Construction of the second runway at Long Thanh airport began at the end of May

HÀ ANH CHIẾN |

Dong Nai - ACV Airport Corporation said it is completing procedures to strive to start the second runway at Long Thanh airport on May 30.

On May 21, a working group of the Ministry of Construction led by Minister Tran Hong Minh inspected the construction sites of the Bien Hoa - Vung Tau expressway project and Long Thanh airport in Dong Nai province.

Bo Truong Bo Xay dung Tran Hong Minh kiem tra 2 du an cao toc Bien Hoa - Vung Tau, san bay Long Thanh o Dong Nai. Anh: HAC
Minister of Construction Tran Hong Minh inspected the two projects of Bien Hoa - Vung Tau Expressway and Long Thanh Airport in Dong Nai. Photo: HAC

For the Bien Hoa - Vung Tau expressway project, according to Project Management Board 85 (Ministry of Construction), the Bien Hoa - Vung Tau expressway component project 2 (more than 18km long through Long Thanh district) has reached 51% of output. The most difficult thing at present is land clearance problems, especially the technical infrastructure system (14 locations of high-voltage, medium-voltage and low-voltage power lines that need to be relocated and lowered).

Component project 1, Bien Hoa - Vung Tau Expressway (more than 16km long through Bien Hoa City and Long Thanh District) is also accelerating the progress with 34 construction teams.

On May 21, the working group also inspected the site of the bidding packages at the Long Thanh airport project.

According to the Long Thanh Airport Project Management Board, up to now, package 4.6 has basically completed the runway item, the signal lighting system has been lit, and the operation has been successfully tested.

Package 5.10, construction of Long Thanh airport passenger terminal also strives to complete the construction before December 31, then complete the installation of the equipment system for testing. The consortium of contractors mobilized nearly 5,000 human resources and more than 1,000 equipment under construction, with a total completed value of about VND 13,504 billion. Currently, the underground reinforced concrete structure, floors 1-4, and rough construction have been completed at 72%, and painting, ceilings are being completed...

As for package 6.12, the construction of the traffic route connecting Long Thanh airport has so far opened to technical traffic on T1 road, and is continuing to construct the bridge and T2 road, completing asphalt pavement, planting trees in sections...

At the inspection point, Minister Tran Hong Minh visited, encouraged and presented gifts to engineers and construction workers "3 shifts, 4 teams" day and night at the 2 projects.

Bo truong Tran Hong Minh tang qua cho cac can bo, ky su thi cong tai cong truong. Anh: HAC
Minister Tran Hong Minh presented gifts to officers and construction engineers at the construction site. Photo: HAC

After the field inspection, Minister of Construction Tran Hong Minh and the working delegation of the Ministry of Construction worked with the People's Committee of Dong Nai province and investors and contractors related to the two projects of Long Thanh airport and Bien Hoa - Vung Tau expressway.

According to Vietnam Airports Corporation (ACV), runway No. 1 has been completed, 3 months ahead of schedule and has successfully tested the traffic light system. For the implementation of the second runway, ACV quickly selected consultants in special cases to establish and review technical designs. The dossier has also been appraised by the Ministry of Construction, and ACV is currently implementing the next steps, striving to start the second runway on May 30.

Regarding connecting transportation, ACV proposed to soon expand the Ho Chi Minh City - Long Thanh expressway to 10 lanes as planned to ensure effective operation and conversion of international flights from Tan Son Nhat airport to Long Thanh.

Mr. Ho Van Ha - Vice Chairman of Dong Nai Provincial People's Committee said that the locality will strive to complete the site as soon as possible and quickly relocate technical infrastructure so that units can speed up construction.

Also at the meeting, contractors constructing airports and expressways requested Dong Nai province leaders to create conditions for early support of soil and rock materials to meet the project's progress requirements.

HÀ ANH CHIẾN
TIN LIÊN QUAN

The T1 traffic route connecting Long Thanh airport is ready for technical traffic

|

Dong Nai - Route T1 under package 6.12 of the Long Thanh International Airport project (abbreviated as Long Thanh airport) is ready to open to technical traffic.

Long Thanh Airport proves the capacity of Vietnamese officials and engineers

|

The successful construction of difficult items in the Long Thanh airport project as well as the determination to complete the basic construction progress before December 31, 2025, proving the management capacity as well as the technical qualifications of the Vietnamese engineering team.

The Long Thanh airport runway lighting system is officially lit up

|

Dong Nai - The traffic light system of Long Thanh International Airport runway (abbreviated as Long Thanh airport) officially lit up on the night of April 26.

Ngan 98 responds to suspicions of selling poor quality weight loss drugs, authorities intervene

|

DJ Ngan 98 responded to the fact that the weight loss products she sells and advertises are suspected to be of poor quality.

The incident at Song Doc oil and gas field has been controlled

|

The incident at Song Doc mine, off the coast of Southwest Vietnam, has been controlled and has not affected the environment.

VinFuture 2025 reaches 14,772 nominating partners, 12 times higher after 5 years

|

Hanoi - VinFuture 2025 has received 1,705 nominations globally, reaching 14,772 nominating partners - an increase of 12 times after the 5th season.

Need to add 37,300 grades to preschool teacher staff for the 2026-2030 period

|

The National Assembly's Committee on Culture and Society determined that it is necessary to add 37,300.000 preschool teachers in the period of 2026-2030.

US holds grand parade with 6,700 soldiers and heavy equipment

|

In addition to the large number of soldiers and heavy military equipment, the US will also bring a number of animal species to the upcoming parade and only 1 dog.

The T1 traffic route connecting Long Thanh airport is ready for technical traffic

HÀ ANH CHIẾN |

Dong Nai - Route T1 under package 6.12 of the Long Thanh International Airport project (abbreviated as Long Thanh airport) is ready to open to technical traffic.

Long Thanh Airport proves the capacity of Vietnamese officials and engineers

HÀ ANH CHIẾN |

The successful construction of difficult items in the Long Thanh airport project as well as the determination to complete the basic construction progress before December 31, 2025, proving the management capacity as well as the technical qualifications of the Vietnamese engineering team.

The Long Thanh airport runway lighting system is officially lit up

HÀ ANH CHIẾN |

Dong Nai - The traffic light system of Long Thanh International Airport runway (abbreviated as Long Thanh airport) officially lit up on the night of April 26.