Waiting for compensation land price for project over 7,200 billion in Can Tho

YẾN PHƯƠNG |

Can Tho is determined in site clearance for the Project to Upgrade and Expand National Highway 91 (Km0 - Km7) to start construction as planned.

The Project to Upgrade and Expand National Highway 91 (section from Km0 - Km7) was approved by the People's Committee of Can Tho City in July 2024, with the City Construction Investment Project Management Board as the investor, with a total investment of more than 7,237 billion VND.

According to the Can Tho City Construction Investment Project Management Board, up to now, the Project Management Board has completed the selection and implementation of 5 bidding packages; is continuing to select the remaining bidding packages; and is expected to start the project in the second quarter of 2025.

The city is currently urgently implementing the project to start construction as planned. However, the project is facing difficulties and obstacles. Among them, there is no specific land price to calculate compensation; there is no unit price for compensation for crop damage when the State reclaims land.

Nhieu vi tri tai Quoc lo 91 xuong cap, ngap nuoc khi trieu cuong. Anh: Yen Phuong
Many locations on National Highway 91 are degraded and flooded during high tide. Photo: Yen Phuong

As a resident whose house is affected by the project, Mr. Tran Van Thanh (Tra An ward, Binh Thuy district) said that the relevant authorities have completed the measurement, the local people are very sympathetic and supportive, now they are just waiting for a reasonable compensation price from the project.

Similarly, Ms. Nguyen Thi Nhan (Tra An Ward, Binh Thuy District) shared, “We are waiting for the compensation price and then ready to hand over the site. I also hope the project will be implemented quickly so that the landscape is clean and beautiful and traffic accidents on this road section are limited.”

Anh: Ta Quang
Households affected by the project are waiting for compensation land prices soon. Photo: Ta Quang

According to the report of the City Land Fund Development Center, there are about 994 households, individuals and 84 organizations affected by the project (in Ninh Kieu and Binh Thuy districts). The total cost of site clearance is about 5,556 billion VND, the need for resettlement is about 300 plots.

Ms. Do Thi Nu - Vice Chairman of Tra An Ward People's Committee, Binh Thuy District - informed that for the project of Upgrading and Expanding National Highway 91 (section from Km0 - Km7), 100% of households and organizations have agreed with the measurement data, and are currently waiting for the project's compensation price. When the price list is available, the locality will coordinate to implement the next steps according to regulations.

Quoc lo 91 nhin tu tren cao. Anh: Ta Quang
National Highway 91 in Can Tho seen from above. Photo: Ta Quang

At the recent meeting to check the progress of the National Highway 91 Upgrade and Expansion Project (section from Km0 - Km7), Can Tho City Party Secretary Nguyen Van Hieu requested Party committees and local authorities at all levels to strengthen inspection, monitoring of progress and urging project implementation; focusing on land acquisition and infrastructure construction for resettlement areas.

According to Secretary of the City Party Committee Nguyen Van Hieu, the people have agreed with the project, now they are just waiting for the compensation price; it is necessary to ensure the legitimate rights and interests of the people. The Secretary requested that localities soon issue and post specific compensation land prices to calculate compensation according to the commitment, complete site clearance work soon, and start the project as planned.

Recently, the People's Committee of Can Tho City issued a Decision on the advance capital plan for the project to Upgrade and Expand National Highway 91 (section from Km0 - Km7). Accordingly, the City People's Committee assigned more than 410 billion VND in advance capital plan for this project from local budget sources.

This is a Group A project, a level 1 road traffic project, with implementation time from 2023 to 2027. The overall goal of the project is to complete the traffic infrastructure, striving to build Can Tho into a modern and civilized city, basically becoming an industrial city.

YẾN PHƯƠNG
RELATED NEWS

Can Tho advances more than 410 billion VND to upgrade 7km of National Highway 91

|

Can Tho - Can Tho City People's Committee has allocated more than 410 billion VND in advance capital for the project to upgrade and expand National Highway 91 (section from Km0 - Km7).

Chairman of Lam Dong Provincial People's Committee requested an investigation into the case of a dam burst causing flash floods

|

Lam Dong - Chairman of the Provincial People's Committee directed competent agencies to focus on investigating and clarifying the cause of the water reservoir burst in village 2, Tuy Phong commune.

Revealing the ecosystem of hundreds of billions of VND of actor Truong Ngoc Anh

|

Before being arrested, Truong Ngoc Anh had built a business ecosystem worth hundreds of billions of VND, from real estate, advertising, beauty rights, entertainment, etc.

Urgently rescue people in a house buried by landslides in Da Nang

|

Da Nang - Severe landslides buried 6 houses, authorities saved 1 person.

Commune government in Gia Lai speaks out about the case of large trees rising unusually in the middle of the Ayun River bank

|

Gia Lai - Phu Thien commune authorities determined that the large piece of wood that had risen on the banks of the Ayun River had been submerged in water for a long time, with no signs of being newly sawed and the owner unknown.

Cold air intensifies and causes rain, forecast coldest day

|

Due to the strengthening of cold air, the temperature continued to decrease on the night of November 3 and November 4. The mountainous areas of the North will have severe cold, with temperatures dropping below 15 degrees Celsius.

New road to the East of Ho Chi Minh City opens more direction, reducing pressure on Vo Nguyen Giap traffic axis

|

The Vo Nguyen Giap parallel road has just been put into operation, opening a new traffic direction, contributing to reducing pressure on the East of Ho Chi Minh City.

Banning all cars across the Lo River bridge in Phu Tho

|

Phu Tho - The provincial Department of Construction has just announced the adjustment of traffic flow through the Lo River Bridge, Doan Hung Commune.

Can Tho advances more than 410 billion VND to upgrade 7km of National Highway 91

YẾN PHƯƠNG |

Can Tho - Can Tho City People's Committee has allocated more than 410 billion VND in advance capital for the project to upgrade and expand National Highway 91 (section from Km0 - Km7).

Hiện trạng 7km quốc lộ sắp nâng cấp hơn 1.000 tỉ đồng/km

Tạ Quang - Yến Phương |

Cần Thơ - Dự án nâng cấp, mở rộng Quốc lộ 91 ở Cần Thơ có tổng mức đầu tư gần 7.238 tỉ đồng. Như vậy, mỗi 1 km thì chi phí phải bỏ ra là 1.000 tỉ đồng.

Dự kiến chi hơn 7.200 tỉ đồng nâng cấp, mở rộng Quốc lộ 91 thành phố Cần Thơ

Huy Hùng |

Bộ Tài nguyên và Môi trường đang tham vấn môi trường dự án “Nâng cấp, mở rộng Quốc lộ 91 (đoạn từ Km0 – Km7), thành phố Cần Thơ". Dự án đi qua địa bàn quận Ninh Kiều và quận Bình Thủy, thành phố Cần Thơ.