Strictly handle the responsibility of the Ministry of Health in 2 hospital projects in Ha Nam

TRÍ MINH |

The Government Inspectorate recommends strictly handling the responsibility of the leaders of the Ministry of Health in violations at 2 hospital projects in Ha Nam.

Handling the responsibilities of Ministers and Deputy Ministers assigned to be in charge

On April 4, the Government Inspectorate announced the Inspection Conclusion on the Inspection of the Investment Project to build a new facility 2 of Bach Mai Hospital and Viet Duc Friendship Hospital in Ha Nam province.

Through the inspection, for the Ministry of Health, the Government Inspectorate recommended reviewing responsibilities and strictly handling responsibilities according to the provisions of law for Ministers and Deputy Ministers assigned to be in charge of 2 Projects (depending on each period) related to violations and violations; reviewing according to the provisions of law for Deputy Ministers related to other violations of the Management Board of Key Medical Projects pointed out in the Inspection Conclusion;

Organize a review and strictly handle the responsibilities of the Department of Medical Equipment and Construction (now the Department of Infrastructure and Medical Equipment), Key Medical Project Management Board including director, deputy director, chief accountant, Bidding Expert Team, Appraisal Team...

Based on legal regulations, the organization determined the damage and handled the responsibility for compensation for damages in accordance with regulations with an amount of more than 354 billion VND (including the implementation of 2 projects behind approved progress due to subjective reasons leading to the suspension of construction from January 2021 to December 31, 2024, causing additional costs outside the contract, causing a temporary waste of about 253.6 billion VND).

Reviewing tax compliance of some enterprises

For the Ministry of Construction, the Government Inspectorate recommended directing the Institute of Construction Economics to review the responsibility for reviewing a number of contents of the two projects, including: investment preparation costs, financial proposals (investment project consultancy, architectural design consultancy);

Proactively coordinate with the Ministry of Health and relevant ministries and branches to strengthen specialized inspections on compliance with standards, regulations and norms in the construction sector for the investment and construction process of projects under the approval authority of ministries and branches to promptly detect, prevent and handle arising violations, especially acts of waste, violations of the law on practicing thrift and combating waste.

For the Ministry of Finance, the Inspectorate proposes to direct the Tax Department to review and examine the observance of the law on corporate income tax in 2015, 2016 of 319 Corporation, Thanh An Corporation (Implementation of Bidding Package Bidding Package), Hanoi Construction Corporation, Hong Ha Joint Stock Company, Hanoi Construction and Construction Technology Joint Stock Company (implementing the construction package of construction-01) due to the 2015 Unit in 2015 Meanwhile, the corporate income tax rate has changed (in 2015 was 22%, in 2016 was 20%), there was a risk of failing corporate income tax collection. In case of violations, the Tax Department according to its competence consider handling in accordance with the law, ensuring no loss of the state budget.

TRÍ MINH
TIN LIÊN QUAN

Intentionally violating legal regulations in 2 hospital projects in Ha Nam

|

The Government Inspectorate pointed out intentional violations of legal regulations in the implementation of 2 hospital projects in Ha Nam.

Violations, wasting thousands of billions of VND at 2 hospitals in Ha Nam

|

The inspection team inspected and evaluated nearly 3,000 items of documents to point out violations at the Bach Mai and Viet Duc Hospital projects in Ha Nam.

Transfer the file to the Ministry of Public Security after inspecting Bach Mai Hospital, Viet Duc Facility 2

|

On the afternoon of March 31, the Government Inspectorate announced the Inspection Conclusion on the Inspection of the Investment Project to build a new facility 2 of Bach Mai Hospital and Viet Duc Friendship Hospital in Ha Nam province.

Removing bottlenecks, the 329 billion VND bypass in Tuyen Quang is about to reach the finish line

|

After the problems with the site were resolved, the bypass route worth more than 329 billion VND in Tuyen Quang is accelerating to the finish line.

Removing obstacles for 2 BT projects worth nearly VND2,000 billion in Thai Nguyen

|

The Deputy Prime Minister has issued instructions to remove obstacles for 2 construction projects under BT contracts in Thai Nguyen province.

Forecast for heavy rain in the North due to cold air, some places over 50mm

|

According to the meteorological agency, the Northwest region is about to have rain, with some places having heavy rain over 50mm.

Panorama of raising the steel roof of Long Thanh airport terminal weighing 5,300 tons using a pull-up and push-up solution

|

Dong Nai - The steel roof of the Long Thanh airport passenger terminal weighing 5,300 tons was successfully lifted with a towing and pushing solution using a hydraulic shock system.

The Politburo proposed that the Party Central Committee consider disciplining Mr. Truong Hoa Binh

|

On April 4, 2025, at the Party Central Committee Headquarters, the Politburo reviewed and disciplined party members who violated and had shortcomings.

Intentionally violating legal regulations in 2 hospital projects in Ha Nam

TRÍ MINH |

The Government Inspectorate pointed out intentional violations of legal regulations in the implementation of 2 hospital projects in Ha Nam.

Violations, wasting thousands of billions of VND at 2 hospitals in Ha Nam

TRÍ MINH |

The inspection team inspected and evaluated nearly 3,000 items of documents to point out violations at the Bach Mai and Viet Duc Hospital projects in Ha Nam.

Transfer the file to the Ministry of Public Security after inspecting Bach Mai Hospital, Viet Duc Facility 2

TRÍ MINH |

On the afternoon of March 31, the Government Inspectorate announced the Inspection Conclusion on the Inspection of the Investment Project to build a new facility 2 of Bach Mai Hospital and Viet Duc Friendship Hospital in Ha Nam province.