Quang Ngai seeks to remove difficulties for two key projects worth VND2,194 billion

VIÊN NGUYỄN |

Quang Ngai speeds up site clearance for two key projects, the Thach Bich - Tinh Phong connecting road and Tra Khuc Dam.

The road project connecting Thach Bich Bridge to Tinh Phong has a total length of 6.11 km. Of which, the main route is more than 4.82 km long, the branch route is more than 1.29 km long. The total investment is more than 694 billion VND, with implementation period from 2019 to 2025.

Currently, according to the investor's report, localities have only handed over 3.57 km of site to contractors for construction, reaching 58.4%. Of which, the section through Quang Ngai city is 2.5/3.04 km, reaching 82%; the section through Son Tinh district is 1.07/3.06 km, reaching 35%. There are still 208 households with 5.69 hectares that have not yet established a compensation, support and resettlement plan.

Up to now, the construction value of VND 190 billion, equivalent to more than 46% of the contract value. The implementation plan in the coming time, agencies and units continue to focus on speeding up the construction of the segments that have been handed over the ground, especially focusing on the intersection positions of the project with Highway 1 and Provincial Road 622C.

The road project connecting Thach Bich Bridge to Tinh Phong is a key project with an important role and significance. After completion, the project will help reduce traffic congestion through National Highway 1, create regional linkages, exploit land funds on both sides, and create momentum for local economic and social development.

During the project progress inspection on April 21, Mr. Nguyen Hoang Giang - Chairman of the People's Committee of Quang Ngai province requested relevant agencies and units to urgently coordinate to remove difficulties and obstacles in site clearance to speed up construction progress.

Quang Ngai City must complete site clearance in May 2025. Son Tinh District to be completed before June 15, 2025. Mr. Nguyen Hoang Giang emphasized that according to the general policy, by the end of June 2026, the district-level administrative unit will be dissolved, so compensation must be urgently worked on. If it continues after this time, it will cause many difficulties. The provincial leaders will monitor and inspect the implementation of this project more regularly. The project investor urges contractors to mobilize resources to construct as much as possible, and the site will be available.

In addition to the above project, the Tra Khuc River downstream dam project has a total investment of nearly 1,500 billion VND, implemented since 2019, expected to be completed in 2021. However, after 6 years, the project is still in a state of disrepair. According to the investor's explanation, the reason is due to land clearance problems.

Du an dap dang ha luu song Tra Khuc van dang do sau 6 nam thi cong. Anh: Vien Nguyen.
The Tra Khuc River downstream dam project is still unfinished after 6 years of construction. Photo: Vien Nguyen.

The ground problems are mainly due to previous authorities, the competent authority has approved for land users to separate the parcel, raise the purpose of land use in large quantities. After that, through the inspection, some shortcomings were discovered and the authorities advised to cancel some of the land use right certificates due to the wrong purpose of the regulations. Since then, many households have not agreed to hand over the ground. Currently, the unit has grouped these households to gradually remove obstacles and accelerate the site clearance.

According to the investor, up to now, the resettlement has been arranged for people in the affected area in 2 positions. It is the Iricitarian resettlement area of ​​23 lots and the I (expansion) resettlement area is investing in 38 lots in Truong Quang Trong ward. Up to now, the units have basically completed the work items for the scope of handing over the ground. Accumulated implementation value reached VND 1,130 billion, reaching 88.4% of the contract value.

VIÊN NGUYỄN
TIN LIÊN QUAN

The fate of the land is planned to be a love park in Quang Ngai

|

From the planning of a love park to the school project, the golden land in Quang Ngai City is still abandoned for 10 years.

The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

|

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

Confused when implementing, many key projects in Quang Ngai are sluggish

|

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.

Allocate 1,000 billion VND to deploy additional expressway connecting to Long Thanh airport

|

Ba Ria - Vung Tau - The Provincial People's Council has approved the allocation of 1,000 billion VND to deploy the expressway connecting Long Thanh and Ho Tram in 2025.

Vietnam Military History Museum is crowded with visitors before the grand ceremony on April 30

|

Before the grand ceremony on April 30, the Vietnam Military History Museum welcomed a large number of visitors, customers lined up to buy tickets.

Launching the Press Center to serve the 50th anniversary of the Liberation of the South and National Reunification

|

Ho Chi Minh City - The Press Center aims to improve the effectiveness of propaganda and support domestic and international reporters to work at the 50th anniversary of the Liberation of the South and National Reunification Day.

Management loopholes, fake functional foods rampant

|

Management loopholes make fake functional foods rampant, consumers become victims.

Vietnam's import and export of goods increased by 16.5%

|

From the beginning of the year to the end of April 15, 2025, Vietnam's total import-export turnover of goods reached 237.97 billion USD, up 16.5% over the same period in 2024.

The fate of the land is planned to be a love park in Quang Ngai

VIÊN NGUYỄN |

From the planning of a love park to the school project, the golden land in Quang Ngai City is still abandoned for 10 years.

The site of the nearly 1,500 billion VND dam project in Quang Ngai is deserted

VIÊN NGUYỄN |

Quang Ngai - The Tra Khuc River downstream dam project is expected to be completed in 2021, but is still unfinished, the construction site is deserted.

Confused when implementing, many key projects in Quang Ngai are sluggish

Viên Nguyễn |

Many key projects in Quang Ngai province are behind schedule, causing difficulties in disbursing public investment capital, directly affecting the province's economic growth rate in 2025.