Khanh Hoa removes obstacles in site clearance for expressway projects

Hữu Long |

Khanh Hoa - On November 13, Vice Chairman of the province Le Huyen chaired a meeting on the problems and problems related to site clearance for the expressway project.

Regarding the Nha Trang - Cam Lam expressway project, the leader of the Ho Chi Minh Road Project Management Board said that the expressway has been opened to traffic, but there are still some problems, including a rest stop at Km33+930 (Cam Hiep commune). Up to now, compensation and site handover to investors have been completed.

During the implementation of the rest stop, we request that the authorities coordinate with the locality to provide goods and promote the strengths of local specialties, suggested a representative of the Ho Chi Minh Road Project Management Board.

Regarding this content, Vice Chairman of the Provincial People's Committee Le Huyen assigned the Land Fund Development Center to complete payment procedures for people; at the same time, requested the Department of Agriculture and Environment to provide specific instructions on procedures related to land allocation.

Mr. Huyen suggested that the Project Management Boards coordinate with the Department of Agriculture and Environment to complete the Nha Trang - Cam Lam expressway rest stop on schedule.

Regarding the old problems of this project, the Ho Chi Minh Road Project Management Board said that the handover of service roads and level crossings is completing procedures to hand over to the locality for management.

For the Cam Lam - Vinh Hao Expressway project, the representative of Project Management Board 85 informed about the site clearance of the rest stop at Km90+900 (Do Vinh ward, Khanh Hoa province) which has been completed and handed over to the investor for construction.

Meanwhile, for the Thuan Nam intersection connecting route DT.709, the site clearance work has basically been completed, but during the construction process, problems arose related to the relocation of the water supply pipeline.

Currently, the relocation dossier is being completed by the Land Fund Development Branch of Nam Khanh Hoa area, submitted to the People's Committee of Phuoc Ha commune for approval for implementation.

Vice Chairman of the Provincial People's Committee Le Huyen requested the investor to transfer the payment funds on schedule so that Do Vinh ward can promptly pay the people. Regarding the Thuan Nam intersection, Mr. Huyen suggested that the locality must complete the relocation of the water pipeline before November 20, if there are any problems, they must promptly report to the Provincial People's Committee for direction on handling.

Hữu Long
RELATED NEWS

Ministry of Construction provides new information about Khanh Hoa - Buon Ma Thuot Expressway

|

On the Portal, the Ministry of Construction has just responded to the People's Committee of Khanh Hoa province about the Khanh Hoa - Buon Ma Thuot expressway project.

Component 3 project of Khanh Hoa - Buon Ma Thuot expressway reaches more than 50% of construction value

|

Dak Lak - Up to now, the Khanh Hoa - Buon Ma Thuot Expressway Component 3 Project has reached more than 71.8% of the construction contract value, equivalent to VND 3,084/4,293 billion

Close-up of the luxurious villa of the beauty salon owner Mailisa

|

HCMC - At the end of the afternoon of November 13, the authorities completed the search after many hours at the villa of the owner of Mailisa beauty salon.

The case of 40 students suspected of poisoning: Additional violations of the principal discovered

|

Quang Tri - In addition to the suspension of the vice principal in the case of 40 students suspected of poisoning, the People's Committee of Kim Ngan commune also determined further violations by the school principal.

The weather in the North is about to have a big change due to the strengthening of cold air

|

Due to the influence of the strengthening cold air, from the night of November 13 to 15, the Northern region will be cold, with some mountainous areas experiencing severe cold below 13 degrees Celsius.

Ms. Phung Thi Hong Ha becomes Chairwoman of the Hanoi People's Council

|

Hanoi - Deputy Secretary of the City Party Committee, Permanent Vice Chairwoman of the City People's Council Phung Thi Hong Ha was elected to hold the position of Chairwoman of the City People's Council for the 16th term, 2021-2026.

Gasoline prices increase simultaneously from 3:00 p.m. this afternoon, November 13

|

Gasoline prices increased simultaneously, oil prices fluctuated in different directions from 3:00 p.m. today (November 13), after adjustments by the Ministry of Industry and Trade - Ministry of Finance.

The profiteering tricks of land brokers in Phu Quoc

|

Phu Quoc - The proposal to divide the portion is not only an insult to the ethics of journalism, but also exposes the nature of the thief in the lawsuit to profit under the guise of the subject.

Ministry of Construction provides new information about Khanh Hoa - Buon Ma Thuot Expressway

Xuyên Đông |

On the Portal, the Ministry of Construction has just responded to the People's Committee of Khanh Hoa province about the Khanh Hoa - Buon Ma Thuot expressway project.

Component 3 project of Khanh Hoa - Buon Ma Thuot expressway reaches more than 50% of construction value

PHAN TUẤN |

Dak Lak - Up to now, the Khanh Hoa - Buon Ma Thuot Expressway Component 3 Project has reached more than 71.8% of the construction contract value, equivalent to VND 3,084/4,293 billion

Đắk Lắk yêu cầu chấm dứt chậm trễ tại dự án cao tốc Khánh Hòa - Buôn Ma Thuột

BẢO LÂM |

Đắk Lắk - Chủ tịch tỉnh Đắk Lắk yêu cầu khẩn trương tháo gỡ vướng mắc, chấm dứt tình trạng chậm trễ tại Dự án thành phần 3 cao tốc Khánh Hòa - Buôn Ma Thuột.