Can Tho leaders inspect the progress of Dai Ngai bridge project

Tạ Quang |

Can Tho - City leaders requested localities to accelerate inventory and complete compensation and support plans for affected households.

On May 15, Mr. Dong Van Thanh - Member of the Party Central Committee, Standing Deputy Secretary of the City Party Committee, Chairman of the People's Council of Can Tho City had a working session with Soc Trang ward and Tan Thanh, Dai Ngai, and Truong Khanh communes to inspect the progress of the Dai Ngai bridge construction investment project on National Highway 60.

Lãnh đạo TP Cần Thơ làm việc với địa phương về tiến độ thực hiện Dự án đầu tư xây dựng cầu Đại Ngãi. Ảnh: Hữu Phần
Can Tho City leaders work with local authorities on the progress of the Dai Ngai bridge construction investment project. Photo: Huu Phan

According to the report at the meeting, the planned section of National Highway 60 from National Highway 91B to existing National Highway 60 belongs to the Project to invest in the construction of Dai Ngai bridge on National Highway 60 passing through Can Tho City and Vinh Long province, with a length of about 12.39km. In Can Tho City, the project passes through Soc Trang ward and Dai Ngai, Tan Thanh, and Truong Khanh communes.

This is a key transportation project of important significance in connecting regional transport infrastructure, creating motivation to promote socio-economic development, expand regional linkages, and gradually complete the transportation network on National Highway 60.

Over the past time, the Branch of Land Fund Development Region IX has closely coordinated with localities to implement many tasks related to site clearance. Up to now, the units have carried out inventory and developed compensation and support plans for 41/42 graves affected by the project; and at the same time organized people's meetings to inform policy information, disseminate implementation plans and receive opinions from people related to compensation, support and resettlement.

Regarding land recovery work, Soc Trang ward and Dai Ngai and Truong Khanh communes have deployed land recovery notices in accordance with regulations. In Tan Thanh commune alone, there are still some households that have not completed inventory work, and the locality is continuing to mobilize and propagate to get people to agree and coordinate in implementation.

At the working session, local leaders reported on difficulties and obstacles arising in the project implementation process, especially related to the determination of land prices, architectural values, crops and affected assets to develop appropriate compensation plans, ensuring the rights of people.

Concluding the working session, Mr. Dong Van Thanh acknowledged the efforts of functional sectors and local authorities in the past time; and shared, exchanged and directed specific removals for each existing difficulty and obstacle.

City leaders proposed that localities continue to focus on performing well two key tasks: accelerating the inventory progress for the remaining households, especially in Tan Thanh commune; and at the same time urgently reviewing and determining land prices and the value of architectural works affected to soon complete compensation and support plans according to regulations.

In addition, the Land Fund Development Center continues to coordinate and support localities in each specific task; strengthen propaganda and mobilization to create consensus among the people, contributing to accelerating site clearance progress, ensuring that the Dai Ngai Bridge construction investment project is implemented on schedule.

Tạ Quang
RELATED NEWS

Ca Mau Party Secretary and Chairman and provincial leaders participate in humanitarian blood donation

|

On the morning of May 15, the Steering Committee for Voluntary Blood Donation Mobilization of Ca Mau province organized a blood donation day in response to "Humanity Month" 2026.

Workers construct during holidays at Dai Ngai 1 bridge

|

During the holiday, hundreds of workers at Dai Ngai 1 bridge construction site are still diligently working throughout to ensure project progress, despite difficulties from weather and tides.

Dai Ngai bridge project adds a connecting route of more than 12km, increasing connectivity in the Mekong Delta

|

The Ministry of Construction approved the adjustment of the Dai Ngai bridge project, supplementing the connecting route from National Highway 91B (South Hau River road) to existing National Highway 60, more than 12km long.

Ho Chi Minh City deploys meaningful ticket ATMs, people in need can travel on Metro Line 1 for free

|

Ho Chi Minh City deploys "Gratitude ticket ATM" at Metro Line 1, supporting workers, students in difficult circumstances to travel on trains for free using socialized sources.

Proposal to expand the "Three Assistance" model for Trade Unions to accompany workers

|

Dong Thap - Workers expect the "Three Assistants" model including support - assisted reproduction - capital support to be expanded, so that the Trade Union can accompany workers.

Can Miu Le continue to sing and act in movies when managed locally?

|

According to experts, whether Miu Le is allowed to continue singing and acting when being managed locally needs to be determined based on many factors.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Ca Mau Party Secretary and Chairman and provincial leaders participate in humanitarian blood donation

NHẬT HỒ |

On the morning of May 15, the Steering Committee for Voluntary Blood Donation Mobilization of Ca Mau province organized a blood donation day in response to "Humanity Month" 2026.

Workers construct during holidays at Dai Ngai 1 bridge

TẠ QUANG |

During the holiday, hundreds of workers at Dai Ngai 1 bridge construction site are still diligently working throughout to ensure project progress, despite difficulties from weather and tides.

Dai Ngai bridge project adds a connecting route of more than 12km, increasing connectivity in the Mekong Delta

PHƯƠNG ANH |

The Ministry of Construction approved the adjustment of the Dai Ngai bridge project, supplementing the connecting route from National Highway 91B (South Hau River road) to existing National Highway 60, more than 12km long.