Clarifying responsibilities when the National Highway 9 expansion project has its funding cut

HƯNG THƠ |

The project to expand National Highway 9 in Quang Tri, which was funded by the World Bank (WB), was suspended and cut off due to slow site clearance. Although there was a plan to close the old project and continue implementation, the responsibilities of the organizations and individuals involved have not been clarified.

Use public investment capital to continue project implementation

The project "Upgrading and expanding National Highway 9 from Cua Viet Port to National Highway 1" uses surplus capital from the VRAMP Project, a WB loan approved for investment in August 2021. The project is 13.8km long, a level II delta road with 4 lanes, with a total investment of more than 440 billion VND. In which, the Ministry of Transport is responsible for implementing the construction investment and the People's Committee of Quang Tri province completes compensation and site clearance work, ensuring the project's construction progress in 2021-2022. However, due to slow site clearance, the project implementation period has not been completed yet, so the project had to stop construction and the capital was cut.

In November 2024, Party Central Committee member, Minister of Foreign Affairs, Deputy Prime Minister Bui Thanh Son directed and assigned the Ministry of Transport to close the WB loan project and take responsibility for managing and developing a plan to continue investing and completing the unfinished items of the above project.

Mr. Le Duc Tien - Vice Chairman of Quang Tri Provincial People's Committee said that the Ministry of Transport is currently completing the procedures to close the project, then will continue to invest in upgrading and expanding National Highway 9. On the side of Quang Tri province, after receiving instructions from the Deputy Prime Minister, Quang Tri province has assigned the Department of Transport of Quang Tri province to be the focal agency, coordinating with the Provincial Investment and Construction Project Management Board and related departments and branches - working with the Ministry of Transport and the Vietnam Road Administration, to complete the procedures, continue to deploy investment and construction to complete the project in the medium-term public investment plan for the period 2026-2030. At the same time, Quang Tri Provincial People's Committee also assigned the People's Committees of Cam Lo, Gio Linh districts and Dong Ha city to be responsible for resolving the consequences arising from the project's site clearance work. And clarify the causes and responsibilities of organizations and individuals in not completing the site clearance work according to the project's schedule.

Whose responsibility is it?

Research shows that the project "Upgrading and expanding National Highway 9 from Cua Viet Port to National Highway 1" has a very large volume of land acquisition and clearance work. The area of ​​land acquisition and clearance is about 452,205m² with 2,133 plots of land, 807 cases are affected, of which 19,000m² of architectural works, 66 houses are affected, 17 households have to resettle. The measurement, counting, owner planning for compensation, and construction of resettlement areas according to the correct procedures take a lot of time.

For example, from the time of land reclamation notification to the decision on land reclamation, the latest is 90 days for agricultural land, 180 days for non-agricultural land; the time for surveying and adjusting cadastral maps to serve land reclamation and land allocation is 120 days. Thus, the time for implementing land clearance work from the time of implementation to the decision on land reclamation is about 310 days (10 months), while the project implementation time is only 1 year.

According to the leader of the People's Committee of Quang Tri province, in addition to many objective and subjective reasons, Quang Tri province has not anticipated the sudden change in real estate prices in the area at the time of estimating the total investment compared to the time of project implementation, as well as the complicated site clearance process of the sponsor, leading to commitments on progress that cannot be fulfilled.

HƯNG THƠ
TIN LIÊN QUAN

Removing bottlenecks, the 329 billion VND bypass in Tuyen Quang is about to reach the finish line

|

After the problems with the site were resolved, the bypass route worth more than 329 billion VND in Tuyen Quang is accelerating to the finish line.

Forecast for heavy rain in the North due to cold air, some places over 50mm

|

According to the meteorological agency, the Northwest region is about to have rain, with some places having heavy rain over 50mm.

Strictly handle the responsibility of the Ministry of Health in 2 hospital projects in Ha Nam

|

The Government Inspectorate recommends strictly handling the responsibility of the leaders of the Ministry of Health in violations at 2 hospital projects in Ha Nam.

The Politburo proposed that the Party Central Committee consider disciplining Mr. Truong Hoa Binh

|

On April 4, 2025, at the Party Central Committee Headquarters, the Politburo reviewed and disciplined party members who violated and had shortcomings.

HCMC plans to clear 2,452 households to expand 4 gateway roads

|

Ho Chi Minh City plans to reclaim land from 4,730 households for 4 projects to upgrade and expand National Highways 1, 13, 22, and the North-South axis road. Of which, 2,452 households were cleared.

Mr. Trump unexpectedly sets negotiation conditions to reduce counterpart taxes

|

President Donald Trump has said he is ready to negotiate counterpart tax reductions if there is an attractive enough proposal.

Công an Đakrông truy đuổi xe ôtô chở pháo lậu trên Quốc lộ 9

HƯNG THƠ |

Quảng Trị - Công an huyện Đakrông đã truy đuổi chiếc xe ôtô lưu thông trên Quốc lộ 9, bắt quả tang tài xế chở theo nhiều pháo lậu.

Bắt nam thanh niên vận chuyển pháo lậu trên Quốc lộ 9

HƯNG THƠ |

QUẢNG TRỊ - Lực lượng công an phát hiện trên chiếc xe ôtô do nam thanh niên điều khiển có 236 hộp pháo lậu.

Sau 2 năm dừng triển khai, dự án mở rộng Quốc lộ 9 ở Quảng Trị sẽ ra sao?

HƯNG THƠ |

Tỉnh Quảng Trị báo cáo với Bộ Kế hoạch và Đầu tư, đề nghị báo cáo Thủ tướng Chính phủ xem xét việc dừng thực hiện dự án mở rộng Quốc lộ 9.