Ring Road 4 contractor faces difficulties due to scarce raw materials and high prices

SÓNG HỮU |

Hanoi - Scarce raw materials and high prices have forced some bidding packages for the Ring Road 4 parallel road project in the Capital region to be constructed sparingly.

Component project 2.1 - construction of the parallel road of Ring Road 4 in Hanoi Capital region has 4 bidding packages, of which bidding package No. 10 is about 12 km long, undertaken by a consortium of 4 contractors.

Talking to a reporter from Lao Dong Newspaper, Mr. Doan Viet Thang, Commander of package No. 10 - contractor General Corporation 319, Ministry of National Defense, said that the progress of the route section undertaken by the contractor to date has reached about 60% of the volume.

The remaining 40% of the volume cannot be deployed synchronously by contractors due to a shortage of raw materials.

Construction soil and rock are mainly purchased in Phu Tho, Ninh Binh, Hung Yen... Supply is limited, while Hanoi is simultaneously implementing many large projects, so the scarcity of raw materials is inevitable" - Mr. Doan Viet Thang said.

s
Parallel road of Ring Road 4 section passing through Hanoi. Photo: Song Huu

According to Mr. Thang, the price of sand has reached nearly 400,000 VND/m3. Construction stone fluctuates around nearly 500,000 VND/m3, which is very scarce and difficult to buy. Asphalt has to be imported from abroad, the price has also increased very high.

For more than a month, the contractor has almost had no construction activities at the construction site while still having to retain workers. Material costs are increasing, the contractor is losing more and more" - Mr. Doan Viet Thang said.

According to the plan, the parallel road of Ring Road 4 will have to be completed in June 2026. However, Mr. Thang said that it is difficult to implement with the current shortage of construction materials.

s
Parallel road intersection Ring Road 4 - National Highway 32. Photo: Song Huu

The high price of raw materials and scarcity also caused the contractor, Urban Infrastructure Development Investment Corporation UDIC (package No. 10), to be slow to construct.

Mr. Nguyen Huu Tu, Commander of package No. 10 - contractor of Urban Infrastructure Development Investment Corporation UDIC, said that the contractor is currently constructing using stockpiled raw materials from before.

However, this source of raw materials is expected to run out in the next week to 10 days and the contractor is facing the risk of having to temporarily stop construction.

With the current difficult reality, Mr. Tu hopes that the investor will compensate for the price, and at the same time soon have solutions to remove difficulties and obstacles related to raw materials so that construction can be deployed synchronously throughout the bidding package.

s
A section of the parallel road of Ring Road 4 is asphalted. Photo: Song Huu

And Mr. Nguyen Hoang Hai, Commander of package No. 9 - contractor of Vietnam Import-Export and Construction Joint Stock Corporation - Vinaconex, said that the lack of raw materials has caused some packages to have to be constructed halfway or temporarily suspended while waiting for materials.

This leads to the risk of delays in the Hanoi Capital Ring Road 4 parallel road project.

Currently, Vinaconex contractor is still organizing construction with reserves of raw materials, and at the same time finding solutions to ensure supply.

Mr. Nguyen Hoang Hai said that package No. 9 currently reaches about 88% of the volume, if the supply of raw materials is guaranteed, the package will be completed in June 2026.

SÓNG HỮU
RELATED NEWS

16 construction teams accelerate the progress of the bridge over the Red River belonging to Ring Road 4

|

Hanoi - The contractor mobilized 16 construction teams to deploy bridge items across the Red River under Ring Road 4, ensuring the set schedule.

Hanoi takes over the 840 billion VND road project connecting Ring Road 4 with Ring Road 5

|

Hanoi is assigned to be the managing agency for a project of a road about 2.22km long with a total investment of 840.155 billion VND connecting Ring Road 4 with Ring Road 5.

Arbitrarily leveling, subdividing, and selling agricultural land plots in the highlands of Lang Son

|

Lang Son - Thousands of square meters of forest land and agricultural land are plowed and illegally divided into plots for sale.

Secretariat appoints personnel for the Inspection Committee of the Party Committee of Central Party Agencies

|

The Secretariat appointed the Inspection Committee of the Party Committee of Central Party Agencies for the term 2025-2030, including 9 personnel.

Stock market continues to set a new historical high

|

The stock market increased by more than 61 points and set a new peak in the first trading week of May.

16 construction teams accelerate the progress of the bridge over the Red River belonging to Ring Road 4

SÓNG HỮU |

Hanoi - The contractor mobilized 16 construction teams to deploy bridge items across the Red River under Ring Road 4, ensuring the set schedule.

Hanoi takes over the 840 billion VND road project connecting Ring Road 4 with Ring Road 5

PHẠM ĐÔNG |

Hanoi is assigned to be the managing agency for a project of a road about 2.22km long with a total investment of 840.155 billion VND connecting Ring Road 4 with Ring Road 5.

Cuộc sống của người dân ở khu tạm cư sau khi nhường đất làm Vành đai 4

Cường Ngô |

Những nơi dự án đường Vành đai 4 đi qua, người dân đều đồng thuận chủ trương thực hiện dự án. Hiện cuộc sống trong khu tạm cư cũng đã dần ổn định.