200m connecting link in Can Tho restarted after 3 years of suspension

Tạ Quang |

Can Tho - After 3 years of suspension due to land clearance problems, the project to upgrade and expand Tran Phu Street has just restarted.

After many years of suspension due to problems in site clearance, the project to upgrade and expand Tran Phu Street (Cai Khe Ward, Can Tho City) has been officially restarted since the beginning of October 2025. Up to now, the items are being urgently deployed to complete in 2025.

Doan duong Tran Phu (TP Can Tho) nhin tu tren cao. Anh: Ta Quang
Tran Phu Street (Can Tho City) seen from above. Photo: Ta Quang

Mr. Doan Quoc Huy - Acting Director of the Land Fund Development Branch of Area 1 (Can Tho City) said that after implementing the two-level local government and receiving active support from the People's Committee of Cai Khe Ward, the work of mobilizing and propagating people has been carried out regularly and continuously. Thanks to that, the entire remaining site of the project has been cleared.

According to the reporter of Lao Dong Newspaper, the construction unit is currently expanding the roadbed and surface and coordinating with the electricity, water supply and drainage, and telecommunications sectors to relocate technical infrastructure. This is an important item, deciding the overall progress of the project.

Nhan cong, thiet bi may moc thi cong tai “nut that“. Anh: Ta Quang
Workers, construction machinery and equipment at the "bottleneck". Photo: Ta Quang

Mr. Nguyen Thanh Thai - Technical Officer of Tri Viet Construction Investment Joint Stock Company (project construction unit) said that after completing the relocation of electricity, water, telecommunication cables, etc., the contractor will focus on human resources and machinery to speed up the construction progress. And try to complete the entire project in 2025.

The project to upgrade and expand Tran Phu Street was previously invested by the People's Committee of Ninh Kieu District (now closed), with a total investment of more than 122.4 billion VND, of which the construction package was worth more than 37.3 billion VND. The project started in October 2021 and was expected to be completed in October 2022, but was delayed for about 3 years due to land clearance problems.

The restart of the project not only helps improve traffic infrastructure in the central area but also receives consensus and support from local people.

Mr. Doan Van Viet (Cai Khe ward, Can Tho city) shared that before, this road was very bad, only a short section was narrow, the rest was wide, not synchronous in appearance. Now that it has been expanded and upgraded, it is much more convenient and also more beautiful.

Sharing the same joy, Mr. Nguyen Van Em (Cai Khe ward, Can Tho city) said that in the past, the road was small, degraded, and often flooded. Every time a car or motorbike passes by, water shoots into the house. Now that the project has been restarted, everyone is happy because the roads will be spacious and convenient for travel.

The completion of the Tran Phu road project is expected to contribute to solving local flooding problems, improving traffic connectivity in the central area of Cai Khe ward and Ninh Kieu ward, creating a civilized and modern urban appearance for Can Tho city.

Tạ Quang
RELATED NEWS

Current status of Can Tho Stadium proposed to be relocated

|

Can Tho - After being renovated in 2019, Can Tho Stadium now has many items that are gradually deteriorating.

Contradictory opinions on the proposal to relocate Can Tho Stadium

|

Can Tho - The proposal to relocate Can Tho Stadium creates many conflicting opinions between commercial interests and community values.

Close-up of the road in Can Tho devastated by high tides

|

Can Tho - Many sections of the road are cracked and peeling after high tides, causing danger to people when traveling.

Union Newsletter: Localities applying the highest regional minimum wage from 2026

|

Union newsletter: Provinces and cities apply a minimum wage of 5.31 million VND from January 1, 2026; Enterprises in Ho Chi Minh City need 30,000 more workers...

The new Minister of Home Affairs will explain the issues in the draft Law on Civil Servants (amended)

|

Minister of Home Affairs Do Thanh Binh will explain and clarify a number of issues raised by National Assembly deputies in the draft Law on Civil Servants (amended).

Pokrovsk is tense, fog creates an advantage for the Russian army's advance

|

The thick fog helps the Russian army advance deeper into the strategic city of Pokrovsk, eastern Ukraine.

functioningless while teaching, a teacher in the highlands has been teaching for 20 years

|

For more than 20 years on the podium, teacher Hoang Thi Thiet (Chieng Xuan Primary and Secondary School) still maintains her passion for the profession, considering sowing in the highlands as a part of her life.

Citizens will have the right to complain about the results of consulting on merging and renaming provinces and communes

|

The Ministry of Home Affairs proposes to regulate the reception and handling of recommendations on the results of collecting public opinions on the establishment, dissolution, merger and renaming of provinces and communes.

Current status of Can Tho Stadium proposed to be relocated

Tạ Quang |

Can Tho - After being renovated in 2019, Can Tho Stadium now has many items that are gradually deteriorating.

Contradictory opinions on the proposal to relocate Can Tho Stadium

Tạ Quang |

Can Tho - The proposal to relocate Can Tho Stadium creates many conflicting opinions between commercial interests and community values.

Close-up of the road in Can Tho devastated by high tides

Tạ Quang |

Can Tho - Many sections of the road are cracked and peeling after high tides, causing danger to people when traveling.