As of January 7, 2026, localities in Phu Tho province such as: Thanh Mieu Ward, Phuc Yen Ward, Tam Nong Commune, Van Ban Commune, Bao La Commune... have implemented bidding for a number of construction packages worth billions of VND.
In which, the project to renovate and upgrade the inter-zone Noi Danh Go Muoi traffic road in Van Ban commune, Phu Tho province is the project with the largest valued construction and installation package.
The above project was approved according to Decision No. 364/QD-UBND dated November 24, 2025 of Van Ban Commune People's Committee, the total investment of the project is nearly 20 billion VND, the Investor is Van Ban Commune Public Service Center.
According to the bidding invitation notice of the investor, Package No. 05 - Construction of the project is priced at more than 18.1 billion VND from the State budget and mobilized from other legal capital sources.
This construction package will build a road with a total length of 2,031.16m, a 20cm thick cement concrete road surface; a 15cm thick grade II crushed stone layer, and a synchronous sewer system design.
The construction time of package No. 05 is 330 days.
The project is invested with the aim of serving the management of traffic works, creating favorable conditions for goods circulation and travel of people in the area; and at the same time helping to protect the foundation and road surface; promoting the potential and advantages of traffic roads, contributing to socio-economic development, ensuring political security and social stability of people on the route.
Some other construction packages worth billions of VND were also implemented in the early days of 2026 in Phu Tho province such as:
In Phuc Yen ward, on January 7, the investor of the Luu Quy An Primary School Renovation and Repair Project, Phuc Yen ward, Phu Tho province also announced an invitation to bid for the Construction and Installation package with a price of nearly 11.9 billion VND.
In Thanh Mieu ward, on January 6, the investor of the Urban Embellishment project to welcome the new year and celebrate the Party and Spring 2026 announced the bidding invitation for Package No. 06: Construction and installation of works with a price of nearly 5.8 billion VND.
In Tam Nong commune, on January 5th, the investor of the project to renovate and upgrade rural roads from Nha Ba Temple road to Tung Son pagoda, Tam Nong commune announced the bidding invitation for Package No. 03: construction of works with a price of more than 9.2 billion VND.
In Bao La commune, on January 5th, the investor of the project to repair and renovate Ngoa hamlet and Den hamlet roads, Mai Hich commune announced the bidding invitation for Package No. 01: Construction and installation of works with a price of nearly 2.5 billion VND.
At the Tan Son Regional Health Center, on January 5th, the investor of the project "Repairing the basement of the parking lot in front of the high-quality clinic and treatment facility", relocating the medical gas pipeline and relocating the 0.4KV low voltage power system announced the bidding invitation for Package No. 03: Construction of the project with a price of nearly 1.5 billion VND.