16 construction teams accelerate the progress of the bridge over the Red River belonging to Ring Road 4

SÓNG HỮU |

Hanoi - The contractor mobilized 16 construction teams to deploy bridge items across the Red River under Ring Road 4, ensuring the set schedule.

Hong Ha bridge across the Red River belongs to a public investment sub-project in Component Project 3 of the Ring Road 4 project in Hanoi Capital Region.

The project has a length of about 4.377km, crossing the Ta Hong and Huu Hong dikes, with the starting point of the route in Me Linh commune, and the ending point in O Dien commune.

The construction value of Hong Ha bridge is about 4, 273 billion VND.

s
Hong Ha bridge construction site across the Red River under Ring Road 4 Project. Photo: Song Huu
s
Barges and machinery gathered to serve the project construction. Photo: Song Huu

According to the Hanoi Traffic Construction Investment Project Management Board, to date, Me Linh and O Dien communes have handed over land to project enterprises (O Dien commune 2.908 ha, Me Linh commune 4.3 ha).

Currently, the 2 communes are continuing to coordinate to relocate underground and above-ground works within the land clearance scope.

According to Lao Dong Newspaper reporters' records at the Hong Ha bridge construction site, the contractor is actively implementing the item of drilling bored piles and making steel beams.

Many construction teams and many modern machines are under construction in all areas of the project.

s
s
Workers constructing the Hong Ha bridge item. Photo: Song Huu

The Hanoi Traffic Construction Investment Project Management Board said that it has deployed the construction of both construction packages on the entire handed-over site with 16 construction teams (package XL-NS. 01 mobilized 13 construction teams; package XL-NS. 02 mobilized 3 construction teams).

Up to now, about 600/941 bored piles have been completed. The items of foundation pits for bridge piers; concrete pouring of pier bases; steel plank pile frames for bridge piers; casting Super T beams... are being implemented by contractors.

To ensure the project progress, the Hanoi Traffic Construction Investment Project Management Board proposed that the People's Committees of Me Linh and O Dien communes accelerate the relocation of underground and above-ground works after demolition within the project scope.

According to the plan, the Hong Ha bridge across the Red River will be completed in the second quarter of 2027.

s
Hong Ha bridge across the Red River connecting Me Linh and O Dien communes (Hanoi). Photo: Song Huu

Bridges such as Hong Ha and Me So belonging to Ring Road 4, when completed, will strengthen inter-regional connectivity, shorten travel time between Hanoi and Hung Yen, Bac Ninh, Phu Tho provinces, and reduce the load on existing bridges such as Thanh Tri, Vinh Tuy, Thang Long. The new bridge system is also closely linked to ring roads and expressways, contributing to the formation of a synchronous traffic network.

For socio-economics, bridges open up opportunities to promote trade, develop industrial parks, new urban areas, reduce logistics costs, and increase competitiveness for businesses. People in riverside provinces benefit from modern infrastructure and more convenient transportation.

In particular, the construction of bridges over the Red River is also meaningful in implementing the capital's expansion planning, creating conditions for population reduction, developing satellite cities, and shaping Hanoi into a modern, multi-polar, and sustainable urban area.

SÓNG HỮU
RELATED NEWS

Dismantling works in the riverside area serving the Tu Lien bridge project

|

Hanoi - The City Infrastructure Construction Investment Project Management Board is organizing the dismantling of works in the Con River bank area to serve the Tu Lien bridge project.

Ring Road 4 parallel road project: Many bidding packages are about to be completed

|

Hanoi - The bidding packages for the Ring Road 4 parallel road project are ensuring the set progress, including one bidding package that will be completed in March.

16th National Assembly deputies candidates meet with voters in Bac Ninh

|

Candidates for National Assembly Deputies of the 16th term meet with voters at constituency No. 3, Bac Ninh province.

Prime Minister directs the planning and investment attraction of Lai Chau airport

|

The Prime Minister requested to review and study adjusting the planning of Lai Chau airport to suit the general development of the country.

Thanh Hoa Department of Education and Training concludes the case of teachers of To Hien Thanh High School correcting scores

|

Thanh Hoa - The Department of Education and Training (GDĐT) of the province has the results of inspection and verification of the case of amending semester exam scores that occurred at To Hien Thanh High School.

Stormy sea, voters in island communes in Gia Lai send petitions through screens

|

Gia Lai - Stormy sea, voter meeting at Nhon Chau island commune must be organized online. Through the screen, voters raised recommendations on infrastructure, environment, and livelihoods.

High lending interest rates, real estate investors struggle to push goods

|

Home loan interest rates are the highest in the past two years, shocking homebuyers.

Ukraine loses 1,255 soldiers in 1 day

|

Ukrainian forces have lost about 1,255 soldiers in the special military operation area on March 8.

Dismantling works in the riverside area serving the Tu Lien bridge project

HOÀI ANH |

Hanoi - The City Infrastructure Construction Investment Project Management Board is organizing the dismantling of works in the Con River bank area to serve the Tu Lien bridge project.

Dự án cầu qua sông Hồng: Trường hợp ưu tiên bố trí vị trí tái định cư thuận lợi

SÓNG HỮU |

Hà Nội - Phường Hồng Hà nêu rõ các trường hợp được ưu tiên bố trí vị trí tái định cư thuận lợi khi thu hồi đất xây cầu Tứ Liên qua sông Hồng.

Cuộc sống của người dân ở khu tạm cư sau khi nhường đất làm Vành đai 4

Cường Ngô |

Những nơi dự án đường Vành đai 4 đi qua, người dân đều đồng thuận chủ trương thực hiện dự án. Hiện cuộc sống trong khu tạm cư cũng đã dần ổn định.

Ring Road 4 parallel road project: Many bidding packages are about to be completed

SÓNG HỮU |

Hanoi - The bidding packages for the Ring Road 4 parallel road project are ensuring the set progress, including one bidding package that will be completed in March.