Highway 91
O Mon bridge on National Highway 91 in Can Tho is being dismantled
|
Can Tho - Up to now, all the asphalt section of the O Mon bridge has been demolished, and the unit has begun demolishing the concrete section of the bridge in the middle span.
Morning in the West 27.5: Expected start date for National Highway 91 in Can Tho
|
Morning in the West 27.5: Expected start date for National Highway 91 in Can Tho; Phu Quoc tourism accelerates, preparing to welcome APEC 2027;...
Expected start date of National Highway 91 with capital of VND 7,238 billion in Can Tho
|
Can Tho - The Chairman of the People's Committee of Can Tho City requested to ensure that the site is qualified to start the National Highway 91 project, expected on August 19.
By the end of June, the National Highway 91 expansion project must disburse all VND 3,235 billion
|
Can Tho - To ensure progress and quality, by the end of June 2025, the project to upgrade and expand National Highway 91 must disburse all the capital allocated in 2025.
Reasons why the VND7,238 billion project in Can Tho cannot start construction before April 30
|
Can Tho - The project to upgrade and expand National Highway 91 with a total investment of VND 7,238 billion cannot start construction in the first quarter of 2025 due to many procedures.
VND7,238 billion project in Can Tho faces difficulties
|
Can Tho - The project to upgrade and expand National Highway 91 (section from Km0 - Km7) with a total investment of VND 7,238 billion is being urgently implemented by the city.
Can Tho resolves the backlog of the National Highway 91 expansion project
|
Can Tho - Authorities are actively resolving the outstanding issues of the National Highway 91 expansion project, including compensation payment and resettlement arrangements.
Speed up the compensation progress for a project worth over VND7,200 billion in Can Tho
|
Can Tho - Up to now, 73/101 cases have been compensated, with an amount of more than 268 billion VND.
Project of over 7,200 billion VND in Can Tho compensates people
|
Can Tho - The total compensation cost for people affected by the National Highway 91 Upgrading and Expansion Project (Km0 - Km7) this time is about 410 billion VND.
Project worth over 7,200 billion in Can Tho will start construction before April 30, 2025
|
Can Tho - The project to upgrade and expand 7km of National Highway 91, section Km0 - Km7, with a total investment of more than 7,237 billion VND, will start construction before April 30, 2025.
Waiting for compensation land price for project over 7,200 billion in Can Tho
|
Can Tho is determined in site clearance for the Project to Upgrade and Expand National Highway 91 (Km0 - Km7) to start construction as planned.
Can Tho advances more than 410 billion VND to upgrade 7km of National Highway 91
|
Can Tho - Can Tho City People's Committee has allocated more than 410 billion VND in advance capital for the project to upgrade and expand National Highway 91 (section from Km0 - Km7).
Resolving difficulties in the project of over 7,200 billion in Can Tho
|
Can Tho - The project to upgrade and expand National Highway 91 (section from Km0 - Km7), Can Tho City has a total investment of nearly 7,238 billion VND, expected to start construction in the second quarter of 2025.