Revealing the route of the 10-lane road project in Hanoi after site clearance

HỮU CHÁNH |

Hanoi - The Tay Thang Long road project, the section from Ring Road 3 to Van Tien Dung road, has basically completed site clearance, and the project route has been revealed.

The Tay Thang Long trunk road is about 34.17km long, starting point at Vo Chi Cong street, ending point intersecting National Highway 32, passing through 10 communes and wards.

The current investment status of the entire route is divided into 9 sections, including 3 sections that have been put into operation, 2 sections under construction, 1 section preparing to start construction and 3 sections under research and investment preparation.

To date, about 6.08km has been completed and put into operation; about 9km is under construction; preparations for the commencement of the Tay Thang Long - Ring Road 3 underpass, 0.92km long (expected in August 2026); and at the same time, preparations for investment in the remaining route sections are being implemented.

s
Tay Thang Long road section from Ring Road 3 to Van Tien Dung road (Hanoi) has basically completed site clearance after many years of obstacles. Photo: Song Huu
s
s
Some works within the project are being demolished. Photo: Song Huu

For the section from Ring Road 3 to Van Tien Dung road, it is more than 3.2km long, with a total investment of more than 2,300 billion VND, of which site clearance costs are about 1,673 billion VND.

The section from Ring Road 3 to Van Tien Dung street was started many years ago, but due to problems in site clearance, it is behind schedule.

It will not be until June 2026 that site clearance work will be basically completed.

According to Dong Ngac Ward People's Committee, to date, 100% of agricultural land has been cleared.

Regarding residential land, all 454 households have been counted and mobilized to hand over land. Many households have received compensation money. Demolition work is being implemented, expected to be completed in June 2026.

Regarding construction work, Dong Ngac Ward People's Committee said that the volume of the entire route has only reached about 65%. Some items such as bridges, drainage systems and technical trenches have been deployed, but the overall progress is still slow.

s
Some sections are under construction. Photo: Song Huu
s
The bridge across the Nhue River has revealed its shape. Recorded in the afternoon of June 23, there was no construction activity here. Photo: Song Huu
s
Construction materials are gathered on the bridge over the Nhue River. Photo: Song Huu
s
The bridge railing system has been installed. Photo: Song Huu
s
The project site is adjacent to the West bank of the Nhue River. Photo: Song Huu
s
Tay Thang Long road section from Ring Road 3 to Van Tien Dung road has a scale of 10 lanes. Photo: Song Huu

The section from Ring Road 3.5 to Dan Hoai canal (belonging to O Dien commune) is 5.8km long, with a total investment of 1,298 billion VND.

To date, the land area recovered for site clearance has reached over 95%; site clearance is expected to be completed in June 2026 and the project to be completed in the fourth quarter of 2026.

Regarding the Tay Thang Long road project, Politburo Member, Secretary of the Hanoi Party Committee Tran Duc Thang requested the Party Committee and People's Committee of the City to direct departments, branches, and localities to focus on accelerating the implementation progress of the entire route, ensuring synchronous investment and interconnection of the entire route to Ring Road 5 (Vinh Thinh bridge), striving to complete it in 2027.

Hanoi Party Secretary Tran Duc Thang also requested to urgently complete investment procedures for the remaining route sections; agreed to assign the City Traffic Construction Investment Project Management Board as the focal point for implementing the overall project.

HỮU CHÁNH
RELATED NEWS

Recovering 3, 472.6m2 of land to implement the Tay Thang Long road project in Hanoi

|

Hanoi - Dan Phuong Commune People's Committee has just issued a decision to recover a total area of 3, 472.6m2 to implement the Tay Thang Long road construction investment project.

Traffic police pave the way to take a child with convulsions to the emergency room

|

Quang Tri - The patrol team of Dakrong Traffic Police Station used specialized vehicles to open roads and support bringing a 3-year-old child who was having convulsions to the hospital in time.

Former Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong becomes Secretary of Saigon Ward

|

Ho Chi Minh City - After being dismissed from the position of Vice Chairman of Ho Chi Minh City People's Committee, Mr. Bui Xuan Cuong received a decision to become Secretary of the Party Committee of Saigon Ward.

Ronaldo breaks a series of records at World Cup 2026

|

Cristiano Ronaldo continues to make his mark at the 2026 World Cup when he scored a double in the first half of the match between Portugal and Uzbekistan in the second match of Group K.

Gold prices fall nearly 2% as the USD hits a one-year high

|

Gold prices fell nearly 2% as the USD rose to its highest level in a year.

Lawyers talk about the basis for sanctioning violations of regulations on child safety seats from July 1st

|

From July 1, the regulations on child safety seats take effect, but lawyers recommend caution when identifying and penalizing violations.

Đề xuất chấm dứt hợp đồng 2 gói thầu đường Tây Thăng Long

Minh Hạnh |

Hà Nội đề xuất chấm dứt, thanh lý hợp đồng với hai nhà thầu thi công gói thầu số 14 dự án đường Tây Thăng Long do khó khăn tài chính.

Nguyên nhân khiến người dân chưa thể bốc thăm tái định cư dự án đường Tây Thăng Long

Anh Tuấn |

Đợt bốc thăm tái định cư lần thứ hai của của dự án đường Tây Thăng Long chưa thể triển khai là do địa phương đang chờ văn bản chấp thuận một số cơ chế đặc thù

Recovering 3, 472.6m2 of land to implement the Tay Thang Long road project in Hanoi

Anh Tuấn |

Hanoi - Dan Phuong Commune People's Committee has just issued a decision to recover a total area of 3, 472.6m2 to implement the Tay Thang Long road construction investment project.