Ninh Binh accelerates construction of a series of landslide prevention projects, protecting dykes before the rainy and storm season

Lương Hà |

Ninh Binh - A series of dike and flood control culvert projects are being urgently completed by construction units to ensure safety before the 2026 rainy and storm season.

Urgently construct a series of key disaster prevention projects

In May, on the Red River mouth dike in Giao Hoa and Giao Minh communes (Ninh Binh province), the construction atmosphere at the Con Tu and Con Nam culvert construction project took place urgently. Dozens of workers and machinery and equipment were mobilized to accelerate progress and soon complete the project before the 2026 rainy and storm season.

Accordingly, the works are built with reinforced concrete, using stainless steel valve doors, electric winch opening and closing systems, combined with reinforcement of canals, slopes and bottoms of upstream and downstream canals.

Thi công cống Cồn Tư và Cồn Năm đạt khoảng 80% khối lượng đảm bảo an toàn trước mùa mưa bão. Ảnh: Lương Hà
Construction of Con Tu and Con Nam culverts reached about 80% of the volume, ensuring safety before the rainy and storm season. Photo: Luong Ha
Cống Cồn Năm đang lát bờ kè kênh. Ảnh: Lương Hà
Con Nam culvert is paving the canal embankment. Photo: Luong Ha

Mr. Nguyen Dinh Dung - Supervisor of 2 Con Tu and Con Nam culvert projects - said that currently, the construction progress of basic items is closely following the set plan, reaching more than 80% of the volume and filling up to the flood and storm prevention elevation, 2 culvert shafts of 2 culverts have been installed. The construction site is divided into 4 construction teams.

In Hai Thinh commune, units are constructing component project No. 2 of Con Tron sea dike, Hai Thinh (Hai Thinh commune, Ninh Binh province), belonging to the Project to consolidate, complete and treat sea dike erosion in some Northern provinces (also known as the Project to consolidate, complete and treat sea dike erosion in Hai Thinh commune) with a total investment of about 500 billion VND.

According to reporters of Lao Dong Newspaper, in May, the construction of the final items is gradually being completed to ensure safety before the rainy and storm season.

The construction process of the sea dyke faces many difficulties, the construction of the underwater area depends on the tide and is calculated according to the water level. At any time, whenever the tide recedes, all personnel must focus to coordinate to quickly complete the work before the water rises," said the Commander of the sea dyke construction site of Hai Thinh commune.

Increasing the ability to prevent and combat natural disasters along the coast and rivers

According to the Ninh Binh Provincial Construction Investment Project Management Board No. 2, Con Tu culvert and Con Nam culvert belong to the project to handle landslides and infiltration of some dike and embankment sections to overcome the consequences of storm No. 3 and floods after the storm on river dikes in Nam Dinh province (old), now Ninh Binh province. When completed, the works will contribute to improving drainage capacity, serving agricultural production, reducing the risk of landslides, and at the same time protecting the safety of the Red River mouth dike and riverside residential areas.

Thi công
Construction of Hai Thinh commune sea dyke has been basically completed. Photo: Luong Ha

For the project to consolidate and complete and handle sea dike erosion in Hai Thinh commune, the project is expected to help prevent erosion, reduce waves, cause alluviation, and enhance the safety of the existing sea dike; protect residents and infrastructure inside the dike.

In addition, the project also serves disaster prevention and control, sea dike rescue in case of incidents, contributing to stabilizing people's lives and promoting socio-economic development in coastal areas.

Lương Hà
RELATED NEWS

Ninh Binh plans to spend more than 2 billion VND to support households relocating from degraded apartment buildings

|

Ninh Binh is expected to spend more than 2 billion VND to support relocation and arrange temporary accommodation for households living in two seriously degraded houses.

Slow disbursement of public investment capital, project progress in Ninh Binh is affected

|

Ninh Binh - Difficulties and obstacles in site clearance, lack of filling material sources... have affected the disbursement progress of public investment capital in Ninh Binh.

Scarce sand resources, Ninh Binh - Hai Phong expressway project faces difficulties

|

Hung Yen - The province requests to accelerate site clearance, remove materials, and promote the progress of the Ninh Binh - Hai Phong expressway.

Hanoi "races" overnight, clearing the flow before the rainy and storm season

|

Hanoi drainage workers are strengthening dredging, pumping mud and soil, and handling obstacles in the underground sewer system to prevent flooding as the rainy and storm season is approaching.

Controlling a fire at a material warehouse of a resident's house in Ho Chi Minh City

|

Ho Chi Minh City - Functional forces have controlled a fire at a material warehouse of a resident's house in Bau Bang commune.

The stock market will continue to maintain a state of stalemate

|

The stock market is entering a short-term correction phase, investors need to prioritize "health" of their portfolios rather than chasing the index's upward momentum.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

Ninh Binh plans to spend more than 2 billion VND to support households relocating from degraded apartment buildings

Lương Hà |

Ninh Binh is expected to spend more than 2 billion VND to support relocation and arrange temporary accommodation for households living in two seriously degraded houses.

Slow disbursement of public investment capital, project progress in Ninh Binh is affected

NGUYỄN TRƯỜNG |

Ninh Binh - Difficulties and obstacles in site clearance, lack of filling material sources... have affected the disbursement progress of public investment capital in Ninh Binh.

Scarce sand resources, Ninh Binh - Hai Phong expressway project faces difficulties

Mai Hương |

Hung Yen - The province requests to accelerate site clearance, remove materials, and promote the progress of the Ninh Binh - Hai Phong expressway.