New Year's Day on Dong Dang - Tra Linh Highway

An Trịnh |

Cao Bang - At the Dong Dang - Tra Linh highway construction site, workers are still working hard.

The Dong Dang - Tra Linh Expressway project has a total length of 121 km, divided into two investment phases. In phase 1, the Dong Dang - Tra Linh Expressway is invested with a length of more than 93 km, starting at the Tan Thanh Border Gate intersection, Van Lang district (Lang Son), and ending at the National Highway 3 intersection in Chi Thao commune, Quang Hoa district (Cao Bang). The highlight of the project is the two tunnels through the mountains of Dong Khe and That Khe.

Phase 1 of the project has a total investment of 14,167 billion VND, invested by the consortium of Deo Ca Group Joint Stock Company - ICV Vietnam Investment and Construction Joint Stock Company - Deo Ca Transport Infrastructure Investment Joint Stock Company - Construction Joint Stock Company 568. Phase 1 is expected to be opened to traffic in 2025 and completed in 2026.

Mot goc du an nhin tu tren cao. Anh: Tan Van.
A view of the project from above. Photo: Tan Van.

In Thach An district (Cao Bang), there are 2 priority construction sites: km66+500, Don Lap village, Le Lai commune and tunnel 2 - km72, Thuy Hung commune. These construction sites have a lot of workers and high-capacity machinery.

With 99% of the land in Cao Bang province, contractors actively and urgently constructed with the spirit of "overcoming the sun, overcoming the rain", "3 shifts, 4 crews", mobilizing more than 1,000 personnel and over 370 machines and equipment to deploy 26 construction points in all categories of roads, bridges, tunnels, and culverts.

Cong nhan trong nhung ong ham xuyen nui da. Anh: Tan Van.
Workers in tunnels through rocky mountains. Photo: Tan Van.

Currently, Dong Khe tunnel has opened both tunnels, 3 months ahead of schedule. The contractor is pouring concrete for the tunnel lining, creating the roadbed inside the tunnel and installing equipment.

Having worked with Deo Ca Group for more than 2 years on large and small projects, Mr. Nguyen Van Thanh (from Ha Trung district, Thanh Hoa province) shared: "Every year, the group takes good care of the workers, so even though they have to be away from home and work through Tet, everyone is still very excited."

According to Mr. Thanh, on the first day of Tet this year, some workers are taking a temporary break, on the second day of Tet, everyone will return to their old work rhythm.

Cac cong nhan lam viec xuyen Tet. Anh: Tan Van.
Workers work through Tet. Photo: Tan Van.

After more than 2 years away from home during Tet, putting aside the joy of family reunion during the New Year, Mr. Thanh is a bit proud that his wife has taken care of everything for his 3 children at home.

Besides the encouragement from Deo Ca Group and his wife and children in his hometown, local leaders also regularly care for and encourage workers working directly at the construction site.

Previously, on January 24-25, Chairman of the Provincial People's Committee Hoang Xuan Anh and Secretary of the Cao Bang Provincial Party Committee Quan Minh Cuong visited, encouraged and gave gifts to workers who worked through Tet.

Bi thu Tinh uy Cao Bang Quan Minh Cuong tham va chuc Tet cac cong nhan lam viec xuyen Tet. Anh: Vu Tiep.
Cao Bang Provincial Party Secretary Quan Minh Cuong visits and wishes a happy new year to workers who work through Tet. Photo: Vu Tiep.

Cao Bang provincial leaders all acknowledged and commended the investor and contractor for their efforts in the construction process, ensuring the progress of the expressway project.

"In the last days of the year, our employees worked very urgently, following the spirit of 'overcoming the sun and overcoming the rain' initiated by the Prime Minister. The company also encouraged workers to stay and work through Tet to strive to open the route by the end of 2025.

Hoi ha nhung ngay dau nam moi. Anh: Tan Van.
Busy first days of the new year. Photo: Tan Van.

Regarding the workers' lives during Tet, what is at home is the same at the construction site. We organize Chung cake wrapping, peach blossoms, kumquats and traditional Tet dishes so that our brothers can enjoy the spring but not forget their duties, trying to keep up with the set schedule," said the investor representative.

An Trịnh
TIN LIÊN QUAN

Dong Dang - Tra Linh Expressway strives to open in 2025

|

99% of the land for the Dong Dang - Tra Linh expressway project has been handed over in Cao Bang and Lang Son provinces. Currently, contractors are urgently implementing construction at the site.

The first tunnel on Dong Dang - Tra Linh highway takes shape

|

Cao Bang - The government and a consortium of investors have just held a ceremony to open the Dong Khe tunnel on the Dong Dang - Tra Linh expressway project.

With increased capital, how is the Dong Dang - Tra Linh expressway being built

|

The two localities through which the expressway passes are speeding up the process of site clearance and related procedures to serve the project's construction.

Health status of 2 survivors in the accident that killed 7 people in Nam Dinh

|

Nam Dinh - The health of the two lucky survivors of the serious accident on the second day of Tet in Nam Dinh has basically stabilized.

Wrong weather forecast will be fined up to 100 million VND from 1.2

|

The maximum fine for making incorrect weather forecasts is 50 million VND for individuals and 100 million VND for organizations.

Two black boxes found in plane crash in the US

|

Both black boxes of the American Airlines plane have been found, according to the latest news about the collision between a commercial plane and a military helicopter in the US on January 29.

Dong Dang - Tra Linh Expressway strives to open in 2025

Khánh Linh |

99% of the land for the Dong Dang - Tra Linh expressway project has been handed over in Cao Bang and Lang Son provinces. Currently, contractors are urgently implementing construction at the site.

The first tunnel on Dong Dang - Tra Linh highway takes shape

Tân Văn |

Cao Bang - The government and a consortium of investors have just held a ceremony to open the Dong Khe tunnel on the Dong Dang - Tra Linh expressway project.

With increased capital, how is the Dong Dang - Tra Linh expressway being built

Tân Văn |

The two localities through which the expressway passes are speeding up the process of site clearance and related procedures to serve the project's construction.