Intense heat, the tunnel through the mountains of the Noi Bai - Lao Cai expressway still has red lights

Nguyên Phong |

In the harsh summer heat, workers are still clinging to the construction site, speeding up the progress of the mountain tunnel belonging to the Noi Bai - Lao Cai expressway expansion project.

The Noi Bai - Lao Cai expressway expansion project is invested by Vietnam Expressway Development Investment Corporation, with a total investment of nearly 7,700 billion VND.

According to the design, the project will expand the scale from 2 to 4 lanes with a cross-section of 24m, add a median strip, build more bridges, extend the underpass and complete the synchronous traffic safety system.

Dự án có tổng chiều dài 121km, tổng mức đầu tư gần 7.700 tỉ đồng. Ảnh: Hà Thắng
The project has a total length of 121km, total investment of nearly 7,700 billion VND. Photo: Pham Bang

In which, the 530m long Dai Viet tunnel through Lao Cai province is considered a key item, deciding the progress of the entire project.

In mid-May days, in hot weather, the tunnel entrance area is always covered with rock dust and the sound of drilling machines echoes.

Under the subsidence heat from the cliffs, workers are still continuously operating excavators, drills, reinforcing tunnel arches, and spraying concrete to prevent landslides.

Hầm Đại Việt dài khoảng 530m được xác định là điểm then chốt của dự án
Dai Viet tunnel, about 530m long, is identified as the key point of the project. Photo: Pham Bang

Each drill bit resounds continuously day and night in the heart of the mountain. Each meter of tunnel dug is the result of a tightly coordinated chain from drilling, blasting, excavating, transporting soil and rocks to spraying concrete and installing support structures.

Mr. Nguyen Van Hung - a worker in the tunnel drilling team - said that there are working shifts lasting many hours in a hot and humid environment, thick rock dust and continuous roar of machinery.

Working in the tunnel is very hot and suffocating, clothes are always soaked in sweat. Some days working through the night until morning, people are very tired, but looking at each meter of the tunnel being extended, brothers have more motivation," Mr. Hung expressed.

Từng mũi khoan thủ công trong lòng núi.
Each manual drill bit in the heart of the mountain.
Mỗi mối hàn đều phải kiểm tra kỹ, đảm bảo đúng kỹ thuật, mới chuyển sang công đoạn tiếp theo.
Each weld must be carefully checked, ensuring technical correctness, before moving to the next stage. Photo: Pham Bang

Mr. Phung Duc Tue - Construction site commander of Song Da Company 10.1 said that the unit maintains continuous construction, almost no days off to compensate for progress and ensure the tunnel opening plan on schedule.

“Construction conditions in the mountains are complex, prolonged hot weather increases labor intensity. We have to arrange flexible shifts, increase ventilation fans, drinking water, and protective equipment to ensure workers' health,” Mr. Tue said.

According to Mr. Tue, technical work is strictly controlled in each stage. After each blasting and explosion, technical teams must carefully check the geological status and stability of the tunnel wall before deploying excavation and reinforcement.

Trong điều kiện thời nắng nóng, đơn vị vẫn tổ chức thi công liên tục “3 ca, 4 kíp”.
In hot weather conditions, the unit still organizes continuous construction "3 shifts, 4 teams". Photo: Pham Bang

Mr. Tran Ngoc Hai - Deputy Director of the Northern Expressway Project Management Board (Vietnam Expressway Development Investment Corporation) - said that contractors are accelerating construction simultaneously on the entire route to ensure the goal of completing the project by the end of 2026.

The biggest difficulty currently is the complex mountainous terrain, erratic weather and pressure to both construct and ensure traffic on the expressway being operated. However, the units still maintain stable progress, especially the mountain tunnel item," Mr. Hai informed.

Đến nay, đơn vị đã khoan được khoảng 475 m trên tổng chiều dài 530 m.
To date, the unit has drilled about 475 m on a total length of 530 m. Photo: Pham Bang

After more than 6 months of implementation, the project has reached over 40% of the construction volume. On the entire route, the shape of the 4-lane road is gradually becoming clear. Many sections of the roadbed have been paved with the first asphalt layer; bridges, taluy, culverts, and drainage ditches are also being urgently completed.

Dai Viet tunnel alone has been dug about 475m on a total length of 530m so far, approaching the time of technical tunnel opening. Construction teams are being strengthened with manpower and equipment to complete the last meters of the tunnel.

Workers constructing the mountain tunnel of the Noi Bai - Lao Cai expressway.
Nguyên Phong
RELATED NEWS

Forecast of the time to end widespread heat waves in the North

|

The meteorological agency forecasts that hot weather in the North and South will end from May 16. Hot weather in the Central region is likely to last until around May 16-17.

Tightening safety at the large construction site to expand the Noi Bai - Lao Cai expressway

|

The traffic police force is tightening control and strictly handling violations to ensure safety during the construction of the Noi Bai - Lao Cai expressway expansion.

Risk of unsafety during the construction of the Noi Bai - Lao Cai expressway

|

Both constructing expansion and operating, the Noi Bai - Lao Cai expressway is facing the risk of traffic unsafety when traffic accidents continuously occur.

Gas stations in Ho Chi Minh City are ready to sell E10 gasoline

|

From May 15, gas stations in Ho Chi Minh City began switching from RON 95-V gasoline to E10 gasoline.

Buses and electric taxis in Hanoi increase rapidly

|

Clean buses running on green energy have exceeded 42%, electric taxis have reached more than 60% in just the first 4 months of 2026; many people expect the green transition process to take place faster to improve the air quality of the Capital.

After 1 month of subscriber verification, users are surprised to still receive warnings from the network operator

|

After 1 month of deploying SIM authentication, users continue to receive messages from network operators requesting confirmation of phone numbers still in their names.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Forecast of the time to end widespread heat waves in the North

LINH ANH |

The meteorological agency forecasts that hot weather in the North and South will end from May 16. Hot weather in the Central region is likely to last until around May 16-17.

Tightening safety at the large construction site to expand the Noi Bai - Lao Cai expressway

Bảo Nguyên |

The traffic police force is tightening control and strictly handling violations to ensure safety during the construction of the Noi Bai - Lao Cai expressway expansion.

Risk of unsafety during the construction of the Noi Bai - Lao Cai expressway

Bảo Nguyên |

Both constructing expansion and operating, the Noi Bai - Lao Cai expressway is facing the risk of traffic unsafety when traffic accidents continuously occur.