge across Long Tau River is urgently under construction, speeding up progress to complete the Ben Luc - Long Thanh Expressway project by 2026.

Current status of Phuoc An bridge completes the first cable-stayed stretching

|

The Phuoc An bridge project connecting Ho Chi Minh City with Dong Nai has just completed the first cable-stayed stretch, marking an important milestone in the construction process.

Pork farm discharges waste, turning streams black, foul odor covers the entire village in Lam Dong

|

Lam Dong - People in Hoa Ninh commune (Lam Dong) cry out for help because they have to live with heavy pollution from the pig farm discharging waste in the area.

Difficulty renting rooms when a building in Da Nang arbitrarily sets up Face ID

|

Da Nang - Many tourists are hesitant when the Wyndham Danang Golden Bay hotel apartment recently arbitrarily set up a facial recognition system (Face ID).

Hanoi Traffic Police dress up to patrol, record and handle a series of trucks with lights and horns

|

Hanoi - The traffic police team combined disguise and publicity to detect and handle a series of street-locked and horn-loading trucks running on the road.

Identity of a boy who turned a motorbike scooter causing a tragic accident

|

Lao Cai - The authorities have identified the identity of the boy who died in a rare accident at a tourist market.

People brave the heavy rain on Binh Trieu 1 bridge in Ho Chi Minh City

NHÓM PV |

HCMC - After the break, many vehicles traveling through the Binh Trieu 1 bridge area had to inject little by little to move.

Speed up the progress of Phuoc Khanh bridge, an important bottleneck of Ben Luc - Long Thanh expressway

Anh Tú |

HCMC - Phuoc Khanh Bridge across Long Tau River is urgently under construction, speeding up progress to complete the Ben Luc - Long Thanh Expressway project by 2026.

Current status of Phuoc An bridge completes the first cable-stayed stretching

Thành An |

The Phuoc An bridge project connecting Ho Chi Minh City with Dong Nai has just completed the first cable-stayed stretch, marking an important milestone in the construction process.