The largest intersection in Ho Chi Minh City has postponed completion until the second quarter of 2026

MINH QUÂN |

HCMC - An Phu intersection has postponed the completion of the completion date to the second quarter of 2026, with the underpass and a branch of the bridge to be completed before the Lunar New Year 2026.

The Ho Chi Minh City People's Committee has just issued a document in agreement with the proposal of the Department of Construction on adjusting the implementation time of the An Phu intersection construction project to the second quarter of 2026.

According to Decision No. 869/QD-UBND dated March 28, 2022, the An Phu intersection project will be implemented in the period of 2021 - 2025.

The progress adjustment is to suit the actual construction situation, creating conditions for investors to continue to carry out acceptance, payment, settlement and completion of the remaining items in accordance with regulations.

To date, the construction value of the project has reached more than 70% of the total contract value.

The Chairman of the Ho Chi Minh City People's Committee assigned the Department of Construction to be responsible for the accuracy and legal basis of the report; at the same time, preside over the appraisal and approval in accordance with legal regulations, ensuring the implementation progress according to the adjustment plan.

The Ho Chi Minh City Traffic Construction Investment Project Management Board (investor) is required to be responsible for the accuracy and suitability of the reported data; promptly deploy the next work in accordance with the order, procedures and instructions of the city leaders.

In particular, the N2 bridge branch (right from the Ho Chi Minh City - Long Thanh - Dau Giay Expressway to Mai Chi Tho Street) must be completed before December 31, 2025.

The HC1-02 underpass (directly connecting the expressway with Mai Chi Tho Street in the direction of the Saigon River tunnel) must be completed before January 15, 2026.

Ham chui HC1-02 co ban hoan thien phan tho.  Anh: Anh Tu
The HC1-02 underpass has basically completed the rough construction. Photo: Anh Tu

Ho Chi Minh City leaders requested relevant units to strengthen management of construction quality, strictly control investment costs, avoid additional capital and waste due to prolonging project implementation time; at the same time, speed up the construction progress to complete and finalize the project according to plan.

The An Phu intersection is a key traffic project at the eastern gateway of Ho Chi Minh City, started at the end of 2022 with a total investment of more than VND 3,400 billion.

The project is built on a 3-storey scale, including a two-way underpass connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway with Mai Chi Tho Street (towards the tunnel across the Saigon River), then extending through the Mai Chi Tho - Dong Van Cong intersection.

Above, the intersection has two overpasses, one of which is Y-shaped, connecting Mai Chi Tho (towards Hanoi Highway) with Luong Dinh Cua Street through the expressway access road; one turn bridge from the expressway access road to Mai Chi Tho. On the ground, the project is organized with a central roundabout and a symbolic tower.

In particular, at the Mai Chi Tho - Dong Van Cong intersection, in addition to the underpass extending through the intersection, the project also builds two more overpasses to connect the routes.

The existing Giong Ong To Bridge on Dong Van Cong Street will also be expanded by building two parallel branches to increase traffic capacity.

Toan canh du an nut giao An Phu o cua ngo phia Dong TPHCM. Anh: Anh Tu
Overview of the An Phu intersection project at the eastern gateway of Ho Chi Minh City. Photo: Anh Tu

After more than 3 years of construction, the project has just completed some main items such as Ba Dat Bridge, Giong Ong To Bridge and HC1-01 underpass (through Mai Chi Tho - Dong Van Cong intersection).

Recently, the construction barrier at An Phu intersection has caused the eastern gateway area of Ho Chi Minh City to frequently fall into a state of prolonged congestion, greatly affecting people's travel and goods transportation.

MINH QUÂN
RELATED NEWS

The An Phu intersection must be completed immediately, it is already too congested!

|

After the press's reflection on the delay of the An Phu intersection project (HCMC), in mid-November, the construction site became bustling again.

The overpass and underpass at An Phu intersection are sprinting to complete by the end of the year

|

HCMC - In mid-November, the An Phu intersection construction site was bustling, the overpass and underpass items simultaneously accelerated, gradually taking shape.

People struggle with traffic jams at the VND3,400 billion intersection project at the gateway to Ho Chi Minh City

|

HCMC - The An Phu intersection project with a total investment of more than VND3,400 billion is slowly constructing, with barriers overflowing onto the road, causing serious congestion in the area.

Nguyen Thi Oanh equalizes a record of 15 gold medals in SEA Games athletics

|

The victory in the 3,000m final overcoming obstacles helped Nguyen Thi Oanh equal the record of 15 gold medals in the SEA Games athletics.

Updated gold price at the end of the session on December 16: Deep decrease of 1.6 million VND/tael

|

Updated gold price at the end of the session on December 16: Domestic and world gold both decreased in today's trading session.

Police exposed the tricks of drivers to avoid AI cameras

|

Hanoi - Many drivers use all kinds of methods to cover and blur their license plates to bypass the AI camera.

Accelerating site clearance, Ring Road 1 gradually emerges

|

Hanoi - The site clearance of Ring Road 1 from Hoang Cau to Voi Phuc is in the acceleration phase, with continuous machinery and openings.

Explaineration of the principal for the case of " blocking" A80 money before being arrested

|

Before being arrested for allegedly having violations related to paying money to students on the occasion of A80, the Principal of Hanoi College of Tourism affirmed that this was just a " misunderstanding".

The An Phu intersection must be completed immediately, it is already too congested!

Lê Thanh Phong |

After the press's reflection on the delay of the An Phu intersection project (HCMC), in mid-November, the construction site became bustling again.

The overpass and underpass at An Phu intersection are sprinting to complete by the end of the year

Anh Tú |

HCMC - In mid-November, the An Phu intersection construction site was bustling, the overpass and underpass items simultaneously accelerated, gradually taking shape.

People struggle with traffic jams at the VND3,400 billion intersection project at the gateway to Ho Chi Minh City

MINH QUÂN |

HCMC - The An Phu intersection project with a total investment of more than VND3,400 billion is slowly constructing, with barriers overflowing onto the road, causing serious congestion in the area.