Another delay in handing over the site for the Tam Trinh road expansion project

HỮU CHÁNH |

Hanoi - Hoang Mai District has postponed the site clearance progress of the Tam Trinh road expansion project until April 2025 due to some remaining difficulties and problems waiting to be resolved.

The Tam Trinh road expansion project (Hoang Mai district, Hanoi) is 3.5 km long, starting at Minh Khai intersection and ending at Ring Road 3 intersection, with a total investment of nearly VND3,400 billion.

The project started in 2016 and is expected to be completed after 3 years. However, due to many difficulties in site clearance (GPMB), the project has been stalled.

In July 2024, Hoang Mai district handed over about 800 m of clean land to the contractor to implement the expansion of Tam Trinh road after many years of delay.

Cong truong du an mo rong duong Tam Trinh (quan Hoang Mai, Ha Noi). Anh: Huu Chanh
A section of Tam Trinh Street is under construction and expansion. Photo: Huu Chanh

The actual records of the reporter show that at the sections that have been cleared, the contractor has constructed to the last base layer ( mixture layer) but cannot deploy the asphalt concrete layer because some electric poles are still within the roadway.

Up to now, after 8 months of construction, the value of the contractor's construction output - Truong Son 97 Branch - has only reached about 15 - 18% of the construction contract value (over 294 billion VND), significantly behind schedule.

According to the People's Committee of Hoang Mai District, to implement the project, the locality must reclaim over 54,000 m2 (after adjusting the boundary), involving about 1,590 households and 20 organizations in the three wards of Mai Dong, Hoang Van Thu and Yen So.

Up to now, the site clearance work is still stalled due to the locality still facing some difficulties and problems that need to be resolved.

Recently, the Standing Committee of Hoang Mai District Party Committee has decided to postpone the handover deadline for the Tam Trinh road project by 30 days, ending before April 30, 2025.

Thus, the site clearance work of this project has changed the completion time frame four times: September 30, 2024; December 31, 2024; March 31, 2025 and now April 30, 2025.

Nhieu can nha tren duong Tam Trinh chua duoc giai phong mat bang. Anh: Huu Chanh
Many houses on Tam Trinh Street have not been cleared. Photo: Huu Chanh

Hoang Mai District said that the policy related to compensation and site clearance is outside the scope of the decision of the District People's Council and People's Committee. Therefore, it is necessary to report and seek opinions from departments and People's Committees of Hanoi City when applying the 2024 Land Law.

According to the provisions of the 2024 Land Law, the resettlement housing fund must be prepared before issuing land recovery decisions for households.

Currently, the resettlement housing fund serving the Tam Trinh road project is the CT1, CT2, CT3 buildings in Den Lu Urban Area. However, these buildings have degraded due to being used as quarantine areas for COVID-19 patient treatment, and need to be renovated and repaired to be eligible for handover.

Hoang Mai District must request the city's policy to provide funding to support resettlement households to rent houses while waiting for the renovation of Den Lu Urban Area.

Quan Hoang Mai phan dau hoan thanh giai phong mat bang vao cuoi thang 4.2025. Anh: Huu Chanh
Hoang Mai District strives to complete site clearance by the end of April 2025. Photo: Huu Chanh

According to the People's Committee of Hoang Mai District, according to the previous Land Law and the city's guiding documents on site clearance, illegal construction works (not granted a construction permit) are still supported at a percentage of new construction value (depending on the time of construction).

However, the 2024 Land Law does not stipulate this content, which means that households with illegal construction will not be compensated.

In fact, on Tam Trinh Street, most of the houses of the people do not have a construction permit or no written approval from the competent authority.

The application of the new law has made the People's Committee of Hoang Mai district unfounded to implement compensation or support policies, prolonging compensation work, even though the authorities of the wards continuously organize dialogues with the people.

Hoang Mai District People's Committee has issued a document reporting to Hanoi City People's Committee. The city's leaders have assigned departments and branches to advise and issue guiding documents.

According to the plan, if the city has a document guiding the implementation before March 20, Hoang Mai district will complete the site clearance for the Tam Trinh road expansion project within 30 - 35 days, expected to be completed in April 2025.

HỮU CHÁNH
TIN LIÊN QUAN

Hanoi starts construction of 2 traffic projects, capital of more than 1,400 billion VND

|

Hanoi - The project to expand National Highway 21B and build a National Highway 21B bypass, with a total investment of more than VND 1,400 billion, will be built in the period from now until 2027.

Hanoi to enforce land acquisition to open 30m wide road

|

Hanoi - The People's Committee of Thuong Tin district has planned to organize compulsory land recovery of some households that do not agree to hand over the land to implement the expansion of National Highway 1A.

President Putin outlines conditions for ceasefire in Ukraine

|

President Vladimir Putin responded to the 30-day ceasefire plan that Ukraine agreed earlier this week after talks with the US.

slow construction of the only road leading to the capital Tuyen Quang

|

Tuyen Quang - The sluggish construction situation has caused the road from Tan Thanh commune to Phu Luu commune to be bumpy and littered with construction materials.

Queuing from 5am to complete administrative procedures in Quang Ninh

|

Quang Ninh - For the past 2 weeks, people completing land procedures at the Branch of the Quang Yen Town Public Administration Service Center have increased dramatically, many people have come since 5am.

Villas worth tens of billions of dong in Hanoi for rent at surprising prices

|

Hanoi - A series of townhouses in Hanoi are currently being announced for rent at prices of just over 10 million VND per month.

Proposal to increase the family deduction level to suit reality

|

The family deduction level has not changed for many years while the cost of living has increased, causing many opinions to suggest that it needs to be adjusted to suit the current standard of living.

311 teachers unexpectedly have their insurance money collected VND4.6 billion

|

Nghe An - 311 teachers were charged VND4.6 billion in insurance, including more than VND2.6 billion in fines for late payment.

Đường hơn 1km ở Nam Từ Liêm làm 5 năm chưa xong

HỮU CHÁNH |

Hà Nội - Thi công từ năm 2020 nhưng đến nay dự án xây dựng đoạn đường dài 1,2km ở Nam Từ Liêm vẫn chưa hoàn thiện, ảnh hưởng đến cuộc sống của người dân.

Hanoi starts construction of 2 traffic projects, capital of more than 1,400 billion VND

HỮU CHÁNH |

Hanoi - The project to expand National Highway 21B and build a National Highway 21B bypass, with a total investment of more than VND 1,400 billion, will be built in the period from now until 2027.

Hanoi to enforce land acquisition to open 30m wide road

HỮU CHÁNH |

Hanoi - The People's Committee of Thuong Tin district has planned to organize compulsory land recovery of some households that do not agree to hand over the land to implement the expansion of National Highway 1A.