Cause of the collapse of the expressway underpass cover in Tuyen Quang

Lam Thanh |

The Tuyen Quang - Ha Giang expressway underpass cover collapse killed 1 worker.

According to information from the Management Board of Traffic Construction Investment Project of Tuyen Quang province, this unit has sent a report to the Ministry of Construction and the Provincial People's Committee about the collapse of the top of the civil traffic tunnel under package No. 20 on the evening of September 16.

Accordingly, the initial cause was determined to be the collapse of the formwork scaffolding system, leading to the collapse of the entire concrete and steel structure of the newly constructed tunnel top.

During the process of pouring reinforced concrete for the tunnel top at Km25+095 from 16:30 to 18:55. After pouring concrete, when cleaning up equipment under the tunnel, the entire scaffolding structure, formwork and reinforced concrete for the top collapsed.

Hien truong vu sap nam ham chui cao toc Tuyen Quang - Ha Giang. Anh: Viet Bac
Scene of the Tuyen Quang - Ha Giang expressway underpass cover collapse. Photo: Viet Bac

According to the drawing, the tunnel has an aperture of 6.5 x 4.5 meters. The tunnel structure is made of 30Mpa reinforced concrete, the tunnel length is 30.5 meters. The left side of the route has been completed and the formwork has been removed to move on to the construction on the right side of the route.

At the time of the incident, the construction had been completed, with sufficient strength according to the design, and the reinforced concrete formwork for the tunnel bed and the first and second reinforced concrete for the tunnel body had been dismantled. At the same time, the pouring of reinforced concrete for the tunnel top had just been completed.

The contractor for the construction package is Cuong Thinh Thi Construction Investment Group Joint Stock Company (belonging to the Joint Venture of 168 Vietnam Construction Group Joint Stock Company and Cuong Thinh Thi Construction Investment Group Joint Stock Company).

In addition to human losses, material losses include the entire volume of reinforced concrete for the tunnel top (nearly 70.5m3 of concrete; 10.7 tons of various types of steel) and the entire scaffolding system and formwork for pouring concrete for the top of the residential tunnel.

Previously, as Lao Dong Newspaper reported, at around 7:00 p.m. on September 16, the Tuyen Quang - Ha Giang expressway underpass cover at Km25+095 in Tu Quan commune (Yen Son district) collapsed when the concrete pouring had just finished. The incident left one worker dead.

Lam Thanh
RELATED NEWS

All 10 bidding packages for the longest canal renovation project in Ho Chi Minh City are behind schedule

|

Ho Chi Minh City - 10 main construction packages under the Tham Luong - Ben Cat - Nuoc Len canal renovation project are all behind schedule compared to the signed contract.

Quang Ninh provides maximum support to tourists on a burned tourist boat

|

Quang Ninh - In addition to supporting accommodation, healthcare, finance..., Quang Ninh quickly contacted embassies to support the re-issuance of passports and necessary documents.

Moment Iranian missile attacks US military base

|

The Iranian Islamic Revolutionary Guard Corps on February 28 confirmed that it had targeted many US facilities.

Live football Cong An Ha Noi vs Hoang Anh Gia Lai in round 14 of V.League

|

Live match between Hanoi Police and Hoang Anh Gia Lai in round 14 of V.League 2025-2026, taking place at 7:15 PM today (February 28).

Fire in Bo De ward, column of smoke rises tens of meters high

|

Hanoi - A fire suddenly broke out in alley 405 Bac Cau street, Bo De ward.

Officially opening the Tam Chuc Pagoda Spring Festival in 2026

|

Ninh Binh - February 28th, officially opens Tam Chuc Pagoda Spring Festival Binh Ngo 2026 with the theme "Dawn of the Buddhist realm - Tam Chuc Spring Opening".

The government plans to borrow a maximum of 969.796 billion VND, repaying 534.739 billion VND in 2026

|

In 2026, the Government's borrowing plan is a maximum of 969.796 billion VND and debt repayment is about 534.739 billion VND.

Yêu cầu giám định vụ sập nắp hầm chui cao tốc tại Tuyên Quang

Nguyễn Tùng |

Chủ tịch UBND tỉnh Tuyên Quang yêu cầu tổ chức giám định vụ sập nắp hầm chui cao tốc Tuyên Quang - Hà Giang, rà soát công tác thi công trên toàn tuyến.

Hiện trường vụ sập giàn giáo hầm chui cao tốc Tuyên Quang - Hà Giang

Lam Thanh |

Tại hiện trường là khung cảnh đổ nát sau vụ sập giàn giáo trong quá trình đổ bê tông hầm chui cao tốc Tuyên Quang - Hà Giang.

Sập giàn giáo thi công hầm chui cao tốc Tuyên Quang-Hà Giang

Lam Thanh |

Giàn giáo thi công hầm chui tuyến cao tốc Tuyên Quang - Hà Giang đoạn qua địa phận xã Tứ Quận (huyện Yên Sơn, Tuyên Quang) vừa bị sập.