Quang Ngai provincial leaders explain the reasons for a series of key projects being behind schedule

VIÊN NGUYỄN |

Quang Ngai - A series of key projects are behind schedule due to land and planning problems. The provincial leaders pledged to resolve the issue and speed up capital disbursement.

Most key projects in Quang Ngai province are invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Board, including: Tra Khuc River downstream dam; anti-landslide embankment combined with creating land fund on the North bank of Tra Khuc River (section through Tinh An commune and Tinh Long commune, Quang Ngai city); anti-landslide embankment combined with creating land fund on the North bank of Tra Khuc River (section through Tinh Long and Tinh Khe communes, Quang Ngai city); the entire route of the Dung Quat - Sa Huynh Coastal Road project; Tra Khuc 3; bridge; road connecting from Thach Bich bridge to Tinh Phong; and Hoang Sa - Doc Soi road.

Cong tac thi cong du an Hoang Sa - Doc Soi dang cham tre do mat bang ban giao con thap, nha thau chu yeu thi cong cac hang muc cau, cong. Anh: Vien Nguyen.
The construction of the Hoang Sa - Doc Soi project is being delayed due to the low handover site, the contractor mainly constructs bridge and culvert items. Photo: Vien Nguyen.

In recent times, the Standing Committee of the Provincial Party Committee and the Provincial People's Committee have regularly focused on leadership and direction; localities, relevant departments and branches have also taken drastic and responsible action in implementing key and important projects and works. However, up to now, most projects have been implemented more slowly than planned.

A series of key projects are behind schedule, leading to difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

Explaining the reason why a series of key projects in the province are slow to schedule, at the press conference in the first quarter of 2025 took place on the afternoon of April 26, Mr. Tran Hoang Tuan - Standing Vice Chairman of Quang Ngai Provincial People's Committee - frankly said: During the implementation of key projects, the province is very determined, because this is the task of the Prime Minister directly assigned to the head of the province.

However, the implementation process has encountered many difficulties in the mechanism according to the new Land Law, especially in determining specific land prices.

In addition, the issuance of a series of new compensation mechanisms and policies must go through many processes. Land use planning of localities is also slow... By March 31, 2025, these problems will be basically resolved, and the authorities will step up site clearance work.

Du an dap dang ha luu song Tra Khuc la mot trong nhung du an trong diem cua tinh Quang Ngai, khoi cong vao thang 7.2019, du kien hoan thanh nam 2021, nhung mai den nay van chua hoan thien. Anh: Vien Nguyen.
The Tra Khuc River downstream dam project is one of the key projects of Quang Ngai province, started in July 2019, expected to be completed in 2021, but has not been completed yet. Photo: Vien Nguyen.

Mr. Tran Hoang Tuan also said that the province has recently held a review meeting for each agency and individual related to each project. The Provincial Party Committee has also established a steering committee to inspect the progress and disbursement of projects.

The Chairman of the Provincial People's Committee regularly inspects the scene to urge progress. However, it is expected that it will not be until July 2025 that there will be a clean site to speed up the progress of key projects.

"The province is very determined, but must comply with the provisions of the law" - Mr. Tran Hoang Tuan said.

VIÊN NGUYỄN
TIN LIÊN QUAN

The bridge with the second largest total investment capital in Quang Ngai is about to be built

|

Tra Khuc 1 Bridge has a total investment of VND2,199 billion, spanning Tra Khuc River, Quang Ngai Province, expected to start construction in October 2025.

Quang Ngai seeks to remove difficulties for two key projects worth VND2,194 billion

|

Quang Ngai speeds up site clearance for two key projects, the Thach Bich - Tinh Phong connecting road and Tra Khuc Dam.

Quang Ngai hopes to have a special mechanism to remove difficulties for real estate projects

|

Quang Ngai has reported to the Prime Minister... to consider and study specific mechanisms to remove difficulties for real estate projects in the province.

backpackers rush to Ho Chi Minh City to celebrate the 50th anniversary of the new one

|

Towards the 50th anniversary of the Liberation of the South and National Reunification Day, many tourists want to be present in Ho Chi Minh City on the occasion of the April 30 holiday.

At the Noi Bai - Lao Cai Expressway repair site

|

The repair of the Noi Bai - Lao Cai Expressway aims to ensure safety for vehicles participating in traffic.

House fire at dawn in Hanoi, 3 people died

|

Hanoi - 3 people died, 1 person was injured in a 3-storey house fire at dawn on Dinh Cong Ha Street, Hoang Mai District.

Mr. Zelensky admits Ukraine cannot conquer Crimea by force

|

Ukrainian President Volodymyr Zelensky frankly admitted that the country does not have enough military power to conquer Crimea by force.

Hanoi to auction a series of land plots, starting from 2.9 million VND/m2

|

Hanoi - It is expected that in early May, many districts in Hanoi will organize land use rights auctions.

The bridge with the second largest total investment capital in Quang Ngai is about to be built

VIÊN NGUYỄN |

Tra Khuc 1 Bridge has a total investment of VND2,199 billion, spanning Tra Khuc River, Quang Ngai Province, expected to start construction in October 2025.

Quang Ngai seeks to remove difficulties for two key projects worth VND2,194 billion

VIÊN NGUYỄN |

Quang Ngai speeds up site clearance for two key projects, the Thach Bich - Tinh Phong connecting road and Tra Khuc Dam.

Quang Ngai hopes to have a special mechanism to remove difficulties for real estate projects

VIÊN NGUYỄN |

Quang Ngai has reported to the Prime Minister... to consider and study specific mechanisms to remove difficulties for real estate projects in the province.