Opening an inter-port road more than 15 km long to take advantage of Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Nhon Trach inter-port road more than 15 km long connecting the industrial park to the seaport, taking advantage of Long Thanh airport.

On March 14, according to Dong Nai Provincial People's Committee, the Nhon Trach inter-port road construction project has been handed over 36 hectares out of a total of more than 51 hectares of land for deployment, reaching about 70%.

According to the plan, the above road is more than 15 km long, the starting point of the route connects to the boundary of Ong Keo Industrial Park and the ending point of the route connects to the road to Viet Thuan Thanh port.

The Nhon Trach inter-port road construction project phase 1 has a total investment of more than 2,600 billion VND in Dai Phuoc commune, Dong Nai province.

In phase 1, the project deploys the construction of a section of more than 8.8 km (section 1 is 6.9 km long with 8 lanes and section 2 is 1.9 km long with 4 lanes).

In addition to the road section, the project also invests in building 5 bridges on the route.

The project aims to connect the port system according to the plan, improve exploitation capacity, and at the same time promote the development of transport infrastructure, form new residential areas, attract investment in industrial parks, contributing to the development of Nhon Trach urban area and Dong Nai province; Opening up opportunities for modern riverside urban development associated with the goal of green and smart development.

In particular, the route will take advantage of the advantage when Long Thanh airport is put into operation, forming a port - logistics - industrial park - riverside urban linkage chain.

Up to now, the construction unit has carried out sand pumping to treat the 650m long roadbed and excavated unsuitable soil layers to spread earthenware, pumping sand for the next section about 300m long.

HÀ ANH CHIẾN
RELATED NEWS

Dong Nai approves architectural competition results for the Political - Administrative Center

|

Dong Nai - On March 13, the Provincial People's Committee just decided to approve the results of the architectural design competition for the Provincial Political - Administrative Center area.

Technical opening of Hieu Liem bridge across the Dong Nai River on April 30th

|

Dong Nai - Hieu Liem Bridge across the Dong Nai River, the section of Tri An commune, is planned to be technically opened to traffic on April 30th.

200MW hydropower plant project in Dong Nai entangled with site clearance

|

Dong Nai - On March 12, the Provincial People's Committee worked with relevant units on the progress of site clearance for the Tri An Hydropower Plant expansion project.

Dong Nai surveys and maps to reclaim 52 hectares of land for inter-port road

|

On December 1, information from the People's Committee of Dong Nai province said that the inter-port road project in Nhon Trach district is being surveyed for land acquisition.

Stock market continues to bottom out

|

The stock market continues to face many risks from oil price fluctuations and global macroeconomic factors.

Poland faces risk of leaving the EU, Prime Minister Tusk warns

|

Prime Minister Donald Tusk warned that the possibility of Poland leaving the European Union EU (Polexit) is no longer a distant scenario.

Actress Amy Madigan Young emotionally receives Oscar for the first time

|

The 2026 Oscar Awards honored Amy Madigan Young in the Best Supporting Actress category.

The hardships of female nurses in a place fighting for life every minute

|

In the intensive care units of central hospitals, each shift is a race against time, requiring the resilience and endurance of female nurses.

Dong Nai approves architectural competition results for the Political - Administrative Center

HÀ ANH CHIẾN |

Dong Nai - On March 13, the Provincial People's Committee just decided to approve the results of the architectural design competition for the Provincial Political - Administrative Center area.

Technical opening of Hieu Liem bridge across the Dong Nai River on April 30th

HÀ ANH CHIẾN |

Dong Nai - Hieu Liem Bridge across the Dong Nai River, the section of Tri An commune, is planned to be technically opened to traffic on April 30th.

200MW hydropower plant project in Dong Nai entangled with site clearance

HÀ ANH CHIẾN |

Dong Nai - On March 12, the Provincial People's Committee worked with relevant units on the progress of site clearance for the Tri An Hydropower Plant expansion project.

Dong Nai surveys and maps to reclaim 52 hectares of land for inter-port road

HÀ ANH CHIẾN |

On December 1, information from the People's Committee of Dong Nai province said that the inter-port road project in Nhon Trach district is being surveyed for land acquisition.