On June 9, according to information from Vietnam Airports Corporation (ACV), in package 5.10 for the construction of the Long Thanh International Airport passenger terminal (abbreviated as Long Thanh airport), the installation of a fire protection system is being implemented on schedule, according to the overall plan of the project.
According to ACV, the construction of installing a fire prevention and fighting system is an important item in the construction process of large-scale projects such as the passenger terminal at the Long Thanh airport project.
Accordingly, this process requires strict compliance with technical regulations as well as current legal regulations on fire safety.
The main items include: indoor Volleyball Fire Fighting System, Outdoor Fire Fighting System, Sprinkler System, Special Gas Fire Fighting System (fm200, n2).
The inspection and acceptance work in each stage is being seriously implemented, with close coordination between the Project Management Board and supervision consultants, to ensure construction quality and full compliance with fire safety standards for the entire project.
Package 5.10, construction of Long Thanh airport passenger terminal strives to complete the construction before December 31, 2025, then complete the installation of the equipment system for testing.
The consortium of contractors mobilized nearly 5,000 human resources and more than 1,000 construction equipment. Currently, this package has completed the construction of the underground reinforced concrete structure, floors 1-4, rough construction, paint completion, ceilings...