On the hundred-billion-dong bypass road project in the border area

Tân Văn |

Cao Bang - The Quang Uyen town bypass road (Quang Hoa district) will have to be completed in 2025.

According to the reporter's investigation, the project to build the Quang Uyen town bypass is a level 1 project, belonging to group B, using public investment capital managed by Cao Bang province, with the People's Committee of Quang Hoa district as the investor.

The route has a total length of about 4.85km, starting at Phuc Sen commune and ending at Quang Uyen town. The total investment is 200 billion VND. The project started in March 2024 and is expected to be completed in 2025.

Hinh hai tuyen duong dang duoc hoan thanh. Anh: Tan Van.
The shape of the route is being completed. Photo: Tan Van.

Recorded on March 1, at the construction site, machinery is concentrating on construction. Some workers are drilling and breaking rocks to serve the leveling and shaping of the road.

Talking to reporters, the representative of the construction contractor said: "The locality has completed the site clearance work. On the entire route, there are three contractors working together, all of whom strive to complete in 2025".

It is known that in 2024, the project encountered difficulties due to a shortage of more than 300,000m3 of fill soil.

As one of the important projects of Quang Hoa district, when completed, the route will have great significance in promoting the socio-economic development of the locality. Therefore, people have high expectations for this project.

Cac cong nhan khoan pha da tren cong trinh. Anh: Tan Van.
Workers drilling and breaking rocks at the construction site. Photo: Tan Van.

Mr. Hoang Van Da (residing in Quang Uyen town) shared: "I hope the road will be completed soon so that people have more convenient directions to travel. Vehicles going to Ta Lung border gate will also be easier".

Regarding the shortage of fill soil for many projects in the province, the People's Committee of Cao Bang province has directed units assigned as project investors to review projects under construction and prepare for construction.

Tuyen duong tranh khi hoan thanh se giup giao thong thuan tien hon so voi tuyen duong cu von nho hep va xay dung tu lau. Anh: Tan Van.
When completed, the bypass will help improve traffic compared to the old, narrow road that was built a long time ago. Photo: Tan Van.

If there is a surplus amount of soil and rock (after registration for exploitation and on-site use), it can be provided to other projects in the area. At the same time, units need to proactively guide and direct contractors to carry out procedures to request a mineral exploitation license according to regulations to serve related projects.

The procedures for requesting a Mineral Exploitation License will be carried out according to the instructions of the Department of Natural Resources and Environment.

Tân Văn
TIN LIÊN QUAN

Cao Bang seeks solutions to the problem of public investment

|

Cao Bang - The Provincial People's Committee has just held a conference on basic construction and disbursement of public investment capital in 2025.

Northwest end of day: Sa Pa airport bypass landslide

|

Landslide on Sa Pa airport bypass; Termination of billion-dollar steel project; Queuing in cold rain to buy tickets for Vietnam - Indonesia match are some of the highlights.

7,000 billion VND airport bypass in Lao Cai eroded after storm and flood

|

Lao Cai - Many landslides and subsidence points on the Sa Pa Airport bypass road make it difficult for people to travel.

Vietnamese tourists are required to declare online when traveling to Thailand

|

From May 1, all international tourists traveling to Thailand must fill in their digital entry cards before entering the country. This is something Vietnamese tourists need to pay attention to.

The Ministry of Construction has many violations when adjusting the planning of the capital area

|

The Government Inspectorate has just pointed out many violations in adjusting the Construction Planning of the Capital Region.

The Inspection Committee proposes to discipline the former Vice Chairman of the Dong Nai Provincial People's Committee

|

The Provincial Party Committee's Inspection Committee proposed to discipline former Vice Chairman of Dong Nai Provincial People's Committee Vo Van Chanh for related land violations.

Ho Chi Minh City sidewalks "transformed", people are excited about clean and beautiful walking paths

|

HCMC - After the renovation process, many sidewalks in the city center have taken on a new look, people are excited because they have a clean and beautiful walking space.

Hanoi Police lost the first leg of the Southeast Asian Cup C1 semi-final

|

Hanoi Police lost 0-1 to PSM Makassar in the first leg of the 2024-2025 Southeast Asian Cup C1 semi-final on the evening of April 2.

Cao Bang seeks solutions to the problem of public investment

Tân Văn |

Cao Bang - The Provincial People's Committee has just held a conference on basic construction and disbursement of public investment capital in 2025.

Northwest end of day: Sa Pa airport bypass landslide

NHÓM PV |

Landslide on Sa Pa airport bypass; Termination of billion-dollar steel project; Queuing in cold rain to buy tickets for Vietnam - Indonesia match are some of the highlights.

7,000 billion VND airport bypass in Lao Cai eroded after storm and flood

Đinh Đại |

Lao Cai - Many landslides and subsidence points on the Sa Pa Airport bypass road make it difficult for people to travel.