Removing bottlenecks, the 329 billion VND bypass in Tuyen Quang is about to reach the finish line

Việt Bắc |

After the problems with the site were resolved, the bypass route worth more than 329 billion VND in Tuyen Quang is accelerating to the finish line.

In early April 2025, the approach road and the final span on the Pho Day River overpass of the Son Duong town bypass project (Tuyen Quang) are being urgently constructed after land problems have been resolved.

According to the records, workers are focusing on completing the bridge deck and railing, while the approach road section intersecting with km188 of National Highway 37 is under construction, synchronously connecting with the bridge.

The Pho Day River Overpass Bridge with a value of over VND50 billion is the largest item in the Son Duong town bypass project, over 4km long, with a total investment of over VND329 billion. The project is invested by the Department of Transport of Tuyen Quang province (now the Department of Construction), starting construction in November 2021.

Cau vuot song Pho Day giao cat voi QL.37 giup rut ngan thoi gian tu Tuyen Quang di Thai Nguyen. Anh: Viet Bac.
The Pho Day River overpass intersecting with National Highway 37 helps shorten the time from Tuyen Quang to Thai Nguyen. Photo: Viet Bac.

In 2024, the construction area of the Pho Day River Overpass will encounter problems with the clean water pipeline of Son Duong town, so the construction must be temporarily suspended while waiting for the pipeline and underground infrastructure to be relocated.

After having the site in early 2025, the construction of the final items of the Pho Day River overpass will be resumed.

Nearby, the last 400m of this road has hard rock foundation, so the construction has to take longer than expected. Because it is near residential areas, stone breaking cannot be done with blasting and can only be drilled and bulldozed by specialized machines.

Hon 400m duong nen da cung dang duoc thi cong. Anh: Viet Bac.
More than 400m of hard rock road is under construction. Photo: Viet Bac.

Currently, the drilling and breaking of hard rock is about to be completed. A representative of the construction unit (27/7 Company Limited) said that due to the hard rock foundation, the design of some items such as positive slopes, sidewalks, drainage systems, and construction progress is being accelerated.

After more than 3 years of implementation, most of the items of the Son Duong town bypass project have been completed. The entire route has basically been paved with asphalt concrete, sidewalks, lighting systems, signs and lane markings.

Phan lon tuyen duong tranh thi tran Son Duong da hoan thanh, cho dua vao su dung.
Most of the Son Duong town bypass road has been completed and is waiting to be put into use.

The first section of the route intersecting with Km183 QL.37 has now been fenced off and warning signs have been installed to prevent vehicles from entering to ensure safety during the construction process.

According to the investor, the project has now completed over 95% of the volume. The items of the river overpass and the background of 400m at the end of the route are being accelerated. It is expected that the entire route will be completed and put into use in the second quarter.2025.

Việt Bắc
RELATED NEWS

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

|

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

Police investigate the case of illegal excavation of the road slope

|

Lam Dong - The police are investigating the illegal excavation of soil on the southern bypass of Bao Loc city that Lao Dong Newspaper reported.

Tuyen Quang aims to eliminate temporary houses 4 months in advance

|

Tuyen Quang province aims to complete the program to eliminate temporary and dilapidated houses by August 2025, 4 months ahead of schedule set by the Government.

Bao Phuong Vinh wins Asian carom runner-up at home

|

Bao Phuong Vinh lost to Kim Haeng Jik with a score of 42-50 in the final of the 2026 Asian Carom Championship, held on the afternoon of May 8 in Ho Chi Minh City.

Gasoline and oil prices simultaneously decrease sharply, imports of gasoline and oil decrease sharply

|

Domestic gasoline and oil prices continuously decreased after many adjustment periods, imports of crude oil and gasoline of all kinds also decreased sharply in the second half of April 2026.

Motorbike catches fire on Binh Loi bridge during rush hour

|

Ho Chi Minh City - A motorbike suddenly caught fire fiercely while going down Binh Loi bridge, causing traffic congestion in this area.

Arbitrarily leveling, subdividing, and selling agricultural land plots in the highlands of Lang Son

|

Lang Son - Thousands of square meters of forest land and agricultural land are plowed and illegally divided into plots for sale.

Chairman of Ho Chi Minh City People's Committee Nguyen Van Duoc receives additional important task

|

Ho Chi Minh City - Chairman of Ho Chi Minh City People's Committee Nguyen Van Duoc has just been assigned to be the Head of the Investment Task Force for the city's education sector.

Deadline for handing over the Tuyen Quang - Ha Giang expressway site

Việt Bắc |

The Chairman of Tuyen Quang Provincial People's Committee requested localities to complete the handover of the entire Tuyen Quang - Ha Giang expressway site before April 5.

Police investigate the case of illegal excavation of the road slope

LAM HỒNG |

Lam Dong - The police are investigating the illegal excavation of soil on the southern bypass of Bao Loc city that Lao Dong Newspaper reported.

Tuyen Quang aims to eliminate temporary houses 4 months in advance

Việt Bắc |

Tuyen Quang province aims to complete the program to eliminate temporary and dilapidated houses by August 2025, 4 months ahead of schedule set by the Government.