Flexibility in construction of Quang Ngai - Hoai Nhon expressway

VIÊN NGUYỄN |

Quang Ngai - Hoai Nhon Expressway mobilizes maximum human resources and construction equipment even during the rainy season to ensure project progress and quality.

Highly concentrated on digging mountains and drilling tunnels

It is currently the rainy season. However, at the construction site of the Quang Ngai – Hoai Nhon Expressway project, officers, engineers and workers are still being mobilized to the maximum to complete the set goals.

Nha thau dat muc tieu thong ham so 3 vao ngay 30.4.2025, hoan thanh du an trong nam 2025. Anh: Vien Nguyen
The contractor aims to open tunnel No. 3 on April 30, 2025, completing the project in 2025. Photo: Vien Nguyen

Tunnel No. 3 has now dug nearly 2,000m in the left tunnel and more than 2,180m in the right tunnel. Engineers and workers are working hard in difficult construction conditions to strive to clear Tunnel No. 3 before April 30, 2025.

Talking to reporters, Mr. Nguyen Trung Thanh - a worker on the Quang Ngai - Hoai Nhon expressway said: "The heavy rain lasted for a long time, so the construction process encountered difficulties, but we tried our best to overcome them so that the work went smoothly and fully met the schedule."

In the rainy season in the Central region, road construction encountered obstacles, so contractors flexibly shifted construction directions to building bridges and culverts, focusing on digging mountains and drilling tunnels.

Mr. Hoang Dinh Thinh - Head of the North Steering Committee of Tunnel No. 3 - Deo Ca Group said: "The construction team of Tunnel No. 3 mobilized more personnel as well as increased 50 motor vehicles to ensure the progress set by the Prime Minister".

Ready to remove obstacles

To carry out the peak period of 500 days and nights to complete 3,000km of expressway, the investor and contractor of Quang Ngai - Hoai Nhon expressway mobilized nearly 4,200 personnel and 1,700 machines and equipment, implementing construction "3 shifts and 4 teams" on the entire route. Due to the urgent project progress requirement to open the tunnel by April 30, 2025 and complete the project in 2025 as launched by the Prime Minister in the emulation campaign "500 days to complete 3,000km of North-South expressway", the contractor organized the construction in a rolling manner, spraying concrete mortar, installing waterproofing and reinforcing the tunnel shell as the tunnel was dug.

Mot so doan vo ham so 3 duoc hoan thien trong dieu kien vua dao vua thi cong de dap ung tien do du an. Anh: Vien Nguyen
Some sections of tunnel 3 were completed under excavation and construction conditions to meet the project schedule. Photo: Vien Nguyen

For the tunnel section alone, engineers work in shifts 24/7. Quang Ngai Province also closely coordinates with the investor and construction unit to resolve remaining problems.

Speaking to reporters, Mr. Nguyen Dang Vinh - Chairman of Tu Nghia District People's Committee expressed: "During the construction process of the Quang Ngai - Hoai Nhon expressway project, if there are any problems that require the contractor and construction unit to coordinate with the government, the district will always accompany the people, investors and contractors to focus on directing the handling of problems."

To date, the Quang Ngai - Hoai Nhon expressway project has achieved a construction output of more than 6,400 billion VND and strives to complete about 61% of the total contract volume in 2024. Of which, tunnel No. 1 and tunnel No. 2 will be completed, 63/77 bridges will be completed, and asphalt concrete will be deployed simultaneously on all 3 packages XL1, XL2 and XL3 to complete the project by the end of 2025.

According to Mr. Tran Phuoc Hien - Vice Chairman of the People's Committee of Quang Ngai province, "Quang Ngai is very happy to have contributed and fulfilled the commitment to the Prime Minister in the story to ensure the ground for construction, and at the same time active materials for construction, contributing to the project to the destination as planned".

VIÊN NGUYỄN
TIN LIÊN QUAN

Quang Ngai will completely handle hundreds of behind-schedule projects

|

In the coming time, Quang Ngai will support any project with goodwill from investors. However, for investors who are procrastinating, the province will inspect and terminate the project.

The largest bridge on the Quang Ngai - Hoai Nhon highway is about to be completed

|

Song Ve Bridge, the largest bridge on the Quang Ngai - Hoai Nhon expressway, is pouring concrete on the final span, urgently completing important items before the rainy season.

Gold prices fluctuate, people wait for opportunities to buy gold

|

On December 16, the price of plain round gold rings increased compared to last week. In Hanoi, buyers still face many difficulties due to the scarcity of sales.

Hanoi land prices reach average of 70 million VND/m2

|

Hanoi - The average selling price of land in Hanoi in November 2024 is 70 million VND/m2, an increase of 32% compared to January 2023.

Will veteran artists appear in Tao Quan 2025?

|

The first information about Tao Quan 2025 attracts the attention of the audience.

Lao Dong Newspaper received Certificate of Merit from the Central Propaganda Department

|

The Central Propaganda Department awarded Certificates of Merit to 10 collectives with outstanding achievements in journalism work in 2024, including Lao Dong Newspaper.

Department of Education talks about handling the first grade teacher who taught extra classes

|

Ha Tinh - Regarding the proposal to handle the first grade teacher of Tran Phu Primary School for violating extra teaching, the representative of the Department of Education and Training of Ha Tinh City has provided specific information.

Thousands of students in Binh Dinh have to stay home from school due to flooding

|

Binh Dinh - Tuy Phuoc District has agreed to let about 4,000 students stay home from school because many schools were flooded after the rain.

Quang Ngai will completely handle hundreds of behind-schedule projects

VIÊN NGUYỄN |

In the coming time, Quang Ngai will support any project with goodwill from investors. However, for investors who are procrastinating, the province will inspect and terminate the project.

The largest bridge on the Quang Ngai - Hoai Nhon highway is about to be completed

VIÊN NGUYỄN |

Song Ve Bridge, the largest bridge on the Quang Ngai - Hoai Nhon expressway, is pouring concrete on the final span, urgently completing important items before the rainy season.

Cao tốc Quảng Ngãi - Hoài Nhơn tăng tốc ngay cả trong dịp lễ

VIÊN NGUYỄN |

Kỳ nghỉ lễ Quốc khánh 2.9 kéo dài 4 ngày. Tuy nhiên, hàng nghìn kỹ sư, công nhân vẫn miệt mài làm việc xuyên lễ trên cao tốc Quảng Ngãi - Hoài Nhơn.