Opening up key traffic projects in Quang Ngai

ĐÔNG GIANG |

Quang Ngai - Many multi-billion VND transport projects are behind schedule due to site clearance issues, people have not received compensation, and land legal issues.

Still problems with compensation

The Hoang Sa - Doc Soi road project has a total investment of 3,500 billion VND, implementation time from 2022 - 2027, invested by the Provincial Traffic Construction Investment Project Management Board. The total planned construction area of the main route is 172.16 ha, passing through many communes and wards in the province.

One of the bottlenecks that has caused many obstacles to project construction in the past time is site clearance issues.

According to Truong Quang Trong Ward People's Committee, the Hoang Sa - Doc Soi road project passing through the ward area, has now handed over most of the area. However, the handed over site is not continuous because 63 cases refuse to receive compensation money.

Các cơ quan chức năng đang tập trung tháo gỡ khó khăn, nhằm đẩy nhanh tiến độ thi công dự án đường Hoàng Sa - Dốc Sỏi. Ảnh: Hồ Phương - Huyền Phương
Functional agencies are focusing on removing difficulties to speed up the construction progress of the Hoang Sa - Doc Soi road project. Photo: Ho Phuong - Huyen Phuong

The main reason is that some households do not agree with not being supported with career change, claiming that the unit price is low and there are no inheritance procedures to receive money. In addition, the project also has to solve the difficult problem of relocating more than 1,000 graves while the temporary borrowed area has only 400 plots.

Similarly, the Thach Bich - Tho Phong road project has a total investment of more than 694 billion VND, invested by the Provincial Traffic Construction Investment Project Management Board, implemented from 2019, expected to be completed in 2025, but is still unfinished to this day.

The reason is that the handed-over site is not continuous, leading to construction work always being chaotic, although provincial leaders have directly gone to the site four times to inspect and urge progress.

According to reporters' records, at the connecting point of National Highway 24B (Truong Quang Trong ward), the road surface has been asphalted, painted, and planted with quite complete green trees. However, going about 300 m, the road suddenly "interrupted" due to households not yet relocated.

From above, it can be clearly seen that many sections of the route have completed the roadbed but are divided by houses that have not been cleared.

Many residential land plots are issued red books with incorrect limits

According to Truong Quang Trong Ward People's Committee, for the Thach Bich - Tho Phong road project, currently 0.97ha is stagnant due to problems related to Inspection Conclusion No. 87/KL-UBND of the Provincial People's Committee. Dozens of residential land plots have been granted red books with incorrect limits since 1996 - 1997, and have now been transferred many times.

At the first Conference to remove bottlenecks and obstacles held at Truong Quang Trong Ward People's Committee on April 14, 2026, Truong Quang Trong Ward People's Committee resolutely defended the view that the Department of Agriculture and Rural Development must review and thoroughly handle these legal errors before developing a compensation plan. Absolutely do not let local authorities bear risks or be sued for applying unfounded laws.

Nhiều người dân vẫn chưa bàn giao mặt bằng để thi công dự án đường nối từ cầu Thạch Bích đến xã Thọ Phong, một trong những dự án trọng điểm của tỉnh Quảng Ngãi. Ảnh: ĐÔNG GIANG
Many people have not yet handed over land to construct the road project connecting Thach Bich bridge to Tho Phong commune, one of the key projects of Quang Ngai province. Photo: DONG GIANG

According to Mr. Tran Quang Toa - Secretary of the Party Committee of Truong Quang Trong ward, for projects being implemented in the ward, the volume of site clearance in 2026 is very large, requiring the drastic involvement of the entire political system.

Also at the above conference, Mr. Tran Quang Toa directed the Ward People's Committee to focus highly and coordinate to complete the work of re-determining specific land prices for items of the Hoang Sa - Doc Soi project, right in April 2026, in order to accelerate capital disbursement.

Proposing the Provincial Party Committee and Provincial People's Committee to directly assign tasks to the Department of Agriculture and Environment and the Provincial Land Registration Office to urgently rectify violations according to Conclusion 87/KL-UBND to unlock the Thach Bich - Tinh Phong connecting road project, ensuring compliance with the law.

The Steering Committee will specifically assign each member to be in charge of monitoring and urging each area and each group of households that still have problems to have effective mobilization and persuasion measures to completely resolve the current stagnant construction situation.

ĐÔNG GIANG
RELATED NEWS

Quang Ngai changes the purpose of nearly 83ha of forest to make a project

|

Quang Ngai - Changing the purpose of forest use to implement the Urban Area No. 1 Project in Mang Den commune with a total investment of about 6,600 billion VND.

Bridge in Quang Ngai is built but lacks access roads and the story of visibility gaps

|

Son Mua bridge - Quang Ngai invested nearly 80 billion VND but is still unfinished due to lack of access roads, making the project unable to be exploited, causing waste.

Quang Ngai starts construction of 94 ha ecological urban area project

|

Quang Ngai - The Coastal Eco-urban Area project has been started with a scale of nearly 94ha. Contributing to elevating the appearance and creating attraction for local tourism.

Series of slow-progress projects in Long Bien named

|

Hanoi - In the list of 341 slow-progress projects in the city, there are 25 projects located in Long Bien district (old).

Vietnam speaks out about the visit of Taiwan Coast Guard (China) leaders to Ba Binh Island

|

Vietnam speaks out about the leaders of the Taiwan Coast Guard (China) coming to Ba Binh Island to participate in drills, including drills to deploy armed personnel to suspicious ships.

Mountains of garbage smell, dirty wastewater flows everywhere in Thai Nguyen

|

Thai Nguyen - Mountains of domestic waste piled up for many years without treatment plans cause prolonged pollution and frustration for local people.

Audiences wearing bachelor's degree shirts come to see Soobin and the "talented brothers

|

On April 26, tens of thousands of spectators flocked to Hung Yen to attend the Anh Trai Vuot Ngan Chong Gai concert with the participation of Soobin, Bui Cong Nam and many artists.

Main activities at Hung Temple 2026 on March 10th of the lunar calendar

|

Phu Tho - April 26th (March 10th of the lunar calendar) is the main day of Hung Kings' Death Anniversary. There will be many activities at the Hung Temple relic.

Quang Ngai changes the purpose of nearly 83ha of forest to make a project

ĐÔNG GIANG |

Quang Ngai - Changing the purpose of forest use to implement the Urban Area No. 1 Project in Mang Den commune with a total investment of about 6,600 billion VND.

Bridge in Quang Ngai is built but lacks access roads and the story of visibility gaps

Lê Thanh Phong |

Son Mua bridge - Quang Ngai invested nearly 80 billion VND but is still unfinished due to lack of access roads, making the project unable to be exploited, causing waste.

Quang Ngai starts construction of 94 ha ecological urban area project

ĐÔNG GIANG |

Quang Ngai - The Coastal Eco-urban Area project has been started with a scale of nearly 94ha. Contributing to elevating the appearance and creating attraction for local tourism.