On January 31, Dong Nai Provincial People's Committee just had a plan and assigned the Provincial Construction Investment Project Management Board to organize the preparation, appraisal, and decision approval of the component project of Ring Road 4 HCMC and carry out the next tasks to start construction before June 30, 2026 (for component projects invested in the form of public investment).
For component projects implemented according to the public-private partnership method, organize the preparation, appraisal, evaluation, decision approval of component projects and select investors to complete before June 30, 2026; carry out the next tasks to start construction in the fourth quarter of 2026.
According to the People's Committee of Dong Nai province, the project strives to be completed in 2028 and put into operation in 2029.
The Ho Chi Minh City Ring Road 4 project has a planned route length of more than 159km, passing through the provinces of: Dong Nai, Tay Ninh and Ho Chi Minh City. In which, the section passing through Dong Nai province is about 46km long (including Thu Bien bridge).
Component projects 1-2: Compensation, support, resettlement and construction of service roads and side roads, in Dong Nai province, with a total investment of more than 10,000 billion VND from local budget capital.
Component project 2-2: Construction of the expressway section from Chau Duc bridge to Thu Bien bridge (including Thu Bien bridge), according to public-private partnership (PPP) method, with a total investment of more than 16,200 billion VND. Of which, the local budget allocates capital of more than 4,000 billion VND and investor capital of more than 12,200 billion VND.
In phase 1, the road is invested in construction with a scale of 4 lanes, road speed of 100km/h.