Lang Son spends 19 billion VND to repair and upgrade 15 irrigation works

Khánh Linh |

Lang Son - In 2026, the province allocates 19 billion VND to repair and upgrade 15 irrigation works, serving irrigation for 404 hectares of production land.

Lang Son Provincial People's Committee has just approved a plan to repair and upgrade irrigation works using irrigation career capital in 2026.

Accordingly, the repair and upgrade plan for 2026 includes a total of 15 irrigation works, including 2 transitional works and 13 newly started works.

The total investment demand is 28 billion VND, of which 1.8 billion VND has been allocated until the end of 2025, and the 2026 capital plan is 19 billion VND. The completed projects are expected to effectively serve irrigation and drainage for 404 hectares.

For new projects started in 2026, many projects are spread across communes and wards in the province such as Khuoi Da (That Khe commune), Na Moi (Thien Hoa commune), Mo Gia dam and Cai Xoong ditch and dam (Yen Binh commune), Coc Cum (Vu Le commune), Khon Heng (Ky Lua ward), Ban Moi (Thuy Hung commune);

Phai Pan (Diem He commune), Lan Chau (Huu Lien commune), Na Dong (Tan Van commune), Na Nhan (Chien Thang commune), Trang Tung and Lang Tang (Tan Doan commune), Bo Hay (Bang Mac commune), and Chien Thang lake ditch (Thien Tan commune).

The total planned capital allocated for this group of projects in 2026 is 16.2 billion VND, serving effectively irrigation for 384 hectares.

Among these, the repair and reinforcement project of the Bo Hay ditch in Bang Mac commune has the largest planned capital in 2026, reaching 3 billion VND.

Next are Khuoi Da, Na Moi, Mo Gia dam, Cai Xoong ditch dam, Ban Moi ditch line, Lan Chau, Na Dong, Na Nhan projects... with capital from 1 billion VND or more.

Regarding the repair and reinforcement project of Chien Thang lake ditch in Thien Tan commune, although there is an investment demand of 3 billion VND, the 2026 capital plan only allocates 814 million VND; this project is expected to serve irrigation and drainage for 200 hectares, the largest in this year's list.

Khánh Linh
RELATED NEWS

Standing Vice Chairman of Lang Son Provincial People's Committee receives new assignment

|

Lang Son - Standing Vice Chairman of Lang Son Provincial People's Committee as Chairman of the Investor Selection Council of Dong Mo Industrial Cluster.

Lang Son establishes working group to remove obstacles for Mau Son cable car project 7. 352 billion VND

|

Lang Son - The Provincial People's Committee established an inter-sectoral working group to remove obstacles and promote the progress of the Mau Son eco-tourism and cable car complex project.

Lang Son transfers nearly 18.8 billion VND of estimated expenditure to the Provincial Fatherland Front

|

Lang Son - The Provincial People's Committee adjusted nearly 18.8 billion VND of the 2026 budget estimate to the Provincial Vietnam Fatherland Front Committee for management and task implementation.

Measles increases, many people actively get vaccinated before pregnancy

|

Faced with the increasing trend of suspected measles cases, many women planning to become pregnant have proactively vaccinated against the disease, protecting a safe pregnancy.

The case of the former principal collecting 15,000 VND for tutoring and being sentenced to 3 years in prison makes National Assembly deputies heartbroken

|

Referring to the case of the former principal collecting 15,000 VND for tutoring and being sentenced to 3 years in prison, delegate Pham Khanh Phong Lan (Ho Chi Minh City delegation) said that this is a "very painful" case.

Overnight control of forest fires in Lam Dong

|

Lam Dong - Dozens of people were mobilized overnight to extinguish the fire, promptly controlling the forest fire that occurred in Tan Hoi commune.

Iran wants oil tankers passing through the Strait of Hormuz paid by electronic money

|

Iran's new move shows efforts to adapt to financial sanctions pressure and global geopolitical volatility.

Stock market regains green color in last week's session

|

Cash flow returned with the focus being bank stocks, which helped the stock market regain its green color.

Standing Vice Chairman of Lang Son Provincial People's Committee receives new assignment

Khánh Linh |

Lang Son - Standing Vice Chairman of Lang Son Provincial People's Committee as Chairman of the Investor Selection Council of Dong Mo Industrial Cluster.

Lang Son establishes working group to remove obstacles for Mau Son cable car project 7. 352 billion VND

Khánh Linh |

Lang Son - The Provincial People's Committee established an inter-sectoral working group to remove obstacles and promote the progress of the Mau Son eco-tourism and cable car complex project.

Lang Son transfers nearly 18.8 billion VND of estimated expenditure to the Provincial Fatherland Front

Khánh Linh |

Lang Son - The Provincial People's Committee adjusted nearly 18.8 billion VND of the 2026 budget estimate to the Provincial Vietnam Fatherland Front Committee for management and task implementation.