The intersection worth over VND3,400 billion in the East of Ho Chi Minh City is gradually revealed

Tâm Tú |

HCMC - The An Phu intersection has an investment capital of more than VND 3,400 billion, is accelerating construction with more than 70% of the volume, expected to be put into operation before Tet.

After a long period of delay, the An Phu intersection project (HCMC) with a total capital of more than VND 3,400 billion is being accelerated by the investor and construction units.

Recorded at the large construction site on October 5, the urgent working atmosphere, with many overpass and underpass items, has gradually revealed a clear shape, promising to significantly reduce traffic pressure at the eastern gateway of the city.

Nut giao hon 3.400 ti dong dan lo hinh hai. Anh: Anh Tu
The An Phu intersection (HCMC) worth more than VND3,400 billion is gradually revealed. Photo: Anh Tu

The construction site has expanded the barrier area, with hundreds of workers and machines operating continuously. Important items such as the N2 overpass branch (right turn from Ho Chi Minh City - Long Thanh Expressway to Mai Chi Tho Street) and the HC1-02 underpass along with other overpass branches such as N3, N4 (connecting Mai Chi Tho - Dong Van Cong) are gradually taking shape.

The expansion of the barrier at the Mai Chi Tho - Dong Van Cong intersection to deploy the overpass branch forces vehicles traveling directly on Mai Chi Tho Street to divert to the temporary road. Similarly, at the intersection between Mai Chi Tho and Ho Chi Minh City - Long Thanh Expressway, the construction of the overpass also occupies a large area, making it difficult for people to move.

Hien du an da dat hon 70% khoi luong tong the. Anh: Anh Tu
Inside the construction site, workers are working busily. Photo: Anh Tu

The Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) said that after nearly three years of construction since the end of 2022, the project has reached more than 70% of the total volume. The two priority items and the high level of construction is the N2 bridge branch and the HC1-02 underpass.

The N2 bridge branch (for vehicles turning right from the Ho Chi Minh City - Long Thanh Expressway to Mai Chi Tho Street, towards Vo Nguyen Giap Street) has reached 55% of the volume. Currently, the project is being constructed simultaneously with three main points, with the goal of completion and opening to traffic on December 31, 2025.

Hien du an da dat hon 70% khoi luong tong the. Anh: Anh Tu
Currently, the project has reached more than 70% of the total volume. Photo: Anh Tu

The HC1-02 underpass is 760 m long, with a scale of 4 lanes in both directions, directly connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway with Mai Chi Tho Street (towards the Saigon River tunnel). This project has reached about 73% of the volume, with 7 construction teams operating continuously.

The Traffic Department added that from October 2025, the underpass construction progress will be further accelerated after infrastructure problems, especially the relocation and reconstruction of the D400 water pipeline and 12 power cables, are handled. The HC1-02 underpass is expected to be completed and put into operation before the Lunar New Year 2026.

The operation of the N2 bridge branch and the HC1-02 underpass is expected to help reduce traffic pressure by up to 80% at the An Phu intersection.

Nhieu hang muc dan hoan thien, nguoi dan ki vong du an som dua vao khai thac giup giam un tac giao thong qua khu vuc. Anh: Anh Tu
Many items are gradually being completed, and people expect the project to be put into operation soon to help reduce traffic congestion in the area. Photo: Anh Tu

Currently, behind the barrier is the sound of machines resounding, workers working enthusiastically. However, outside, people are still struggling to move through the intersection. Mr. Nguyen Hong Luan (residing in An Khanh ward) shared: "It is very difficult to travel here every day because of traffic jams. The road is narrowed due to the project, and the increased waiting time for lights is prolonged, causing traffic congestion and making it very difficult to move".

Cong trinh dang gap rut thi cong du kien dua vao khai thac truoc Tet. Anh: Anh Tu
The project is under urgent construction and is expected to be put into operation before Tet. Photo: Anh Tu

The An Phu intersection project plays the role of a direct connection point between Mai Chi Tho axis and the Ho Chi Minh City - Long Thanh - Dau Giay expressway, holding the key position of the eastern gateway. The completion of the entire project not only solves the current traffic pressure but is also ready to welcome a sudden increase in the number of vehicles when the Ho Chi Minh City - Long Thanh - Dau Giay expressway is expanded by the end of 2026 and Long Thanh International Airport officially goes into operation from June 2026.

Tâm Tú
RELATED NEWS

HCMC last week: The southern gateway is about to build a series of overpasses and underpasses to reduce congestion

|

HCMC - The southern gateway of HCMC is about to build a series of overpasses and underpasses; The HCMC Department of Construction has a new director after 3 months of merger,...

10 traffic projects that change the face of Ho Chi Minh City

|

HCMC - Metro No. 1, Tan Son Nhat T3 Station, Ba Son Bridge, Nguyen Van Linh - Nguyen Huu Tho underpass... are projects that have changed the face of HCMC in the past 5 years.

HCMC widens the death road more than 4 times, ending traffic jams and accidents

|

HCMC - Nguyen Duy Trinh Street will be expanded from 7 m to 30 m, people hope to end traffic jams, accidents that are constant every day.

Plan to arrange public service units in Ha Tinh

|

Ha Tinh province has just developed a plan to reorganize public service units under the management authority of the Provincial People's Committee.

Older workers struggle to find jobs

|

In the context of personnel cuts, competition in the labor market... many older workers struggle to find jobs.

HCMC last week: The southern gateway is about to build a series of overpasses and underpasses to reduce congestion

Nguyên Chân |

HCMC - The southern gateway of HCMC is about to build a series of overpasses and underpasses; The HCMC Department of Construction has a new director after 3 months of merger,...

10 traffic projects that change the face of Ho Chi Minh City

MINH QUÂN |

HCMC - Metro No. 1, Tan Son Nhat T3 Station, Ba Son Bridge, Nguyen Van Linh - Nguyen Huu Tho underpass... are projects that have changed the face of HCMC in the past 5 years.

HCMC widens the death road more than 4 times, ending traffic jams and accidents

NHƯ QUỲNH |

HCMC - Nguyen Duy Trinh Street will be expanded from 7 m to 30 m, people hope to end traffic jams, accidents that are constant every day.