Water level is approximately 62m, the largest hydroelectric reservoir in the South discharges floodwaters

HÀ ANH CHIẾN |

Dong Nai - The water level of Tri An Lake has reached approximately the safe elevation of 62m. Tri An Hydropower Plant announced flood discharge with a total flow rate of 800m3/s to 1,120m3/s.

On October 22, Tri An Hydropower Company (Dong Nai Electricity Group) announced the third spillway to regulate the Tri An Hydropower reservoir.

According to the announcement, at 7:00 a.m. on October 22, the water level of Tri An Lake reached 61.77m (safe elevation is 62m).

Meanwhile, the water flow into the lake is 1,120 m3/second. It is expected that in the next 1 to 2 days, the water flow into the lake will be from 1,100 to 1,200 m3/second.

The downstream water level at the factory is 4.7m; the downstream water level of Dong Nai River at Bien Hoa hydrological station is 1.73m; the water flow through the power turbine is 800 m3/second.

Thuy dien Tri An xa lu. Anh tu lieu: HAC
Tri An Hydropower Plant releases floodwaters. Photo: HAC

Based on the fact that the water level downstream of the Dong Nai River at the Bien Hoa hydrological station has passed the peak of the high tide, is below the first alarm level and will decrease rapidly in the coming days, and at the same time, to ensure that the water level of Tri An Hydropower Reservoir does not exceed the normal water level of 62m, Tri An Hydropower Company will discharge water through the reservoir's regulating spillway at 10:00 a.m. on October 22 with the water flow through the spillway from 160 m3/s to 320 m3/s; the water flow through the power generation turbine from 640 m3/s to 800 m3/s.

Total water discharge downstream from 800 m3/s to 1,120 m3/s.

Speaking to Lao Dong reporter, Mr. Vo Tan Nhan - Director of Tri An Hydropower Company said that depending on the weather, water level of Tri An Hydropower Reservoir, water level downstream of Bien Hoa hydrological station, the company can change the water flow through the spillway from 1-2 spillways.

Tri An Hydropower Plant was inaugurated and put into operation in 1991. Currently, the plant has 4 units, with a total designed capacity of 400MW. This is the largest hydropower project in the Southern region, contributing greatly to the national grid, helping to regulate water sources for daily life, production, repelling salinity and regulating floods for downstream areas.

HÀ ANH CHIẾN
RELATED NEWS

Black Rock Lake in Ba Ria - Vung Tau will discharge floodwaters for 11 days from October 8

|

Ba Ria - Vung Tau - Heavy rain is forecast in the coming days, Da Den Lake plans to discharge floodwaters for 11 days to ensure safety.

3 hydroelectric plants in Tuyen Quang open floodgates

|

Hydroelectric plants on Lo and Gam rivers in Tuyen Quang have announced the opening of floodgates.

Bac Ha Hydropower Plant releases floodwaters tonight

|

Lao Cai - Bac Ha Hydropower Plant opened the flood control gate through the spillway of the hydropower project on the evening of September 30.

Ngan Pho riverbank landslide, people anxiously wait for "ha ba" dyke to save their houses

|

Ha Tinh - Serious landslides along the Ngan Pho River have caused dozens of households in Son Giang commune to live in anxiety, wearyly waiting for the dyke to resist the "ghost" swallowing land.

Rainfall of more than 300mm devastates many areas in Cao Bang, passenger car swept away by flood

|

Cao Bang - The prolonged heavy rain in the late afternoon of May 16 caused many areas in Ly Quoc commune to be deeply flooded and seriously landslide.

Wood workshop in Duong Lam ancient village catches fire fiercely at dawn

|

According to people's reflections, a wood workshop in the ancient village of Duong Lam area caught fire fiercely.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Black Rock Lake in Ba Ria - Vung Tau will discharge floodwaters for 11 days from October 8

Thành An |

Ba Ria - Vung Tau - Heavy rain is forecast in the coming days, Da Den Lake plans to discharge floodwaters for 11 days to ensure safety.

3 hydroelectric plants in Tuyen Quang open floodgates

Việt Bắc |

Hydroelectric plants on Lo and Gam rivers in Tuyen Quang have announced the opening of floodgates.

Bac Ha Hydropower Plant releases floodwaters tonight

Đinh Đại |

Lao Cai - Bac Ha Hydropower Plant opened the flood control gate through the spillway of the hydropower project on the evening of September 30.