Hung Yen promotes progress of two key inter-regional transport projects

Mai Hương |

Hung Yen - Leaders of Hung Yen Provincial People's Committee request units and localities to ensure the progress of implementing two key inter-regional transport projects in the area.

On May 19, Mr. Lai Van Hoan - Vice Chairman of Hung Yen Provincial People's Committee inspected the implementation of the Dong - Tay I road construction project (section from DT. 378 to DT. 382B) and the Ring Road 3.5 construction project (section from DT. 378 to QL. 5).

According to reports from the Construction Investment Project Management Board No. 1 and localities, the Dong - Tay I road construction project (section from DT. 378 to DT. 382B) is more than 4.5km long, with a total investment of 1,310 billion VND, implemented in Van Giang and Nghia Tru communes.

To date, Van Giang commune has handed over about 600m of site for construction, while Nghia Tru commune has not yet handed over the site. The contractor has completed the preparation of the concrete component casting yard, bridge girder, input material testing and started site clearance from May 16, 2026.

According to the plan, by May 30, 2026, localities will hand over the entire agricultural land area; by September 30, 2026, the handover of the entire residential land area for project construction will be completed.

For the Ring Road 3.5 construction project (section from DT. 378 to QL. 5), the project has a total length of more than 8km, passing through Van Giang, Nghia Tru and Nhu Quynh communes, with a total investment of more than 1,490 billion VND.

This is a key project of the province in the 2026 - 2030 period, which plays a connecting role with the project to invest in the construction of Ngoc Hoi bridge and approach roads at both ends of the bridge invested by the Hanoi People's Committee. Currently, localities are actively implementing site clearance work.

Phó Chủ tịch UBND tỉnh Lại Văn Hoàn kiểm tra tình hình triển khai thực hiện dự án xây dựng đường Đông - Tây I (đoạn từ ĐT.378 đến ĐT.382B).
Vice Chairman of the Provincial People's Committee Lai Van Hoan inspects the implementation of the Dong - Tay I road construction project (section from DT. 378 to DT. 382B). Photo: Tat Dat

Through actual inspection and listening to reports, Vice Chairman of the Provincial People's Committee Lai Van Hoan emphasized that these are important transportation projects, with regional connection significance, contributing to promoting urban, industrial and service development of the locality.

He requested units and localities to proactively develop detailed plans, focus on implementing site clearance work, ensuring progress and quality of works according to set requirements.

Regarding the East-West I road project, Mr. Lai Van Hoan requested the construction unit to accelerate the progress, ensuring synchronization with the progress of the PVF stadium construction project; focusing manpower and construction vehicles on the sections that have cleared the ground.

Construction Investment Project Management Board No. 1 is assigned to take the lead in working with relevant departments, branches, localities and the investor of the PVF stadium project to clearly define the boundaries between the two projects, serving the site clearance of the remaining area. Difficulties and obstacles beyond authority need to be promptly summarized and reported to the Provincial People's Committee for consideration and removal.

Regarding the Ring Road 3.5 project, the Vice Chairman of the Provincial People's Committee requested the Construction Investment Project Management Board No. 1 together with departments, branches and localities to urgently hand over the agricultural, transportation, and irrigation land area that has been cleared to the construction unit before May 30 to implement the project; and at the same time continue to focus on clearing the remaining sections of the route, coordinating to promptly remove difficulties and obstacles arising during the implementation process.

Mai Hương
RELATED NEWS

Approaching completion deadline, 3 transportation projects worth more than 2 trillion VND are still facing site clearance issues

|

Can Tho - There are only about 6 months left to reach the target according to the plan, but 3 key transport projects have not yet been able to open the route due to site clearance obstacles.

Ca Mau prepares a series of trillion-VND transport projects to create growth momentum

|

Ca Mau province focuses on investing in many transport infrastructure projects to strengthen inter-regional connectivity, expand urban development space and attract investment.

Opening up key traffic projects in Quang Ngai

|

Quang Ngai - Many multi-billion VND transport projects are behind schedule due to site clearance issues, people have not received compensation, and land legal issues.

Fire at Safira Khang Dien apartment building, residents flee

|

Ho Chi Minh City - In the afternoon of May 19, a fire suddenly broke out in the 7th floor apartment building of Safira Khang Dien apartment building (Ho Chi Minh City), causing many residents to panic and flee.

Bringing studying and following Uncle Ho among union members to become more and more substantive

|

Mr. Nguyen Anh Tuan - Member of the Party Central Committee, Vice Chairman of the Central Committee of the Vietnam Fatherland Front, Chairman of the Vietnam General Confederation of Labor proposed that, in the face of the requirements of the new situation, trade union levels need to continue to promote further, bringing the study and following of Uncle Ho among cadres, union members, and workers to become more and more substantive.

Northern region is about to have widespread heavy rain from tonight, warning of over 250mm in some places

|

The meteorological agency warns that the North, Thanh Hoa and Nghe An are about to welcome a widespread heavy rain; warning of the risk of flash floods and landslides, especially in mountainous areas.

Lack of support, stocks fall due to strong profit-taking pressure

|

Oil and gas and rubber stocks were sold for profit-taking in the afternoon session of May 19, causing the stock market to adjust sharply.

Approaching completion deadline, 3 transportation projects worth more than 2 trillion VND are still facing site clearance issues

Tạ Quang |

Can Tho - There are only about 6 months left to reach the target according to the plan, but 3 key transport projects have not yet been able to open the route due to site clearance obstacles.

Ca Mau prepares a series of trillion-VND transport projects to create growth momentum

NHẬT HỒ |

Ca Mau province focuses on investing in many transport infrastructure projects to strengthen inter-regional connectivity, expand urban development space and attract investment.

Opening up key traffic projects in Quang Ngai

ĐÔNG GIANG |

Quang Ngai - Many multi-billion VND transport projects are behind schedule due to site clearance issues, people have not received compensation, and land legal issues.