With increased capital, how is the Dong Dang - Tra Linh expressway being built

Tân Văn |

The two localities through which the expressway passes are speeding up the process of site clearance and related procedures to serve the project's construction.

The Prime Minister has just signed Decision No. 1436/QD-TTg adjusting the investment policy of the Dong Dang (Lang Son province) - Tra Linh (Cao Bang province) Expressway Construction Investment Project under the PPP form.

The preliminary adjusted total investment for phase 1 of the Project is 14,114,781 billion VND, an increase of more than 3,000 billion VND.

The total investment for phase 2 will be calculated accurately when the start date is determined.

Phase 1 of the expressway was started by Prime Minister Pham Minh Chinh on January 1, 2024.

Cao toc Dong Dang - Tra Linh vua duoc Thu tuong chinh thuc phe duyet tang von Nha nuoc. Anh: Tan Van.
The Dong Dang - Tra Linh Expressway has just been officially approved by the Prime Minister to increase State capital. Photo: Tan Van.
Tren 99% mat bang phuc vu xay dung du an da duoc Cao Bang, Lang Son ban giao. Anh: Tan Van.
Over 99% of the land for project construction has been handed over by Cao Bang and Lang Son. Photo: Tan Van.

After nearly 11 months of implementation, according to the latest report of the Cao Bang Provincial Traffic Project Management Board, over 99.78% of the site has been handed over to investors.

On these areas, the construction unit mobilized 27 construction teams with more than 1,000 people working day and night.

According to the actual observations of the reporter at the end of November, the working atmosphere at the construction site was urgent.

At the construction site of road tunnel No. 2 on the route (in Ban Neng hamlet, Thuy Hung commune, Thach An district), workers are divided into "3 shifts, 4 shifts" to work.

"The road tunnel has 2 tunnels, with the right tube about 500m long; the left tube about 485m long. The construction unit is using modern self-propelled drilling machines to drill 2 tunnels. Every day, the unit goes about 4-6m deep into the mountain," said a representative of the construction unit.

Ben trong 2 duong ham xuyen nui da dau tien tren tuyen. Anh: Tan Van.
Inside the first two tunnels through the rocky mountains on the route. Photo: Tan Van.

The project investor consortium is aiming to open the route on schedule by the end of 2025. The Dong Dang - Tra Linh Expressway is a road project passing through the two provinces of Lang Son and Cao Bang.

According to research, up to now, the two localities have handed over 93.14km/93.35km, reaching 99.78% of the route length.

Of which, Cao Bang province handed over 41.26km/41.35km, equivalent to 99.78% of the route length; Lang Son province handed over 51.88/52km, equivalent to 99.77% of the route length.

According to information from the Cao Bang Provincial Traffic Project Management Board, some difficulties regarding site clearance, dumping sites containing excess soil and rock, and construction material mines serving the construction are being resolved.

It is known that phase 1 of the project starts at Tan Thanh border gate intersection (Van Lang district, Lang Son province). The end point is at National Highway 3 intersection (Chi Thao commune, Quang Hoa district, Cao Bang province).

When put into operation, this border province will escape the traffic "depression". After completion, the route will shorten the travel time from Cao Bang to Hanoi and vice versa from 6-7 hours to 3.5 hours.

Tân Văn
TIN LIÊN QUAN

Prime Minister inspects the first expressway through Cao Bang

|

On the afternoon of November 14, Prime Minister Pham Minh Chinh inspected the Dong Dang - Tra Linh expressway project and encouraged the construction workers.

On the construction site of the first highway through Cao Bang

|

Cao Bang - The Provincial People's Committee directed localities with expressways passing through to complete site clearance in 2024.

Fierce fire at rice husk warehouse in Dong Thap, expected to last all night

|

Dong Thap - The rice husk warehouse is burning fiercely and over a large area. Local authorities mobilized firefighting forces throughout the night to control the spread of the fire.

Dak Lak today has transformed and grown strongly

|

Dak Lak - In the period of 2021 - 2023, the province's economic growth will average 7%/year, and the economic scale will increasingly expand.

School health worker job position is "forgotten"

|

Ninh Binh - Currently, many school health officials in Ninh Binh city are still in the "support and service" group, which has affected their benefits.

Proposal to add monitoring activities for citizen reception

|

National Assembly delegates proposed adding activities to monitor citizen reception to reduce voters' petitions to the Central level.

Thai Binh Provincial Party Secretary appointed Deputy of Central Propaganda Department

|

Thai Binh Provincial Party Secretary Ngo Dong Hai was transferred and appointed to the position of Deputy Head of the Central Propaganda Department.

"3 cars in, 1 car out", parking lot violations face difficulty in finding a solution

|

Currently, many parking lots for vehicles in violation are overloaded because the owners have not come to claim them for a long time.

Prime Minister inspects the first expressway through Cao Bang

Tân Văn |

On the afternoon of November 14, Prime Minister Pham Minh Chinh inspected the Dong Dang - Tra Linh expressway project and encouraged the construction workers.

On the construction site of the first highway through Cao Bang

An Trịnh |

Cao Bang - The Provincial People's Committee directed localities with expressways passing through to complete site clearance in 2024.

Những mũi khoan đầu tiên phá núi đá, đào hầm sâu trên tuyến cao tốc Đồng Đăng - Trà Lĩnh

Tân Văn |

Liên danh nhà đầu tư đã tiến hành thi công mở cửa hầm phía Tây - đây cũng là đường hầm đầu tiên được khai mở trên tuyến cao tốc Đồng Đăng - Trà Lĩnh.