Day and night construction, completing the upgrading of the Lo Te - Rach Soi route in September 2025

Tạ Quang |

Can Tho - Contractors are maintaining 22 simultaneous construction teams at the construction site with more than 80 construction equipment, machines, etc.

The project to renovate and upgrade the Lo Te - Rach Soi route has a total investment of about 750 billion VND. The 51.5km long route, passing through Can Tho city and Kien Giang province (now An Giang province), has so far reached more than 72% of the contract value.

On August 2, My Thuan Project Management Board said that the project started on June 13, 2024 and the completion schedule according to the contract is September 2025. Currently, 100% of the road foundation recycling scraping has been completed.

Cong nhan tham nhua tren tuyen Lo Te - Rach Soi. Anh: Ban Quan ly du an My Thuan
Workers paving asphalt on the Lo Te - Rach Soi route. Photo: My Thuan Project Management Board

For the first layer of asphalt concrete pavement (C19), 45/49km is needed (reaching 91%), expected to be completed with the reinforcement of 48 culverts on the route before August 15, 2025. In addition, contractors are paving 17/49km of layer 2 concrete (C16) to reach 35% and are expected to complete before August 30, 2025.

Regarding the completion of the traffic safety system and inauguration in September 2025, meeting the contract schedule.

Cac nha thau thi cong ca ban dem. Anh: Ban Quan ly du an My Thuan
Contractors worked all night. Photo: My Thuan Project Management Board

The My Thuan Project Management Board added that contractors are currently maintaining 22 simultaneous construction teams at the construction site with more than 80 construction equipment and machines. Along with that, there are 200 technical staff, drivers and workers working continuously; organizing overtime at many levels to determined to complete the project as directed by the Prime Minister and the Minister of Construction.

Co 200 can bo ky thuat, lai may va cong nhan thi cong lien tuc tren tuyen. Anh: Ban Quan ly du an My Thuan
There are 200 technical staff, drivers and workers working continuously on the route. Photo: My Thuan Project Management Board

Regarding the solution to ensure the project is completed on schedule and with quality, My Thuan Project Management Board said that it has directed the contractor to adjust the progress and construction plan in the direction instead of constructing the "shelving" vertically, switching to priority construction to complete 1 layer of C19 asphalt concrete along the entire route and requiring completion before August 15, 2025.

Complete all 2 layers of asphalt concrete before August 30, 2025, ensuring the completion of the entire project in September 2025.

Tạ Quang
RELATED NEWS

More than 2,100 Can Tho - Ca Mau Expressway construction personnel on completion days

|

Can Tho - Despite unfavorable weather, more than 2,100 employees at the Can Tho - Ca Mau expressway construction site are still working hard.

Ky Duyen, Hoa Minzy as team captains, reveal interesting things about the 2025 Drafting Star

|

On August 2, the artists were present at the launch of the 2025 Star Enrollment Program: When the Fatherland calls our names.

Apartment prices are over 80 million VND/m2, it is difficult for people with a salary of 50 million VND/month to buy

|

Hanoi - The average selling price of apartments in Hanoi is gradually beyond the affordability of the entire middle- and high-income group.

Big fire at a match factory in Tay Ninh

|

Tay Ninh - On the evening of August 2, a major fire broke out at a match factory in Tan Hoi Industrial Cluster (Tan Hoi commune), burning down the entire factory.

Storm Gil strengthens into a hurricane, at risk of many new storms

|

Storm Gil has strengthened into a typhoon in the Pacific basin and is experiencing very active storm and tropical depression activities.

Indonesia's most intense volcano bursts out for the second consecutive day

|

Indonesia's most intense Lewotobi Laki volcano has been on the rise for the second consecutive day, creating a column of ash and volcanic material up to 18km high.

Hanoi records first death due to pig collapse

|

Hanoi recorded 7 cases of streptococcus purple, including 1 death. The health sector warns of the risk of bacteria from pigs that can be transmitted to humans.

List of enterprises expected to honor "Outstanding Enterprises for Workers" in 2025

|

The 2025 "Outstanding Enterprise for Workers" Award is a prestigious socio-political event chaired by the Vietnam General Confederation of Labor, in coordination with the Ministry of Home Affairs and the Vietnam Federation of Commerce and Industry (VCCI), assigned to Lao Dong Newspaper to directly implement.

Mặt đường hoàn trả cẩu thả sau thi công, tiềm ẩn nguy cơ tai nạn giao thông

Minh Hạnh |

Hà Nội - Sau khi thi công hạ tầng, nhiều tuyến phố tại Hà Nội được hoàn trả mặt đường sơ sài, ảnh hưởng đến an toàn giao thông và mỹ quan đô thị.

Công an Cần Thơ xác định đối tượng dùng súng bắn chim khiến đạn lạc trúng đầu người khác

Tạ Quang |

Cần Thơ - Cơ quan Công an phát hiện đối tượng Nguyễn Văn Sự cầm súng hơi xuất hiện gần hiện trường và cùng thời điểm nạn nhân bị trúng đạn.

More than 2,100 Can Tho - Ca Mau Expressway construction personnel on completion days

Tạ Quang |

Can Tho - Despite unfavorable weather, more than 2,100 employees at the Can Tho - Ca Mau expressway construction site are still working hard.